ShinyTracker

RSI "Progress Tracker" Delta Reports

by ShinyHobo RSS

Scheduled Deliverables

as of 2022-11-23

There are currently 83 scheduled deliverables being worked on by 43 teams

10 deliverables are scheduled to begin work by 8 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 428 devs (out of ~512, or 84%) with 906 assignments scheduled to work on 83 observable deliverables. Of those deliverables, 35% are for SQ42 exclusively, with ~348 devs (68%) scheduled for approximately 5083 man-days. 29% of deliverables are shared between both projects.

27 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:

Aciedo Station

(Scheduled work ending soon!)

  • SQ42 Art
    4x Art devs working on 4 tasks (62% load) thru 2022-11-23

......................................................................................========|=........

Aerodynamic Control Surfaces

  • Vehicle Feature Team
    1x Engineering dev working on 9 tasks (214% load) thru 2022-12-08

..................................................................==========..================|=====....

AI - Untrained Combat

  • AI Tech and Feature Team
    2x Engineering devs working on 11 tasks (113% load) thru 2022-12-29

..................................................................................============|=========
..........==============............============................============..................|.........

AI - Vehicle Perception

  • AI Tech and Feature Team
    2x Engineering devs working on 7 tasks (87% load) thru 2022-12-15

................................................................================..============|=======..

Anvil C8R Pisces

(Scheduled work ending soon!)

  • Vehicle Feature Team
    1x Design dev working on 1 task (128% load) thru 2022-11-24

..........................................................................................====|=........

AR and Map Marker System Rework

(Scheduled work ending soon!)

  • UI Tech Team
    2x Engineering devs working on 3 tasks (227% load) thru 2022-12-01

..................................==================....================..............====....|===......

Archon

(Scheduled work ending soon!)

  • SQ42 Art
    15x Art devs working on 3 tasks (26% load) thru 2022-11-23

.==========================...........================........................==========..====|=........

Arena Commander: Classic Race Mode Overhaul

  • Arena Commander Feature Team
    1x Design dev working on 14 tasks (131% load) thru 2022-12-22
    1x Engineering dev working on 14 tasks (131% load) thru 2022-12-22

........................................................====================~~~~~~============|=========
........................................................====================~~~~~~============|=========

Argo SRV

  • Vehicle Content - EU
    4x Art devs working on 46 tasks (66% load) thru 2023-02-02

................................==============================================================|=========
................................~~~~~~~~~~~~~~~~~~....======================....==............|.........

Banu Merchantman

  • Vehicle Content - EU
    10x Art devs working on 28 tasks (28% load) thru 2023-03-16

..============~~~~~~~~==~~................======~~....~~~~~~~~~~~~~~~~~~~~~~..................|.........
..================================================..............................==============|=========

Bombs

(Scheduled work ending soon!)

  • Weapon Content Team
    2x Art devs working on 3 tasks (139% load) thru 2022-12-08

..............................................................................................|=====....

Bounty Hunter V2

  • Mission Feature Team
    3x Design devs working on 13 tasks (35% load) thru 2022-12-22

....................................................====~~~~~~~~~~~~~~~~~~~~==================|=========
............................................................................==================|.........

  • EU Landing Zone 2
    2x Art devs will work on 3 tasks (46% load) starting 2022-11-23 thru 2022-12-20

..............................................................................................|~~~~~~~~.

  • Narrative
    2x Design devs will work on 2 tasks (76% load) starting 2022-12-08 thru 2022-12-30

............................................~~~~....~~~~......................................|...======

Bug Fixing & Tech Debt

  • AI Tech and Feature Team
    10x Engineering devs working on 7 tasks (14% load) thru 2022-12-29

..............====~~~~~~................====~~~~........========....============..============|=========

  • Arena Commander Feature Team
    2x Design devs working on 20 tasks (60% load) thru 2022-12-22

..======================....================================================~~~~~~============|=========
..~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~~~~~~~~~~~~~......................................|.........

  • EU Sandbox 1
    6x Design devs working on 6 tasks (128% load) thru 2022-11-29
    13x Art devs working on 12 tasks (118% load) thru 2022-11-29

..............~~~~~~~~~...................====..........................=====...............==|==.......
..............~~~~~~~~~...................====..........................=====...............==|==.......

