ShinyTracker

RSI "Progress Tracker" Delta Reports

by ShinyHobo RSS

Scheduled Deliverables

as of 2023-07-26

There are currently 56 scheduled deliverables being worked on by 33 teams

5 deliverables are scheduled to begin work by 4 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 247 devs (out of ~512, or 48%) with 505 assignments scheduled to work on 56 observable deliverables. Of those deliverables, 11% are for SQ42 exclusively, with ~65 devs (13%) scheduled for approximately 2912 man-days. 23% of deliverables are shared between both projects.

8 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:

Additional Derelict Settlements

  • EU Sandbox 1
    3x Art devs working on 9 tasks (61% load) thru 2023-08-13

................................................~~~~======|======...=====================...========....

  • MTL Sandbox 1
    2x Design devs working on 27 tasks (63% load) thru 2023-12-14
    3x Art devs working on 29 tasks (44% load) thru 2023-12-14

==============================.===============~~~~~~======|=========================================....
==============================.===============~~~~~~======|=========================================....

Aopoa San'tok.yāi

  • Vehicle Content - US
    4x Art devs working on 4 tasks (27% load) thru 2023-09-11
    1x Design dev working on 5 tasks (121% load) thru 2023-09-11

======================....========================......==|=========~~~~~.......====================....
======================....========================..======|==============...............................
..........................................................|.................................========....

AR and Map Marker System Rework

  • UI Tech Team
    3x Engineering devs working on 3 tasks (44% load) thru 2023-08-10

=============...........=============...............======|=====........................................

Arena Commander: Experimental Game Modes

  • Arena Commander Feature Team
    1x Engineering dev working on 12 tasks (114% load) thru 2023-09-20

======================..==================================|=================............................

Arena Commander: Frontend Update

  • Arena Commander Feature Team
    1x Engineering dev working on 12 tasks (114% load) thru 2023-09-20
    1x Design dev working on 12 tasks (114% load) thru 2023-09-20

........................==================================|=================............................
........................==================================|=================............................

Arena Commander: New Racetracks

  • Arena Commander Feature Team
    1x Design dev working on 12 tasks (114% load) thru 2023-09-20

........................==================================|=================............................

Argo SRV

(Scheduled work ending soon!)

  • VFX Team
    1x Art dev working on 2 tasks (128% load) thru 2023-07-26

..................................................========|=............................................

Artificial Gravity

  • EU PU Gameplay Feature Team
    1x Engineering dev working on 4 tasks (81% load) thru 2023-08-14

....................................................~~~~~~|~~~~~~.........~~~~~~~~~~~...................

ATC Service

  • Systemic Services and Tools Team
    2x Engineering devs working on 4 tasks (83% load) thru 2023-08-09

........................=============.............========|=====..........===========...................

Bounty Hunter V2

  • EU Landing Zone 2
    3x Art devs working on 29 tasks (47% load) thru 2023-12-14

==========================================================|=========================================....

  • Mission Feature Team
    6x Design devs working on 6 tasks (18% load) thru 2023-08-23

....=================...................==================|=========......===============...............
....=================...============================......|...............===============...............

  • US PU Gameplay Feature Team
    2x Art devs will work on 2 tasks (128% load) starting 2023-08-01 thru 2023-08-14

========............................~~~~..................|.=====...............=====...................

Bug Fixing & Tech Debt

  • Editor Team
    5x Engineering devs working on 3 tasks (26% load) thru 2023-08-10

=============...........=============...............======|=====........................................

  • Live Tools Team
    7x Engineering devs working on 18 tasks (16% load) thru 2023-09-28

==========================================================|===================..........................

  • US PU Gameplay Feature Team
    7x Design devs working on 13 tasks (19% load) thru 2023-12-14

========================....========~~~~=========...======|=========================================....
....................====............~~~~~~~~~~~~~.........|.....============........================....

Building Interiors

  • MTL Sandbox 1
    13x Art devs working on 27 tasks (13% load) thru 2023-12-14
    5x Design devs working on 25 tasks (23% load) thru 2023-12-14

........................======.===============~~~~~~======|=========================================....
==============================.===============~~~~~~======|=========================================....

Chapter 07

(Scheduled work ending soon!)

  • VFX Team
    1x Art dev working on 1 task (128% load) thru 2023-07-26

............................======....................====|=............................................

Chapter 12

(Scheduled work ending soon!)

  • VFX Team
    1x Art dev working on 2 tasks (128% load) thru 2023-07-26

........................==========................========|=............................................

