RSI "Progress Tracker" Delta Reports

by ShinyHobo RSS

Scheduled Deliverables

as of 2023-06-28

There are currently 44 scheduled deliverables being worked on by 21 teams

16 deliverables are scheduled to begin work by 6 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 190 devs (out of ~512, or 37%) with 408 assignments scheduled to work on 44 observable deliverables. Of those deliverables, 23% are for SQ42 exclusively, with ~97 devs (19%) scheduled for approximately 1769 man-days. 30% of deliverables are shared between both projects.

28 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:
  • AI Content Team
    36% part-time with 74 task(s) scheduled, 71% of which are for SQ42
  • AI Tech and Feature Team
    22% part-time with 101 task(s) scheduled, 70% of which are for SQ42
  • Audio
    full-time with 23 task(s) scheduled, all of which are for SQ42
  • Editor Team
    full-time with 28 task(s) scheduled, 50% of which are for SQ42
  • EU Landing Zone 1
    full-time with 16 task(s) scheduled, all of which are for SC
  • EU Landing Zone 2
    full-time with 52 task(s) scheduled, all of which are for SC
  • EU Sandbox 1
    63% part-time with 24 task(s) scheduled, all of which are for SC
  • EU Sandbox 2
    full-time with 7 task(s) scheduled, all of which are for SC
  • Game Services Team
    20% part-time with 61 task(s) scheduled, all of which are for SC
  • Gameplay Story
    100% part-time with 83 task(s) scheduled, 88% of which are for SQ42
  • Live Tools Team
    full-time with 32 task(s) scheduled, 33% of which are for SQ42
  • Mission Feature Team
    9% part-time with 66 task(s) scheduled, 8% of which are for SQ42
  • Motion Capture Team
    4% part-time with 55 task(s) scheduled, all of which are for SQ42
  • MTL Sandbox 1
    10% part-time with 148 task(s) scheduled, all of which are for SC
  • SQ42 UI Feature Team
    full-time with 47 task(s) scheduled, 67% of which are for SQ42
  • Tech Animation Team
    22% part-time with 46 task(s) scheduled, all of which are for SQ42
  • Tools Team
    full-time with 44 task(s) scheduled, 50% of which are for SQ42
  • UI Tech Team
    full-time with 4 task(s) scheduled, 50% of which are for SQ42
  • Weapon Feature Team
    46% part-time with 112 task(s) scheduled, 42% of which are for SQ42

Additional Derelict Settlements

  • EU Sandbox 1
    3x Art devs working on 6 tasks (45% load) thru 2023-08-13

................................................~~|~=============...=====================...========....

  • MTL Sandbox 1
    2x Design devs working on 25 tasks (58% load) thru 2023-12-14
    3x Art devs working on 26 tasks (38% load) thru 2023-12-14

==============================.===============~~~~|~================================================....
==============================.===============~~~~|~================================================....

AI - Vehicle Perception

(Scheduled work ending soon!)

  • AI Tech and Feature Team
    2x Engineering devs working on 5 tasks (154% load) thru 2023-07-02

=============...............................======|==...................................................

Asteroid Facilities

(Scheduled work ending soon!)

  • EU Sandbox 1
    3x Art devs working on 3 tasks (60% load) thru 2023-06-29

........==========..==========.============...~~~~|~....................................................

Bounty Hunter V2

  • EU Landing Zone 2
    3x Art devs working on 27 tasks (44% load) thru 2023-12-14

==================================================|=================================================....

  • Mission Feature Team
    6x Design devs working on 6 tasks (18% load) thru 2023-08-23
    2x Engineering devs working on 6 tasks (54% load) thru 2023-06-29

....=================...................==========|=================......===============...............
....=================...==========================|=......................===============...............

Bug Fixing & Tech Debt

  • AI Tech and Feature Team
    11x Engineering devs working on 4 tasks (22% load) thru 2023-07-02

............=========================.......======|==...................................................

  • Live Tools Team
    6x Engineering devs working on 13 tasks (20% load) thru 2023-07-02

==================================================|==...................................................

  • US PU Gameplay Feature Team
    7x Design devs will work on 12 tasks (18% load) starting 2023-07-04 thru 2023-12-14

========================....========~~~~=========.|.================================================....