  • Live Tools Team
    4x Engineering devs working on 15 tasks (38% load) thru 2022-12-19

..........................====================================================================|========.

  • Mission Feature Team
    4x Engineering devs working on 4 tasks (35% load) thru 2022-12-22
    3x Design devs working on 3 tasks (49% load) thru 2022-12-22

............................................................==================..........======|=========
............................................................................................==|=========

  • Tools Team
    5x Engineering devs working on 7 tasks (29% load) thru 2022-12-29

..============================================~~~~~~~~~~~~=====================...============|=========

  • US PU Gameplay Feature Team
    5x Engineering devs working on 9 tasks (68% load) thru 2022-12-22
    5x Design devs working on 7 tasks (73% load) thru 2022-12-22
    4x Art devs working on 3 tasks (39% load) thru 2022-12-22

..................~~~~~~~~~...................====....................~~~~~~~~................|~~~~~~~~~
..............========~~~~~...................====....................========................|=========
..................====~~~~~...................====....................========................|=========

  • Engine Team
    5x Engineering devs will work on 11 tasks (147% load) starting 2022-12-04 thru 2022-12-29

.~================~~~~~~~~~.================~~~~~~~~~~~~~~=====================...............|...======

  • EU Landing Zone 1
    15x Art devs will work on 17 tasks (62% load) starting 2022-12-07 thru 2023-01-03
    5x Design devs will work on 5 tasks (62% load) starting 2022-12-07 thru 2023-01-03

..............~~~~~~~~~...................====........................======..................|...======
..............~~~~~~~~~...................====........................======..................|...======

  • Graphics Team
    10x Engineering devs will work on 20 tasks (167% load) starting 2022-12-05 thru 2022-12-25
    2x Tech Content devs will work on 4 tasks (167% load) starting 2022-12-05 thru 2022-12-25

....................=======...................========................=========...............|...======
....................~~~~~~~...................========................=========...............|...======

  • Physics Team
    4x Engineering devs will work on 6 tasks (125% load) starting 2022-12-05 thru 2022-12-25

..====================================================..................========..............|...======

  • Systemic Services and Tools Team
    6x Engineering devs will work on 10 tasks (253% load) starting 2022-12-04 thru 2022-12-15

..................=========...................====....................==========..............|...====..

  • Weapon Content Team
    7x Art devs will work on 2 tasks (119% load) starting 2022-11-27 thru 2022-12-01

..==......====............................~~..............==..................................|.==......

Building Interiors

  • Location Concept Art
    7x Art devs working on 21 tasks (28% load) thru 2022-12-30

......................................========================================================|=========

  • MTL Sandbox 1
    14x Art devs working on 14 tasks (24% load) thru 2022-12-07
    4x Design devs working on 6 tasks (36% load) thru 2022-12-07

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============........======================..================|=====....
..~~~~~~~~~~~~~~~~~~~~~...............................======================..================|=====....

Chapter 01

  • AI Content Team
    3x Design devs working on 6 tasks (58% load) thru 2022-12-01

..................................................................................========~~~~|===......

  • Character Tech Art
    5x Tech Content devs working on 9 tasks (57% load) thru 2022-12-01

..................................................................============....============|===......

  • Narrative
    2x Design devs working on 3 tasks (96% load) thru 2022-11-23

..............................................................................======......~~~~|~........

  • SQ42 Character Art
    4x Art devs working on 3 tasks (114% load) thru 2022-12-01

......................................................========================....========....|===......

  • SQ42 Level Design 2 - Flight
    7x Design devs working on 11 tasks (19% load) thru 2022-11-23

.=====================~~~~~~~~======================..========================================|=........

  • VFX Team
    3x Art devs working on 12 tasks (119% load) thru 2022-11-24

..............................................................................================|=........

  • SQ42 Art
    12x Art devs will work on 10 tasks (39% load) starting 2022-11-24 thru 2022-12-30

..................................................................==============..............|=========

Chapter 02

  • SQ42 Art
    4x Art devs working on 9 tasks (29% load) thru 2022-12-30

......................................................==========================......~~~~~~~~|===~~~~~~

Chapter 03

(Scheduled work ending soon!)

  • SQ42 Character Art
    1x Art dev working on 3 tasks (455% load) thru 2022-12-01

..............................................................................................|===......

