Scheduled Deliverables
as of 2023-11-01
There are currently 25 scheduled deliverables being worked on by 16 teams
2 deliverables are scheduled to begin work by 2 team(s) within two weeks
This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.
The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.
The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.
extra analysis (click me)
There are approximately 120 devs (out of ~512, or 23%) with 241 assignments scheduled to work on 25 observable deliverables. Of those deliverables, 8% are for SQ42 exclusively, with ~41 devs (8%) scheduled for approximately 523 man-days. 8% of deliverables are shared between both projects.
7 deliverable(s) are not currently scheduled to continue work after this sprint:
- New Missions - Cargo Hauling
- New Missions - Data Heist
- New Missions - Restoration Contracts
- Origin X1
- Pyro Space Stations
- Reputation - Hostility
- Security Network V1
- EU Landing Zone 1
full-time with 16 task(s) scheduled, all of which are for SC - EU Landing Zone 2
full-time with 71 task(s) scheduled, all of which are for SC - EU PU Gameplay Feature Team
24% part-time with 50 task(s) scheduled, 29% of which are for SQ42 - EU Sandbox 1
full-time with 45 task(s) scheduled, all of which are for SC - Mission Feature Team
full-time with 88 task(s) scheduled, all of which are for SC - MTL Sandbox 1
6% part-time with 276 task(s) scheduled, all of which are for SC - NA PU Gameplay Feature Team
39% part-time with 54 task(s) scheduled, all of which are for SC - Narrative
full-time with 11 task(s) scheduled, all of which are for SC - SQ42 - Chapter Strike Team 0
55% part-time with 11 task(s) scheduled, all of which are for SQ42 - SQ42 - Chapter Strike Team 1
22% part-time with 9 task(s) scheduled, all of which are for SQ42 - SQ42 - Chapter Strike Team 2
33% part-time with 15 task(s) scheduled, all of which are for SQ42 - SQ42 - Social Strike Team
52% part-time with 21 task(s) scheduled, all of which are for SQ42 - Vehicle Content - EU
full-time with 92 task(s) scheduled, 50% of which are for SQ42 - Vehicle Content - US
9% part-time with 22 task(s) scheduled, all of which are for SC
Additional Derelict Settlements
- EU Sandbox 1
3x Art devs working on 31 tasks (250% load) thru 2023-11-05
3x Art devs working on 31 tasks (250% load) thru 2023-11-05
................................................~~~~=============...==================|==...========....
- MTL Sandbox 1
2x Design devs working on 41 tasks (97% load) thru 2023-12-14
3x Art devs working on 50 tasks (76% load) thru 2023-12-14
2x Design devs working on 41 tasks (97% load) thru 2023-12-14
3x Art devs working on 50 tasks (76% load) thru 2023-12-14
==============================.===============~~~~~~==================================|=============....
==============================.===============~~~~~~==================================|=============....
Aopoa San'tok.y?i
- Vehicle Content - US
3x Art devs working on 6 tasks (51% load) thru 2023-12-14
↳ will continue 2023-01-02 with 3x devs
1x Design dev working on 6 tasks (135% load) thru 2023-03-17
3x Art devs working on 6 tasks (51% load) thru 2023-12-14
↳ will continue 2023-01-02 with 3x devs
1x Design dev working on 6 tasks (135% load) thru 2023-03-17
======================....========================......============~~~~~.......======|=============....
======================....========================..=====================.............|.................
......................................................................................|.....========....
======================....========================..=====================.............|.................
Bounty Hunter V2
- EU Landing Zone 2
3x Art devs working on 43 tasks (69% load) thru 2023-12-14
↳ will continue 2022-11-23 with 3x devs
3x Art devs working on 43 tasks (69% load) thru 2023-12-14
↳ will continue 2022-11-23 with 3x devs
======================================================================================|=============....
- Mission Feature Team
2x Engineering devs working on 17 tasks (315% load) thru 2023-11-05
7x Design devs working on 30 tasks (159% load) thru 2023-11-05
2x Engineering devs working on 17 tasks (315% load) thru 2023-11-05
7x Design devs working on 30 tasks (159% load) thru 2023-11-05
....=================...============================......................============|==...............
....=================...................============================......============|==...............