Building Interiors

  • MTL Sandbox 1
    13x Art devs working on 22 tasks (10% load) thru 2023-12-14
    5x Design devs working on 24 tasks (22% load) thru 2023-12-14

........................======.===============~~~~|~================================================....
==============================.===============~~~~|~================================================....

Chapter 04

(Scheduled work ending soon!)

  • AI Content Team
    7x Design devs working on 23 tasks (28% load) thru 2023-07-02

========================================~~~~======|==...................................................

  • Gameplay Story
    5x Animation devs working on 16 tasks (39% load) thru 2023-07-03

................................~~~~~~~~~~~~~~~~~~|~~...................................................

  • SQ42 UI Feature Team
    1x Art dev working on 9 tasks (155% load) thru 2023-07-02

........................==========================|==...................................................

Chapter 08

(Scheduled work ending soon!)

  • Gameplay Story
    5x Animation devs working on 11 tasks (68% load) thru 2023-07-03

............................................~~~~~~|~~...................................................

Chapter 10

(Scheduled work ending soon!)

  • Gameplay Story
    5x Animation devs working on 13 tasks (39% load) thru 2023-07-03

....................................~~~~~~~~~~~~~~|~~...................................................

Chapter 12

(Scheduled work ending soon!)

  • AI Content Team
    6x Design devs working on 11 tasks (75% load) thru 2023-07-02

====~~~~=====...~~~~~...~~~~~...........==========|==...................................................

Chapter 13

(Scheduled work ending soon!)

  • Gameplay Story
    5x Animation devs working on 13 tasks (39% load) thru 2023-07-03

....................................~~~~~~~~~~~~~~|~~...................................................

Chapter 21

  • AI Content Team
    7x Design devs working on 6 tasks (20% load) thru 2023-07-02

........~~~~============~~~~~~~~~~~~~...~~~~======|==...................................................

  • Vehicle Feature Team
    1x Engineering dev will work on 7 tasks (285% load) starting 2023-07-04 thru 2023-08-14

........................................=========.|.=============.......................................

Chapter 26

(Scheduled work ending soon!)

  • Gameplay Story
    4x Animation devs working on 8 tasks (30% load) thru 2023-07-03

~~~~~~~~~...........................~~~~~~~~~~~~~~|~~...................................................

  • SQ42 UI Feature Team
    2x Art devs working on 7 tasks (106% load) thru 2023-07-02

....................................==============|==...................................................

Chapter 27

(Scheduled work ending soon!)

  • Gameplay Story
    4x Animation devs working on 16 tasks (48% load) thru 2023-07-03

................................~~~~~~~~~~~~~~~~~~|~~...................................................

Character Work

(Scheduled work ending soon!)

  • AI Tech and Feature Team
    7x Engineering devs working on 36 tasks (47% load) thru 2023-07-02
    3x Animation devs working on 21 tasks (64% load) thru 2023-07-02
    1x Design dev working on 22 tasks (69% load) thru 2023-07-02

==================================================|==...................................................
==================================================|==...................................................
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~...................................................

  • Motion Capture Team
    9x Animation devs working on 55 tasks (31% load) thru 2023-07-04

==================================================|==...................................................

  • Tech Animation Team
    12x Tech Content devs working on 46 tasks (31% load) thru 2023-07-05

==================================================|===..................................................

Cutting T2

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 16 tasks (152% load) thru 2023-06-29

==============================.===================|=....................................................

Disarray Ammunition

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 16 tasks (460% load) thru 2023-06-29

..........................................~~~~~~~~|~....................................................

Distortion Propagation

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 11 tasks (306% load) thru 2023-06-29

..................................================|=....................................................

Entity Properties Plugin

(Scheduled work ending soon!)

  • Editor Team
    1x Engineering dev working on 6 tasks (182% load) thru 2023-07-02

=========...=====================...==============|==...................................................

Freight Elevators

  • EU Landing Zone 2
    1x Art dev working on 13 tasks (122% load) thru 2023-12-14

............=============.......................==|=================================================....

  • US PU Gameplay Feature Team
    1x Art dev will work on 2 tasks (123% load) starting 2023-07-04 thru 2023-07-31
    3x Engineering devs will work on 7 tasks (56% load) starting 2023-07-04 thru 2023-09-11

........============........========..............|.=========.............=======.......................
====================........========~~~~=====.....|.=====================.===================...........

HEX

(Scheduled work ending soon!)

  • Live Tools Team
    5x Engineering devs working on 19 tasks (35% load) thru 2023-07-02

==================================================|==...................................................

Incendiary Ammunition

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 16 tasks (460% load) thru 2023-06-29

..........................................~~~~~~~~|~....................................................

Miscellaneous Support

  • AI Content Team
    2x Tech Content devs working on 19 tasks (30% load) thru 2023-07-02
    4x Animation devs working on 15 tasks (34% load) thru 2023-07-02

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~...................................................
==================================================|==...................................................

  • Editor Team
    1x Design dev working on 18 tasks (113% load) thru 2023-07-02
    4x Engineering devs working on 4 tasks (30% load) thru 2023-07-02

==================================================|==...................................................
=========...=====================...==============|==...................................................

  • Gameplay Story
    1x Tech Content dev working on 6 tasks (60% load) thru 2023-07-03