Chapter 04

  • AI Content Team
    4x Design devs working on 13 tasks (81% load) thru 2022-12-15

........................................................~~~~~~~~~~~~..............============|=======..

  • AI Tech and Feature Team
    1x Engineering dev working on 6 tasks (189% load) thru 2022-12-15

......................................................................................========|=======..

  • SQ42 Character Art
    3x Art devs working on 5 tasks (71% load) thru 2022-12-15

......................................................========....============............====|=======..

  • SQ42 Level Design 3 - Social
    2x Design devs working on 2 tasks (31% load) thru 2022-11-23

..==============..............................................................~~~~~~..~~~~~~~~|~........

Chapter 05

  • Character Tech Art
    2x Tech Content devs working on 6 tasks (455% load) thru 2022-12-01

..........................................................========............................|===......

  • SQ42 Art
    7x Art devs working on 17 tasks (30% load) thru 2022-12-30

..................................................................============================|=========

  • SQ42 Character Art
    4x Art devs working on 10 tasks (62% load) thru 2022-12-15

......................................................========================....============|=======..

  • SQ42 Level Design 2 - Flight
    6x Design devs working on 2 tasks (21% load) thru 2022-11-23

..............................................................................======..========|=........

  • Tech Animation Team
    4x Tech Content devs working on 10 tasks (39% load) thru 2022-12-22

..................................................................................~~~~~~~~~~~~|~~~======

Chapter 06

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    3x Art devs working on 4 tasks (89% load) thru 2022-12-01

..........................................................................................====|===......

Chapter 07

  • Narrative
    2x Design devs working on 3 tasks (96% load) thru 2022-11-23

..............................................................................~~~~~~......~~~~|~........

  • SQ42 Level Design 2 - Flight
    4x Design devs working on 6 tasks (27% load) thru 2022-12-30

.~~~~~~~..============~~~~~~..................................................================|=========

  • SQ42 Art
    3x Art devs will work on 6 tasks (152% load) starting 2022-12-08 thru 2022-12-30

......................................................................................======..|...======

Chapter 08

(Scheduled work ending soon!)

  • SQ42 Level Design 3 - Social
    3x Design devs working on 2 tasks (41% load) thru 2022-12-07

..............................................................................~~~~~~~~~~..====|=====....

Chapter 09

(Scheduled work ending soon!)

  • Narrative
    4x Design devs working on 5 tasks (51% load) thru 2022-12-07

..............................................................................~~~~~~..========|=====....

  • SQ42 Level Design 2 - Flight
    3x Design devs working on 4 tasks (40% load) thru 2022-11-23

..............................................................................================|=........

  • VFX Team
    1x Art dev working on 4 tasks (247% load) thru 2022-11-24

......................................................................................========|=........

Chapter 10

(Scheduled work ending soon!)

  • SQ42 Level Design 1 - FPS
    1x Design dev working on 2 tasks (123% load) thru 2022-12-07

..........................................................................................====|=====....

Chapter 11

  • SQ42 Character Art
    1x Art dev working on 1 task (152% load) thru 2022-12-01

..............................................................................................|===......

  • Character Tech Art
    1x Tech Content dev will work on 1 task (152% load) starting 2022-12-04 thru 2022-12-15

..............................................................................................|...====..

  • Gameplay Story
    5x Animation devs will work on 1 task (13% load) starting 2022-11-24 thru 2022-12-07

..........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~..................................|~~~~~....

  • Narrative
    2x Design devs will work on 1 task (64% load) starting 2022-11-24 thru 2022-12-07

..............................................................................~~~~~~..........|=====....

  • SQ42 Level Design 2 - Flight
    3x Design devs will work on 2 tasks (31% load) starting 2022-11-24 thru 2022-12-30

.~~~~~~~......................................................................................|=========

Chapter 12

  • AI Content Team
    3x Design devs working on 5 tasks (71% load) thru 2022-12-15

........................................................~~~~~~~~~~~~========..............====|=======..
........................................................................====..................|.........

  • Character Tech Art
    3x Tech Content devs working on 6 tasks (63% load) thru 2022-12-15

......................................................................................========|=======..

  • Motion Capture Team
    1x Animation dev will work on 3 tasks (227% load) starting 2022-12-08 thru 2022-12-30

..............................................................................................|...======

  • Tech Animation Team
    1x Tech Content dev will work on 3 tasks (385% load) starting 2022-11-25 thru 2022-12-08

..............................................................................................|=====....