Chapter 21

  • Vehicle Feature Team
    1x Engineering dev working on 8 tasks (325% load) thru 2023-08-14

........................................=========...======|======.......................................

Chapter 26

  • Narrative
    2x Design devs working on 3 tasks (66% load) thru 2023-08-10

..............................................~~~~..======|=====........................................

Character Work

  • Audio
    11x Audio devs working on 17 tasks (8% load) thru 2023-09-27

............................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~..........................

  • Facial Animation
    9x Animation devs working on 12 tasks (26% load) thru 2023-09-28

====================~~~~~~~~====================....======|===================..........................

  • Motion Capture Team
    9x Animation devs working on 33 tasks (14% load) thru 2023-09-28

============================================~~~~~~~~~~====|===================..........................

  • Tech Animation Team
    12x Tech Content devs working on 24 tasks (12% load) thru 2023-09-20

============================================~~~~~~~~~~====|=================............................

Entity Properties Plugin

  • Editor Team
    1x Engineering dev working on 5 tasks (104% load) thru 2023-07-27

=========...=====================...======================|=..================..........................

Fire Hazard

  • VFX Team
    3x Engineering devs working on 4 tasks (41% load) thru 2023-08-23
    3x Art devs working on 4 tasks (41% load) thru 2023-08-23

==================......==================........========|=========....................................
=========.................................................|.............................................
..................................................========|=========....................................

Freight Elevators

  • EU Landing Zone 2
    1x Art dev working on 14 tasks (131% load) thru 2023-12-14

............=============.......................==========|=========================================....

  • US PU Gameplay Feature Team
    1x Art dev working on 3 tasks (185% load) thru 2023-07-31
    3x Engineering devs working on 10 tasks (81% load) thru 2023-09-11

........============........========................======|==.............=======.......................
====================........========~~~~=====.......======|==============.===================...........
............................====..........................|.............................................

Gen12 - Renderer T1

  • Engine Team
    4x Engineering devs working on 7 tasks (56% load) thru 2023-08-24

=================.......~~~~============............======|=========....................................

  • Graphics Team
    4x Tech Content devs working on 3 tasks (26% load) thru 2023-08-14
    12x Engineering devs working on 13 tasks (38% load) thru 2023-08-14

..................................................========|======.......................................
===================.....==============.======.....========|======.......................................

HEX

  • Live Tools Team
    5x Engineering devs working on 19 tasks (23% load) thru 2023-09-28

==========================================================|===================..........................

Life Support T0

  • EU PU Gameplay Feature Team
    1x Engineering dev working on 4 tasks (81% load) thru 2023-08-14

....................................................~~~~~~|~~~~~~.........~~~~~~~~~~~...................

Map and Radar System Rework

(Scheduled work ending soon!)

  • UI Tech Team
    2x Engineering devs working on 2 tasks (69% load) thru 2023-07-27

=========...............=========...................======|=............................................

MFD Rework

(Scheduled work ending soon!)

  • Vehicle Feature Team
    8x Engineering devs working on 7 tasks (54% load) thru 2023-07-31