~~~~~~~~~~~~~~~~~~~~~~~~~...~~~~~~~~~~~~~~~~~~~~~~|~~...................................................

  • Mission Feature Team
    6x Engineering devs working on 7 tasks (21% load) thru 2023-06-29

........................==========================|=..............======................=====...........
........................=================.........|...............======................=====...........

  • UI Tech Team
    4x Engineering devs working on 4 tasks (41% load) thru 2023-07-02

................=========...............==========|==...................................................

  • Weapon Feature Team
    5x Design devs working on 16 tasks (27% load) thru 2023-06-29

==============================.===================|=....................................................

Mission Manager App

  • Mission Feature Team
    1x Engineering dev working on 10 tasks (113% load) thru 2023-08-23
    1x Art dev working on 6 tasks (54% load) thru 2023-06-29

........................==========================|=================....................................
........................~~~~~~~~~~~~~~~~~~~~~~~~~~|~....................................................

  • US PU Gameplay Feature Team
    2x Art devs will work on 3 tasks (61% load) starting 2023-07-04 thru 2023-08-14

............................~~~~~~~~~~~~..........|.=============.........===========...................

mobiGlas Rework

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    2x Design devs working on 5 tasks (154% load) thru 2023-07-02
    1x Art dev working on 5 tasks (309% load) thru 2023-07-02

............................=====...........======|==...................................................
............................=====...........======|==...................................................

New Interdiction Scenarios

  • EU Sandbox 1
    1x Design dev working on 1 task (60% load) thru 2023-06-29

=============.........................=====...~~~~|~........=====...=====...........=====...............

New Missions - Data Heist

  • Mission Feature Team
    1x Design dev working on 5 tasks (107% load) thru 2023-08-23

........................=================...======|=================....................................

New Missions - Mining Resource Rush

(Scheduled work ending soon!)

  • Mission Feature Team
    1x Design dev working on 6 tasks (109% load) thru 2023-06-29

....==============......==========================|=....................................................

New Missions - Retreive Consignment

(Scheduled work ending soon!)

  • Mission Feature Team
    1x Design dev working on 6 tasks (109% load) thru 2023-06-29

........................==========================|=....................................................

New Missions - Salvage Contracts

(Scheduled work ending soon!)

  • Mission Feature Team
    1x Design dev working on 6 tasks (109% load) thru 2023-06-29

........................==========================|=....................................................
........................=====.....................|.....................................................

New Player Experience

  • EU Landing Zone 2
    1x Art dev working on 12 tasks (112% load) thru 2023-12-14

=====...........................................==|=================================================....

  • Mission Feature Team
    1x Design dev will work on 4 tasks (123% load) starting 2023-06-30 thru 2023-08-23

..................................................|=================....................................

Outpost Homestead - Independent & Outlaw

  • EU Sandbox 1
    12x Art devs working on 8 tasks (13% load) thru 2023-08-13
    4x Design devs working on 6 tasks (32% load) thru 2023-08-13

==================..==========.============...~~~~|~=============...=====================...========....
==================..==========.============...~~~~|~=============...=====================...========....