Chapter 14

  • SQ42 Art
    11x Art devs working on 41 tasks (35% load) thru 2022-12-30

......................................................========================================|=========
..........................========....................==========================..............|.........

  • SQ42 Character Art
    1x Art dev working on 5 tasks (214% load) thru 2022-12-15

..........................................................................................====|=======..

  • Narrative
    2x Design devs will work on 3 tasks (114% load) starting 2022-12-08 thru 2022-12-30

................................====..........................................................|...======

  • SQ42 Level Design 1 - FPS
    7x Design devs will work on 2 tasks (13% load) starting 2022-11-24 thru 2022-12-30

.=====================~~~~~~~~==================================================..............|=========

Chapter 15

(Scheduled work ending soon!)

  • Cinematics Team
    3x Animation devs working on 6 tasks (31% load) thru 2022-12-01

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~|~~~......
.~~~~~~~~~~~~~~~~~~~~~~~~~~.......................................................~~~~........|.........

  • Gameplay Story
    5x Animation devs working on 6 tasks (18% load) thru 2022-12-07

..............~~~~~...~~~~~~..............~~~~~~~~~~~~............................~~~~~~~~~~~~|~~~~~....

  • SQ42 Level Design 3 - Social
    3x Design devs working on 2 tasks (41% load) thru 2022-12-07

......~~~~~~~~==========..................................................................====|=====....

Chapter 16

  • Cinematics Team
    2x Animation devs working on 1 task (38% load) thru 2022-12-01

..................................................................................~~~~........|.........
..................................................................................~~~~........|~~~......

  • SQ42 Level Design 1 - FPS
    2x Design devs will work on 1 task (38% load) starting 2022-12-08 thru 2022-12-30

..............................................................................................|...======

  • SQ42 Level Design 2 - Flight
    2x Design devs will work on 1 task (38% load) starting 2022-12-08 thru 2022-12-30

..............................................................................................|...======

Chapter 17

  • Cinematics Team
    1x Animation dev working on 3 tasks (227% load) thru 2022-12-01

..............................................................................................|~~~......

  • SQ42 Art
    2x Art devs working on 14 tasks (66% load) thru 2022-12-30

......................................................========================================|=========

  • SQ42 UI Feature Team
    2x Art devs working on 5 tasks (107% load) thru 2022-12-01

......................................................................................========|===......

  • SQ42 Level Design 1 - FPS
    1x Design dev will work on 1 task (76% load) starting 2022-12-08 thru 2022-12-30

..==========..................................................................................|...======

Chapter 18

  • SQ42 Art
    4x Art devs working on 17 tasks (77% load) thru 2022-12-30

..............................................................................================|=========

  • SQ42 Level Design 1 - FPS
    4x Design devs working on 5 tasks (30% load) thru 2022-12-07

.~====~~~~~~~~~~~~~~~~~~~~~~..................................................================|=====....

  • SQ42 Level Design 2 - Flight
    2x Design devs working on 3 tasks (61% load) thru 2022-11-23

..................................................................................============|=........

  • Character Tech Art
    1x Tech Content dev will work on 3 tasks (455% load) starting 2022-12-04 thru 2022-12-15

..............................................................................................|...====..

Chapter 19

  • Gameplay Story
    5x Animation devs working on 11 tasks (12% load) thru 2022-12-07

..................~~~~~.......~~~~~~~~........~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~....
..................................~~~~........................................................|.........

  • SQ42 Art
    6x Art devs working on 6 tasks (20% load) thru 2022-12-30

..................................................................~~~~==========......~~~~~~~~|=========

  • SQ42 Level Design 1 - FPS
    5x Design devs working on 9 tasks (25% load) thru 2022-12-30

......~~~~~~~~~~~~~~~~~~~~~~..............============................========================|=========

  • SQ42 Level Design 2 - Flight
    1x Design dev working on 3 tasks (122% load) thru 2022-11-23

..................................................................................============|=........

  • Tech Animation Team
    1x Tech Content dev working on 1 task (64% load) thru 2022-11-24

..........................................................................................~~~~|~........

  • VFX Team
    1x Art dev working on 2 tasks (123% load) thru 2022-11-24

......................................................................................========|=........