Bug Fixing & Tech Debt
- EU PU Gameplay Feature Team
6x Engineering devs working on 2 tasks (15% load) thru 2023-11-19
↳ will continue 2021-03-02 with 6x devs
3x Design devs working on 3 tasks (21% load) thru 2023-12-14
↳ will continue 2021-03-02 with 3x devs
6x Engineering devs working on 2 tasks (15% load) thru 2023-11-19
↳ will continue 2021-03-02 with 6x devs
3x Design devs working on 3 tasks (21% load) thru 2023-12-14
↳ will continue 2021-03-02 with 3x devs
=========================.......=============...................====~~~~~...........~~|~~~~~~...........
....=====================.......=============...................====~~~~====........~~|~~~~~========....
- EU Landing Zone 1
15x Art devs working on 11 tasks (44% load) thru 2021-03-15
5x Design devs working on 3 tasks (36% load) thru 2021-03-15
15x Art devs working on 11 tasks (44% load) thru 2021-03-15
5x Design devs working on 3 tasks (36% load) thru 2021-03-15
=...........=============...............=========...............=========.............|.============....
=...........=============...............=========...............=========.............|.============....
- EU Sandbox 1
6x Design devs working on 5 tasks (9% load) thru 2021-03-22
13x Art devs working on 7 tasks (32% load) thru 2021-03-22
6x Design devs working on 5 tasks (9% load) thru 2021-03-22
13x Art devs working on 7 tasks (32% load) thru 2021-03-22
................=====.....................======................=====.................|.=====...........
................=====.....................======................=====.................|.=====...........
Building Interiors
- MTL Sandbox 1
13x Art devs working on 62 tasks (30% load) thru 2023-12-14
↳ will continue 2021-04-01 with 13x devs
5x Design devs working on 32 tasks (30% load) thru 2023-12-14
↳ will continue 2021-03-30 with 5x devs
13x Art devs working on 62 tasks (30% load) thru 2023-12-14
↳ will continue 2021-04-01 with 13x devs
5x Design devs working on 32 tasks (30% load) thru 2023-12-14
↳ will continue 2021-03-30 with 5x devs
........................======.===============~~~~~~==================================|=============....
==============================.===============~~~~~~==================================|=============....
Freight Elevators
- EU Landing Zone 2
2x Art devs working on 16 tasks (75% load) thru 2023-12-14
↳ will continue 2023-02-15 with 2x devs
2x Art devs working on 16 tasks (75% load) thru 2023-12-14
↳ will continue 2023-02-15 with 2x devs
............=============.......................======================================|=============....
- NA PU Gameplay Feature Team
3x Engineering devs working on 16 tasks (36% load) thru 2023-12-14
1x Design dev working on 12 tasks (112% load) thru 2023-12-14
3x Engineering devs working on 16 tasks (36% load) thru 2023-12-14
1x Design dev working on 12 tasks (112% load) thru 2023-12-14
....................................................~~~~~~~~~~~~~~~~~~~~~~~~==========|=============....
....................................................================~~~~~~~~==========|=============....
New Missions - Cargo Hauling
(Scheduled work ending soon!)
- Mission Feature Team
2x Design devs working on 5 tasks (93% load) thru 2023-11-05
2x Design devs working on 5 tasks (93% load) thru 2023-11-05
..................................................==================......============|==...............
- Narrative
1x Design dev working on 7 tasks (130% load) thru 2023-11-09
1x Design dev working on 7 tasks (130% load) thru 2023-11-09
..............................................................========================|===..............
New Missions - Data Heist
(Scheduled work ending soon!)
- Mission Feature Team
3x Design devs working on 3 tasks (34% load) thru 2023-11-09
3x Design devs working on 3 tasks (34% load) thru 2023-11-09
........................=================...========================......============|==...............
New Missions - Restoration Contracts
(Scheduled work ending soon!)
- Mission Feature Team
2x Design devs working on 5 tasks (93% load) thru 2023-11-05
2x Design devs working on 5 tasks (93% load) thru 2023-11-05
..................................................==================......============|==...............
- Narrative
1x Design dev working on 4 tasks (171% load) thru 2023-11-09
1x Design dev working on 4 tasks (171% load) thru 2023-11-09
..............................................................................========|===..............
New Missions - Steal/Recover Cargo
- Mission Feature Team
1x Engineering dev working on 5 tasks (185% load) thru 2023-11-05
1x Engineering dev working on 5 tasks (185% load) thru 2023-11-05
..........................................................................============|==...............
..................................................==================..................|.................