Persistent Streaming and Server Meshing

(Scheduled work ending soon!)

  • Game Services Team
    10x Engineering devs working on 61 tasks (25% load) thru 2023-07-02

==================================================|==...................................................

Plasma Ammunition

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 16 tasks (460% load) thru 2023-06-29

..........................................~~~~~~~~|~....................................................

Player Interaction Experience T2 - Visor HUD & Helmet

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    3x Design devs working on 15 tasks (86% load) thru 2023-07-02

........=====...........==========================|==...................................................
........................=========.................|.....................................................

Pyro Space Stations

  • EU Landing Zone 1
    14x Art devs working on 11 tasks (24% load) thru 2023-08-13
    3x Design devs working on 5 tasks (51% load) thru 2023-08-13

=============...........=================.......==|==============.......=================...............
=============...........=================.......==|==============.......=================...............

  • EU Sandbox 2
    1x Design dev working on 1 task (128% load) thru 2023-07-02

................................................==|==...................................................

Pyro System, Planet, and Mission Setup

  • Mission Feature Team
    1x Design dev working on 2 tasks (90% load) thru 2023-06-29

........................................==========|=....................................................

  • US PU Gameplay Feature Team
    3x Design devs will work on 5 tasks (51% load) starting 2023-07-04 thru 2023-08-28

................................~~~~~~~~~.........|.=================.....===============...............

Ship Trespass

(Scheduled work ending soon!)

  • Mission Feature Team
    1x Engineering dev working on 6 tasks (109% load) thru 2023-06-29

........................==========================|=....................................................

SQ42 - Vehicle Support

  • AI Tech and Feature Team
    1x Engineering dev working on 3 tasks (122% load) thru 2023-07-02

........................................==========|==...................................................

  • Audio
    10x Audio devs working on 23 tasks (46% load) thru 2023-07-05

==================================================|===..................................................

  • SQ42 UI Feature Team
    2x Art devs working on 6 tasks (60% load) thru 2023-07-02

............................======================|==...................................................

  • Vehicle Content - EU
    4x Design devs will work on 16 tasks (90% load) starting 2023-07-02 thru 2023-09-14
    5x Art devs will work on 14 tasks (63% load) starting 2023-07-02 thru 2023-09-14

======================....======================..|.======================....======================....
..........................======================..|.======================..............................

  • Vehicle Feature Team
    7x Engineering devs will work on 9 tasks (26% load) starting 2023-07-04 thru 2023-09-25

======================..=========================.|.=========================...........................

StarWords Improvements

(Scheduled work ending soon!)

  • Tools Team
    2x Engineering devs working on 25 tasks (78% load) thru 2023-07-02

==================================================|==...................................................

Subsumption Editor Integration

(Scheduled work ending soon!)

  • AI Tech and Feature Team
    1x Engineering dev working on 10 tasks (172% load) thru 2023-07-02

=====================...==========================|==...................................................

TestRunner Improvements

(Scheduled work ending soon!)

  • Tools Team
    3x Engineering devs working on 19 tasks (58% load) thru 2023-07-02

==================================================|==...................................................

Underground Facilities

  • EU Sandbox 2
    3x Design devs working on 2 tasks (85% load) thru 2023-07-02
    4x Art devs working on 4 tasks (128% load) thru 2023-07-02

=====...................======..................==|==...................=====...........................
=====...................======..................==|==...................=====...........................

  • MTL Sandbox 1
    7x Art devs working on 27 tasks (18% load) thru 2023-12-14
    3x Design devs working on 24 tasks (37% load) thru 2023-12-14

==============================.===============~~~~|~================================================....
==============================.===============~~~~|~================================================....

Weapon Misfire & Wear

(Scheduled work ending soon!)

  • Weapon Feature Team
    3x Engineering devs working on 21 tasks (67% load) thru 2023-06-29

==============================.===================|=....................................................


The following deliverables are scheduled to begin (or continue) work within two weeks

Aopoa San'tok.yāi

  • Vehicle Content - US
    1x Design dev will work on 5 tasks (121% load) starting 2023-07-04 thru 2023-09-11

======================....========================|.=====================...............................