  • Character Tech Art
    1x Tech Content dev will work on 1 task (152% load) starting 2022-12-04 thru 2022-12-15

..............................................................................................|...====..

Chapter 20

(Scheduled work ending soon!)

  • Cinematics Team
    3x Animation devs working on 9 tasks (47% load) thru 2022-12-01
    3x Design devs working on 6 tasks (37% load) thru 2022-12-01

.~~~~~~~~~~~~~~~~~~~~~~~~~~.......................................................~~~~~~~~~~~~|~~~......
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~~~~~~~........~~~~~~~~====|~~~......

  • Gameplay Story
    4x Animation devs working on 13 tasks (18% load) thru 2022-12-07

..............................................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~....

  • SQ42 Level Design 1 - FPS
    5x Design devs working on 5 tasks (24% load) thru 2022-12-07

......~~~~~~~~~~~~~~~~~~~~~~..................................................================|=====....

  • SQ42 Level Design 3 - Social
    1x Design dev working on 3 tasks (81% load) thru 2022-12-07

......................................................................................~~~~~~~~|=====....

Chapter 21

  • AI Content Team
    3x Design devs working on 6 tasks (58% load) thru 2022-12-15

......................................................................................====~~~~|=======..

  • SQ42 Art
    2x Art devs working on 7 tasks (108% load) thru 2022-11-23

......................................................................................~~~~~~~~|~........

  • SQ42 UI Feature Team
    1x Art dev will work on 3 tasks (455% load) starting 2022-12-04 thru 2022-12-15

..............................................................................................|...====..

Chapter 22

  • Cinematics Team
    2x Animation devs working on 5 tasks (39% load) thru 2022-12-01

..................................................................................~~~~~~~~~~~~|~~~......

  • Gameplay Story
    4x Animation devs working on 5 tasks (25% load) thru 2022-12-07

..............................................~~~~~~~~................................~~~~~~~~|~~~~~....

  • SQ42 Art
    2x Art devs working on 5 tasks (65% load) thru 2022-12-30

..............................................................................==============..|.........
......................................................................................========|=========

  • SQ42 Level Design 1 - FPS
    10x Design devs working on 8 tasks (11% load) thru 2022-12-30

......================~~~~~~..............============................========================|=========

  • SQ42 Character Art
    1x Art dev will work on 1 task (152% load) starting 2022-12-04 thru 2022-12-15

..................................................................................====........|...====..

  • SQ42 Level Design 2 - Flight
    2x Design devs will work on 2 tasks (46% load) starting 2022-11-24 thru 2022-12-30

..............................................................................................|=========

Chapter 23

(Scheduled work ending soon!)

  • Cinematics Team
    4x Animation devs working on 3 tasks (57% load) thru 2022-12-01
    2x Design devs working on 3 tasks (114% load) thru 2022-12-01

..........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~..............|~~~......
.~~~~~~~~~~~~~~~~~~~~~~~~~~...................................................................|~~~......

  • Gameplay Story
    5x Animation devs working on 11 tasks (45% load) thru 2022-12-07

..................~~~~~.......~~~~~~~~........~~~~~~~~~~~~~~..........................~~~~~~~~|~~~~~....
..................................~~~~........................................................|.........

  • SQ42 Art
    2x Art devs working on 7 tasks (108% load) thru 2022-11-23

......................................................................................~~~~~~~~|~........

  • SQ42 Level Design 3 - Social
    2x Design devs working on 5 tasks (60% load) thru 2022-12-07

..............................................................................================|=====....

  • Narrative
    1x Design dev will work on 3 tasks (385% load) starting 2022-11-24 thru 2022-12-07

..............................................................................................|=====....

Chapter 25

(Scheduled work ending soon!)

  • Gameplay Story
    4x Animation devs working on 3 tasks (48% load) thru 2022-11-23

..............................................................................~~~~~~~~~~..~~~~|~........

  • SQ42 Level Design 3 - Social
    1x Design dev working on 4 tasks (121% load) thru 2022-11-23

..............................................................................================|=........

Chapter 26

  • Cinematics Team
    2x Animation devs working on 3 tasks (50% load) thru 2022-12-01

..........................................................................................~~~~|~~~......

  • Narrative
    1x Design dev working on 1 task (128% load) thru 2022-11-23

..........................................................................................====|=........