New Player Experience
- EU Landing Zone 2
1x Art dev working on 12 tasks (112% load) thru 2023-12-14
↳ will continue 2022-12-07 with 1x dev
1x Art dev working on 12 tasks (112% load) thru 2023-12-14
↳ will continue 2022-12-07 with 1x dev
=====...........................................======================================|=============....
- Mission Feature Team
2x Design devs working on 5 tasks (93% load) thru 2023-11-05
2x Design devs working on 5 tasks (93% load) thru 2023-11-05
..................................................==================......============|==...............
Origin G12
- Vehicle Content - EU
2x Art devs working on 18 tasks (203% load) thru 2023-12-14
1x Design dev working on 14 tasks (315% load) thru 2023-12-14
2x Art devs working on 18 tasks (203% load) thru 2023-12-14
1x Design dev working on 14 tasks (315% load) thru 2023-12-14
..............................................................................========|=============....
..............................................................................========|=============....
Origin X1
(Scheduled work ending soon!)
- Vehicle Content - US
2x Tech Content devs working on 3 tasks (93% load) thru 2023-11-05
2x Tech Content devs working on 3 tasks (93% load) thru 2023-11-05
........................................................~~~~========~~~~~~~~~~~~~.....|.................
................................................................................======|==...............
Outpost Homestead - Independent & Outlaw
- EU Sandbox 1
12x Art devs working on 8 tasks (16% load) thru 2023-11-05
4x Design devs working on 6 tasks (36% load) thru 2023-11-05
12x Art devs working on 8 tasks (16% load) thru 2023-11-05
4x Design devs working on 6 tasks (36% load) thru 2023-11-05
==================..==========.============...~~~~~~=============...==================|==...========....
==================..==========.============...~~~~~~=============...==================|==...========....
Persistent Hangars
- NA PU Gameplay Feature Team
1x Design dev working on 12 tasks (112% load) thru 2023-12-14
2x Engineering devs working on 14 tasks (56% load) thru 2023-12-14
1x Design dev working on 12 tasks (112% load) thru 2023-12-14
2x Engineering devs working on 14 tasks (56% load) thru 2023-12-14
....................................................================~~~~~~~~==========|=============....
....................................................~~~~~~~~~~~~~~~~~~~~~~~~==========|=============....
Pyro Space Stations
(Scheduled work ending soon!)
- EU Landing Zone 1
14x Art devs working on 11 tasks (24% load) thru 2023-11-05
3x Design devs working on 5 tasks (51% load) thru 2023-11-05
14x Art devs working on 11 tasks (24% load) thru 2023-11-05
3x Design devs working on 5 tasks (51% load) thru 2023-11-05
=============...........=================.......=================.......==============|==...............
=============...........=================.......=================.......==============|==...............
Reputation - Hostility
(Scheduled work ending soon!)
- Mission Feature Team
1x Engineering dev working on 10 tasks (370% load) thru 2023-11-05
1x Engineering dev working on 10 tasks (370% load) thru 2023-11-05
..................................................==================......============|==...............
Resource Management
- EU PU Gameplay Feature Team
5x Engineering devs working on 19 tasks (51% load) thru 2023-11-05
↳ will continue 2021-01-04 with 5x devs
3x Design devs working on 21 tasks (56% load) thru 2023-12-14
↳ will continue 2022-03-29 with 3x devs
5x Engineering devs working on 19 tasks (51% load) thru 2023-11-05
↳ will continue 2021-01-04 with 5x devs
3x Design devs working on 21 tasks (56% load) thru 2023-12-14
↳ will continue 2022-03-29 with 3x devs
=====...........=====================...=========...================================~~|~~...========....
=========...............~~~~~~~~~.......====~~~~~...~~~~~~~~~~~~==========~~~~~~~~~~~~|~============....
RSI Apollo
- Vehicle Content - US
2x Design devs working on 8 tasks (73% load) thru 2023-12-14
1x Art dev working on 5 tasks (126% load) thru 2023-12-14
2x Design devs working on 8 tasks (73% load) thru 2023-12-14
1x Art dev working on 5 tasks (126% load) thru 2023-12-14
............................................................................==========|=============....
................................................................................======|=============....
RSI Polaris
- Vehicle Content - EU
8x Art devs working on 22 tasks (62% load) thru 2023-12-14
↳ will continue 2023-04-02 with 8x devs
1x Design dev working on 14 tasks (315% load) thru 2023-12-14
8x Art devs working on 22 tasks (62% load) thru 2023-12-14
↳ will continue 2023-04-02 with 8x devs
1x Design dev working on 14 tasks (315% load) thru 2023-12-14
..........................======================....======================....========|=============....