Artificial Gravity

  • EU PU Gameplay Feature Team
    1x Engineering dev will work on 3 tasks (61% load) starting 2023-07-04 thru 2023-08-14

..................................................|.~~~~~~~~~~~~~.........~~~~~~~~~~~...................

ATC Service

  • Systemic Services and Tools Team
    2x Engineering devs will work on 3 tasks (63% load) starting 2023-06-30 thru 2023-08-09

........................=============.............|=============..........===========...................

Chapter 17

  • Vehicle Feature Team
    2x Engineering devs will work on 5 tasks (321% load) starting 2023-07-04 thru 2023-07-17

............========~~~~~~~~~...=================.|.=====...............................................

Life Support T0

  • EU PU Gameplay Feature Team
    1x Engineering dev will work on 3 tasks (61% load) starting 2023-07-04 thru 2023-08-14

..................................................|.~~~~~~~~~~~~~.........~~~~~~~~~~~...................

MFD Rework

  • Vehicle Feature Team
    8x Engineering devs will work on 6 tasks (46% load) starting 2023-07-04 thru 2023-07-31

======================..=================...=====.|.=========...........................................

Quantum Simulation

  • Systemic Services and Tools Team
    6x Engineering devs will work on 16 tasks (27% load) starting 2023-06-30 thru 2023-12-14

=================================================.|=================================================....

Refinery Ships

  • EU PU Gameplay Feature Team
    2x Engineering devs will work on 1 task (64% load) starting 2023-07-04 thru 2023-07-17

............................=====.......=========.|.=====...............................=====...........

Resource Management

  • EU PU Gameplay Feature Team
    4x Engineering devs will work on 11 tasks (37% load) starting 2023-07-04 thru 2023-11-05
    3x Design devs will work on 13 tasks (41% load) starting 2023-07-04 thru 2023-12-14

=====...........=====================...=========.|.=====================================...========....
=========...............~~~~~~~~~.......====~~~~~.|.====~~~~~~~~==========~~~~~~~~~~================....

  • Vehicle Feature Team
    5x Engineering devs will work on 6 tasks (24% load) starting 2023-07-04 thru 2023-09-25

............................=========.............|.=========================...........................

RSI Polaris

  • Vehicle Content - EU
    7x Art devs will work on 20 tasks (64% load) starting 2023-07-02 thru 2023-09-14

..........................======================..|.======================....======================....

Salvage - Vehicle Munching

  • EU PU Gameplay Feature Team
    1x Engineering dev will work on 4 tasks (121% load) starting 2023-07-04 thru 2023-08-28
    1x Design dev will work on 3 tasks (61% load) starting 2023-07-04 thru 2023-08-14

........................=========...........=====.|.=================...=================...========....
........................~~~~~...............~~~~~.|.~~~~~~~~~~~~~.........~~~~~~~~~~~...................

Tumbril Storm

  • Vehicle Content - US
    3x Art devs will work on 6 tasks (256% load) starting 2023-07-04 thru 2023-07-17
    1x Design dev will work on 3 tasks (185% load) starting 2023-07-04 thru 2023-07-31

======================....========================|.=====...............................................
..........................========================|.=========...........................................

Unannounced Vehicle

  • Vehicle Content - MTL
    2x Art devs will work on 17 tasks (101% load) starting 2023-07-02 thru 2023-10-05

..........................======~~~~~~~~~~~~~~~~..|.~~~~~~~~~~~~~~~~~~~~~~======........................

Unannounced Vehicle

  • Vehicle Content - EU
    4x Art devs will work on 16 tasks (90% load) starting 2023-07-02 thru 2023-09-14

................======....======================..|.======================....======....................

Unannounced Vehicle

  • Vehicle Content - MTL
    2x Art devs will work on 17 tasks (149% load) starting 2023-07-02 thru 2023-10-05

..................................==============..|.============================........................

Virtual AI Service

  • Systemic Services and Tools Team
    2x Engineering devs will work on 4 tasks (62% load) starting 2023-06-30 thru 2023-08-23

=========.........................................|=================......===============...............