  • SQ42 Character Art
    4x Art devs working on 6 tasks (47% load) thru 2022-12-15

......................................................................========........========|=======..

  • Gameplay Story
    4x Animation devs will work on 2 tasks (32% load) starting 2022-11-24 thru 2022-12-07

..............................................................................................|~~~~~....

  • SQ42 Level Design 1 - FPS
    9x Design devs will work on 2 tasks (10% load) starting 2022-11-24 thru 2022-12-30

.===========================..............============................==========..............|=========

  • SQ42 Level Design 3 - Social
    1x Design dev will work on 1 task (128% load) starting 2022-11-24 thru 2022-12-07

..............................................................................................|=====....

Chapter 27

  • Cinematics Team
    1x Design dev working on 3 tasks (455% load) thru 2022-12-01

..............................................................................................|===......

  • Narrative
    1x Design dev will work on 3 tasks (227% load) starting 2022-12-08 thru 2022-12-30

..............................................................................................|...======

  • SQ42 Level Design 2 - Flight
    3x Design devs will work on 2 tasks (31% load) starting 2022-11-24 thru 2022-12-30

..............................................................................................|=========

Character Work

  • Actor Feature Team
    1x Engineering dev working on 6 tasks (109% load) thru 2022-12-30

..............................................................==========......================|=========
..................................................................................==========..|.........

  • AI Content Team
    6x Animation devs working on 17 tasks (58% load) thru 2022-12-29

..======================....====================........================..........============|=========
..................======....................====..............................................|.........

  • AI Tech and Feature Team
    1x Design dev working on 8 tasks (82% load) thru 2022-12-29
    4x Engineering devs working on 6 tasks (47% load) thru 2022-12-15

..==========................========....................========..............................|.........
..................................................................................~~~~~~~~~~~~|~~~~~~~~~
..~~~~========~~~~~~........~~~~========~~~~............============..................========|=======..

  • Facial Animation
    9x Animation devs working on 26 tasks (52% load) thru 2022-12-30

....==========================================~~~~~~~~~~======================================|=========

  • Motion Capture Team
    9x Animation devs working on 29 tasks (38% load) thru 2022-12-30

......=========.......====~~~~~~~~~~~~~~~~........................========~~~~~~~~============|=========

  • Tech Animation Team
    11x Tech Content devs working on 32 tasks (49% load) thru 2022-12-22

..........~~~~~~~~~~~~~~~~~...~~~~=====...~~~~========~~~~~~~~=============...================|=========

Charge/Drain T0

(Scheduled work ending soon!)

  • Weapon Feature Team
    2x Engineering devs working on 11 tasks (95% load) thru 2022-11-23

........................................========~~~~~~~~..........============================|=........

Crusader Spirit

  • Vehicle Content - EU
    5x Art devs working on 12 tasks (54% load) thru 2022-12-15
    1x Design dev working on 8 tasks (290% load) thru 2022-12-15

................................................................................==============|=======..
........................................................................................======|=======..

Cutting T2

  • Weapon Feature Team
    1x Engineering dev working on 10 tasks (181% load) thru 2022-12-30

..............................................................................================|=========

Derelict Spaceships - Points of Interest

  • Audio
    4x Audio devs working on 3 tasks (69% load) thru 2022-12-01

..............................~~~~~~~~~~~~~~~~~~~~~~~~~~~~==......==========................==|===..====

  • MTL Sandbox 1
    4x Design devs working on 7 tasks (42% load) thru 2022-12-07
    8x Art devs working on 11 tasks (33% load) thru 2022-12-07

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============........======================..================|=====....
.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============........======================..================|=====....

Dynamic Events

  • Mission Feature Team
    4x Engineering devs working on 7 tasks (32% load) thru 2022-12-22

..========================..................................................==================|=========
..================================================..~~~~~~~~~~~~~~~~~~~~~~~~~~................|...======

Entity Properties Plugin

  • Editor Team
    1x Engineering dev working on 4 tasks (267% load) thru 2022-12-15

..=========...=========...............========~~~~~~~~~~~~=====...=========.......========....|=======..