======================..=================...=====...======|==...........................................
~~~~~~~~~~~~~~~~~~~~~~....................................|.............................................

Miscellaneous Support

  • Editor Team
    4x Engineering devs working on 6 tasks (31% load) thru 2023-07-27
    1x Design dev working on 24 tasks (113% load) thru 2023-09-28

=========...=====================...======================|=..================..........................
==========================================================|===================..........................

Mission Manager App

  • Mission Feature Team
    1x Engineering dev working on 10 tasks (113% load) thru 2023-08-23

........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~......|.............................................
........................==================================|=========....................................

  • US PU Gameplay Feature Team
    2x Art devs working on 4 tasks (81% load) thru 2023-08-14

............................~~~~~~~~~~~~............======|======.........===========...................

mobiGlas Rework

(Scheduled work ending soon!)

  • UI Tech Team
    1x Engineering dev working on 2 tasks (139% load) thru 2023-07-27

=========...............=========...................======|=............................................

New Missions - Cargo Hauling

  • Mission Feature Team
    2x Design devs working on 4 tasks (62% load) thru 2023-08-23

..................................................========|=========......===============...............

New Missions - Data Heist

  • Mission Feature Team
    2x Design devs working on 5 tasks (53% load) thru 2023-08-23

........................=================...==============|=========......===============...............

New Missions - Restoration Contracts

  • Mission Feature Team
    2x Design devs working on 4 tasks (62% load) thru 2023-08-23

..................................................========|=========......===============...............

New Missions - Steal/Recover Cargo

  • Mission Feature Team
    1x Design dev working on 4 tasks (123% load) thru 2023-08-23

..........................................................|...............===============...............
..................................................========|=========....................................

New Player Experience

  • EU Landing Zone 2
    1x Art dev working on 12 tasks (112% load) thru 2023-12-14

=====...........................................==========|=========================================....

  • Mission Feature Team
    3x Design devs working on 5 tasks (51% load) thru 2023-08-23

..................................................========|=========......===============...............

Origin X1

  • Vehicle Content - US
    4x Art devs working on 9 tasks (38% load) thru 2023-10-08
    1x Design dev will work on 6 tasks (182% load) starting 2023-08-01 thru 2023-09-25

........................................................==|=========~~~~~~~~~~~~~.......................
..........................................................|.....................=========...............

Outpost Homestead - Independent & Outlaw

  • EU Sandbox 1
    12x Art devs working on 12 tasks (18% load) thru 2023-08-13
    4x Design devs working on 8 tasks (39% load) thru 2023-08-13

==================..==========.============...~~~~~~======|======...=====================...========....
==================..==========.============...~~~~~~======|======...=====================...========....

Persistent Streaming and Server Meshing

  • Engine Team
    1x Engineering dev working on 4 tasks (128% load) thru 2023-08-24

=================.......================............======|=========....................................

  • Game Services Team
    10x Engineering devs working on 43 tasks (14% load) thru 2023-09-28

==========================================================|===================..........................

  • Mission Feature Team
    3x Engineering devs working on 4 tasks (41% load) thru 2023-08-23

....=================.............................========|=========....................................

  • Network Team
    9x Engineering devs working on 9 tasks (19% load) thru 2023-09-28

====================~~~~~~~~====================....======|===================..........................

  • Persistent Tech Team
    4x Engineering devs working on 8 tasks (38% load) thru 2023-09-28

====================~~~~~~~~====================....======|===================..........................

Physical Damage & Breakability

  • Physics Team
    3x Engineering devs working on 4 tasks (46% load) thru 2023-08-14

===================.....==============.======.....========|======.......................................

Physics - Ropes Simulation

  • Physics Team
    1x Engineering dev working on 3 tasks (104% load) thru 2023-08-14

===================.....==============.======.....========|======.......................................

Pyro Space Stations

  • EU Landing Zone 1
    14x Art devs working on 19 tasks (41% load) thru 2023-08-13
    3x Design devs working on 7 tasks (71% load) thru 2023-08-13

=============...........=================.......==========|======.......=================...............
=============...........=================.......==========|======.......=================...............

  • VFX Team
    4x Art devs working on 5 tasks (39% load) thru 2023-08-23

..................................................========|=========....................................

Pyro System, Planet, and Mission Setup

  • Narrative
    5x Design devs working on 6 tasks (23% load) thru 2023-09-28

....................................................======|===================..........................

  • US PU Gameplay Feature Team
    3x Design devs working on 7 tasks (71% load) thru 2023-08-28

................................====~~~~~...........======|==========.....===============...............

Quantum Simulation

  • Systemic Services and Tools Team
    6x Engineering devs working on 21 tasks (35% load) thru 2023-12-14

=================================================.========|=========================================....

RaStar

  • Planet Tech Team
    4x Engineering devs working on 7 tasks (44% load) thru 2023-09-07

=====================...====================........======|=============................................

Reputation - Hostility

  • Mission Feature Team
    1x Engineering dev working on 4 tasks (123% load) thru 2023-08-23