..............................................................................========|=============....
Salvage - Vehicle Munching
- EU PU Gameplay Feature Team
1x Engineering dev working on 5 tasks (154% load) thru 2023-11-05
1x Engineering dev working on 5 tasks (154% load) thru 2023-11-05
........................=========...........=====...=================...==============|==...========....
........................~~~~~...............~~~~~...~~~~~~~~~~~~~.........~~~~~~~~~~~.|.................
Security Network V1
(Scheduled work ending soon!)
- Mission Feature Team
2x Engineering devs working on 8 tasks (163% load) thru 2023-11-05
2x Engineering devs working on 8 tasks (163% load) thru 2023-11-05
............................................................................==========|==...............
SQ42 - Polishing
- SQ42 - Chapter Strike Team 0
6x Design devs working on 11 tasks (24% load) thru 2023-12-14
6x Design devs working on 11 tasks (24% load) thru 2023-12-14
........................................................................~~~~~~~~~~~~==|=============....
- SQ42 - Chapter Strike Team 1
4x Design devs working on 9 tasks (35% load) thru 2023-12-14
4x Design devs working on 9 tasks (35% load) thru 2023-12-14
........................................................................==============|=============....
- SQ42 - Chapter Strike Team 2
1x Tech Content dev working on 6 tasks (106% load) thru 2023-12-14
4x Design devs working on 9 tasks (29% load) thru 2023-12-14
1x Tech Content dev working on 6 tasks (106% load) thru 2023-12-14
4x Design devs working on 9 tasks (29% load) thru 2023-12-14
........................................................................==============|=============....
........................................................................~~~~~~~~~~~~==|=============....
- SQ42 - Social Strike Team
9x Design devs working on 14 tasks (17% load) thru 2023-12-14
2x Engineering devs working on 7 tasks (62% load) thru 2023-12-14
9x Design devs working on 14 tasks (17% load) thru 2023-12-14
2x Engineering devs working on 7 tasks (62% load) thru 2023-12-14
........................................................................~~~~~~~~~~~~==|=============....
........................................................................==============|=============....
SQ42 - Vehicle Support
- Vehicle Content - EU
4x Design devs working on 13 tasks (73% load) thru 2023-12-14
↳ will continue 2021-04-18 with 4x devs
5x Art devs working on 11 tasks (50% load) thru 2023-12-14
↳ will continue 2021-03-14 with 5x devs
4x Design devs working on 13 tasks (73% load) thru 2023-12-14
↳ will continue 2021-04-18 with 4x devs
5x Art devs working on 11 tasks (50% load) thru 2023-12-14
↳ will continue 2021-03-14 with 5x devs
======================....======================....======================....========|=============....
..........................======================....======================....========|=============....
- Weapon Content Team
6x Art devs working on 3 tasks (76% load) thru 2022-09-15
6x Art devs working on 3 tasks (76% load) thru 2022-09-15
..==========================..============..========================..======~~========|=================
Underground Facilities
- MTL Sandbox 1
7x Art devs working on 59 tasks (40% load) thru 2023-12-14
3x Design devs working on 32 tasks (50% load) thru 2023-12-14
7x Art devs working on 59 tasks (40% load) thru 2023-12-14
3x Design devs working on 32 tasks (50% load) thru 2023-12-14
==============================.===============~~~~~~==================================|=============....
==============================.===============~~~~~~==================================|=============....
The following deliverables are scheduled to begin (or continue) work within two weeks
Miscellaneous Support
- Mission Feature Team
10x Design devs working on 3 tasks (8% load) thru 2021-04-04
6x Engineering devs working on 1 task (21% load) thru 2021-03-07
10x Design devs working on 3 tasks (8% load) thru 2021-04-04
6x Engineering devs working on 1 task (21% load) thru 2021-03-07
........................=================.........................======..............|.=====...........
........................============================..............======..............|.=====...........
Refinery Ships
- EU PU Gameplay Feature Team
2x Engineering devs working on 9 tasks (577% load) thru 2021-12-20
2x Design devs working on 19 tasks (449% load) thru 2023-04-24
2x Engineering devs working on 9 tasks (577% load) thru 2021-12-20
2x Design devs working on 19 tasks (449% load) thru 2023-04-24
............................=====.......=========...=====.............................|.=====...........
........................~~~~~~~~~.....................................................|.................