EVA T2

  • Actor Tech Team
    2x Engineering devs working on 8 tasks (82% load) thru 2022-12-29

............................====================~~~~~~~~~~====================....============|=========

Flak Ammunition

  • Weapon Content Team
    1x Art dev working on 3 tasks (1250% load) thru 2022-11-24
    ↳ will continue 2022-12-04 with 1x dev

..............................................................................................|=..==....

Freight Elevators

  • Audio
    1x Audio dev working on 4 tasks (370% load) thru 2022-12-01

............................................................................................==|===..====

Frontier Clothing

  • Character Tech Art
    5x Tech Content devs working on 8 tasks (68% load) thru 2022-12-15

......................................========............========....========....====....====|=======..

  • SC Character Art
    15x Art devs working on 23 tasks (32% load) thru 2022-12-29

.=================================================....========================....============|=========

Gen12 - Renderer T1

(Scheduled work ending soon!)

  • Engine Team
    4x Engineering devs working on 11 tasks (86% load) thru 2022-12-01

..=================.........================..........~~~~=============...........============|===......

  • Graphics Team
    7x Engineering devs working on 10 tasks (38% load) thru 2022-12-04

..===================.....======================....====================........==============|====.....

HEX

  • Live Tools Team
    5x Engineering devs working on 55 tasks (61% load) thru 2022-12-19

..=====================...~~~~========================~~~~~~~~~~~~~~~~~~~~~~~~~~~~============|========.

Ladders T1

(Scheduled work ending soon!)

  • Actor Feature Team
    3x Animation devs working on 5 tasks (214% load) thru 2022-11-23

............................====================~~~~~~~~~~======================..........====|=........
..............................................................======..........==========......|.........

Lorville Cityscape

  • MTL Sandbox 1
    4x Art devs working on 10 tasks (60% load) thru 2022-12-07

......................................................======================..================|=====....

  • VFX Team
    1x Art dev working on 3 tasks (385% load) thru 2022-11-24

..........................................................................................====|=........

Map and Radar System Rework

  • Graphics Team
    1x Engineering dev working on 5 tasks (132% load) thru 2022-12-04

................................................................========........==============|====.....

  • SQ42 UI Feature Team
    3x Engineering devs working on 10 tasks (83% load) thru 2022-12-15
    3x Art devs will work on 3 tasks (152% load) starting 2022-12-04 thru 2022-12-15

..............................==============================================......============|=======..
..........................................==============....========..................====....|...====..

MFD Rework

  • Vehicle Feature Team
    8x Engineering devs working on 9 tasks (27% load) thru 2022-12-08

......................................................======================..================|=====....

MISC Hull C

  • Vehicle Content - EU
    2x Design devs working on 14 tasks (174% load) thru 2022-12-15

..........................................................================....==..............|.........
..............................~~~~~~~~~~~~~~~~~~~~................................============|=======..

Miscellaneous Support

  • Actor Feature Team
    3x Design devs working on 29 tasks (43% load) thru 2022-12-30
    2x Engineering devs working on 26 tasks (58% load) thru 2022-12-30
    4x Animation devs working on 29 tasks (32% load) thru 2022-12-30

..==============================================~~~~~~~~~~====================================|=========
..==============================================~~~~~~~~~~====================================|=========
..==============================================~~~~~~~~~~====================================|=========
..==========================..................................................................|.........

  • Actor Tech Team
    5x Engineering devs working on 11 tasks (45% load) thru 2022-12-29

..~~~~~~~~~~~~~~~~~~~~======~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~====================....============|=========

  • AI Content Team
    2x Tech Content devs working on 11 tasks (57% load) thru 2022-12-29

..~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~~~~~........~~~~~~~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~|~~~~~~~~~
..................======....................====..............................................|.........

  • Arena Commander Feature Team
    3x Engineering devs working on 27 tasks (41% load) thru 2022-12-22

........................================================......................................|.........
....====================~~~~================================================~~~~~~============|=========

  • Audio
    6x Audio devs working on 14 tasks (65% load) thru 2022-12-01

................................................................................==============|===..====

  • Editor Team
    1x Design dev working on 8 tasks (165% load) thru 2022-12-29
    3x Engineering devs working on 4 tasks (89% load) thru 2022-12-15

..============================================~~~~~~~~~~~~=====================...============|=========
......................................................~~~~=====...=========.......========....|=======..