..................................................========|=========......===============...............

Reputation - Sandbox Triggers

(Scheduled work ending soon!)

  • Mission Feature Team
    1x Engineering dev working on 2 tasks (128% load) thru 2023-07-26

..................................................========|=............................................

Resource Management

  • EU PU Gameplay Feature Team
    3x Design devs working on 15 tasks (44% load) thru 2023-12-14
    4x Engineering devs working on 13 tasks (44% load) thru 2023-11-05

=========...............~~~~~~~~~.......====~~~~~...====~~|~~~~~==========~~~~~~~~~~================....
=====...........=====================...=========...======|==============================...========....

  • Vehicle Feature Team
    5x Engineering devs working on 7 tasks (28% load) thru 2023-09-25

............................=========...............======|==================...........................

RSI Polaris

  • Vehicle Content - EU
    7x Art devs working on 25 tasks (80% load) thru 2023-09-14

..........................======================....======|===============....======================....

Salvage - Vehicle Munching

  • EU PU Gameplay Feature Team
    1x Engineering dev working on 5 tasks (152% load) thru 2023-08-28
    1x Design dev working on 4 tasks (81% load) thru 2023-08-14

........................=========...........=====...======|==========...=================...========....
........................~~~~~...............~~~~~...~~~~~~|~~~~~~.........~~~~~~~~~~~...................

SQ42 - Vehicle Support

  • Audio
    11x Audio devs working on 17 tasks (8% load) thru 2023-09-27

============================~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~..........................

  • Vehicle Content - EU
    4x Design devs working on 13 tasks (73% load) thru 2023-09-14
    5x Art devs working on 12 tasks (54% load) thru 2023-09-14

======================....======================....======|===============....======================....
..........................======================....======|===============..............................

  • Vehicle Feature Team
    7x Engineering devs working on 7 tasks (20% load) thru 2023-09-25

======================..=========================...======|==================...........................

  • VFX Team
    1x Art dev working on 4 tasks (123% load) thru 2023-08-23

..................................................========|=========....................................

TestRunner Improvements

  • Tools Team
    4x Engineering devs working on 19 tasks (29% load) thru 2023-09-28

==========================================================|===================..........................

Tumbril Storm

(Scheduled work ending soon!)

  • Vehicle Content - US
    2x Tech Content devs working on 6 tasks (385% load) thru 2023-07-31
    1x Design dev working on 4 tasks (247% load) thru 2023-07-31

........................................................==|==...........................................
..........................========================..======|==...........................................
======================....========================..=====.|.............................................

Unannounced Vehicle

  • Vehicle Content - MTL
    2x Art devs working on 15 tasks (96% load) thru 2023-10-05

..........................~~====~~~~~~~~~~~~~~~~....~~~~~~|~~~~~~~~~~~~~~~~~~~~~........................

  • VFX Team
    1x Art dev working on 2 tasks (128% load) thru 2023-07-26

..................................................========|=............................................

Unannounced Vehicle

  • Vehicle Content - EU
    4x Art devs working on 13 tasks (73% load) thru 2023-09-14

................======....======================..........|.............................................
................======....======================....======|===============....======....................

  • VFX Team
    1x Art dev will work on 2 tasks (123% load) starting 2023-07-27 thru 2023-08-23

..........................................................|=========....................................

Unannounced Vehicle

  • Vehicle Content - MTL
    2x Art devs working on 19 tasks (167% load) thru 2023-10-05

..................................==============....======|=====================........................

Underground Facilities

  • Location Concept Art
    5x Art devs working on 10 tasks (38% load) thru 2023-09-28

====================~~~~~~~~====================....======|===================..........................

  • MTL Sandbox 1
    7x Art devs working on 31 tasks (21% load) thru 2023-12-14
    3x Design devs working on 25 tasks (39% load) thru 2023-12-14

==============================.===============~~~~~~======|=========================================....
==============================.===============~~~~~~======|=========================================....

Vehicle Tractor Beams

  • Narrative
    1x Design dev working on 6 tasks (115% load) thru 2023-09-28

................=========...........................======|===================..........................

Virtual AI Service

  • Systemic Services and Tools Team
    2x Engineering devs working on 5 tasks (77% load) thru 2023-08-23

=========.........................................========|=========......===============...............


The following deliverables are scheduled to begin (or continue) work within two weeks

Chapter 05

  • VFX Team
    1x Art dev will work on 1 task (128% load) starting 2023-07-27 thru 2023-08-09

................................======....................|=====........................................

Chapter 17

  • VFX Team
    1x Art dev will work on 2 tasks (123% load) starting 2023-07-27 thru 2023-08-23

................................==========................|=========....................................

New Interdiction Scenarios

  • EU Sandbox 1
    1x Design dev will work on 2 tasks (256% load) starting 2023-07-31 thru 2023-08-13

=============.........................=====...~~~~~~......|.=====...=====...........=====...............

NPC Scheduler Service

  • Systemic Services and Tools Team
    3x Engineering devs will work on 3 tasks (62% load) starting 2023-07-27 thru 2023-08-23

....=========.............................................|=========............=========...............

Reputation - Shop Discounts

(Starting soon!)

  • Mission Feature Team
    1x Engineering dev will work on 2 tasks (123% load) starting 2023-07-27 thru 2023-08-23

..........................................................|=========....................................