  • Gameplay Story
    1x Tech Content dev working on 13 tasks (76% load) thru 2022-12-07

.=====.===============~~~~~~..====........====~~~~~~~~~~~~~~~~~~~~~~~~~~~~====~~~~~~~~~~~~~~~~|~~~~~....

  • Narrative
    1x Design dev working on 8 tasks (145% load) thru 2022-12-30

..............................................................................================|=========

  • SQ42 UI Feature Team
    3x Engineering devs working on 5 tasks (71% load) thru 2022-12-29

..............................................................................................|=========
........................................................................========..............|.......==

  • Systemic Services and Tools Team
    4x Engineering devs working on 7 tasks (45% load) thru 2022-12-03

..............................................................................================|=====....

  • Tools Team
    2x Engineering devs working on 8 tasks (82% load) thru 2022-12-29

..============================================~~~~~~~~~~~~=====================...============|=========

  • UI Tech Team
    4x Engineering devs working on 6 tasks (47% load) thru 2022-12-01

..............................==========================................====......============|===......

  • VFX Team
    2x Tech Content devs working on 3 tasks (192% load) thru 2022-11-24

......................~~~~~~=================.................................==========..====|=........

  • Weapon Content Team
    4x Art devs working on 5 tasks (116% load) thru 2022-12-08

................==............................................................................|=====....
................==............................................................................|.........

  • Weapon Feature Team
    5x Design devs working on 38 tasks (33% load) thru 2022-12-30
    2x Engineering devs will work on 3 tasks (114% load) starting 2022-12-08 thru 2022-12-30

..==============================================~~~~~~~~~~====================================|=========
..........................................................................======..............|...======

New Missions - Orison

(Scheduled work ending soon!)

  • Narrative
    1x Design dev working on 1 task (128% load) thru 2022-11-23

..........................................................................................====|=........

Ocean Shader Improvements

(Scheduled work ending soon!)

  • Graphics Team
    1x Engineering dev working on 2 tasks (81% load) thru 2022-12-04

......................................................................................========|====.....

  • Planet Tech Team
    2x Engineering devs working on 6 tasks (72% load) thru 2022-12-07

..........................................=========...=====================...================|=====....

  • VFX Team
    2x Engineering devs working on 3 tasks (93% load) thru 2022-11-24

......................................................................................========|=........
......................................................................................======..|.........

Outpost Homestead - Independent & Outlaw

  • VFX Team
    1x Art dev working on 3 tasks (385% load) thru 2022-11-24

..........................................................................................====|=........

  • EU Sandbox 1
    12x Art devs will work on 15 tasks (104% load) starting 2022-11-30 thru 2022-12-20

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....===========================...=================.|.=======.

Persistent Streaming and Server Meshing

  • Engine Team
    1x Engineering dev working on 5 tasks (157% load) thru 2022-12-01

..................................................................................============|===......

  • Game Services Team
    10x Engineering devs working on 33 tasks (26% load) thru 2022-12-29

..====================~~~~~~~~================================================~~~~~~~~~~~~~~~~|~~~~~~~~~

  • Mission Feature Team
    3x Engineering devs working on 4 tasks (46% load) thru 2022-12-22

.~========================~~~~~~~~~~~~~~~~~~~~~~~~......................................======|=========

  • Network Team
    9x Engineering devs working on 13 tasks (14% load) thru 2022-12-30

..=====.......============....................================================================|=========

  • Persistent Tech Team
    4x Engineering devs working on 17 tasks (40% load) thru 2022-12-30

..====================~~~~~~~~================================================================|=========

  • Systemic Services and Tools Team
    3x Engineering devs working on 3 tasks (62% load) thru 2022-12-03

..........................................................................................====|=====....

  • Vehicle Feature Team
    5x Engineering devs working on 14 tasks (30% load) thru 2022-12-08

......................................==============..========================================|=====....

Physical Damage & Breakability

(Scheduled work ending soon!)

  • Physics Team
    3x Engineering devs working on 5 tasks (44% load) thru 2022-12-04

..===================.....======================....======================......==============|====.....

Physics - Ropes Simulation

(Scheduled work ending soon!)

  • Physics Team
    1x Engineering dev working on 5 tasks (132% load) thru 2022-12-04

..===================.....======================....======================......==============|====.....

Player Interaction Experience T2 - Visor HUD & Helmet

  • SQ42 UI Feature Team
    1x Engineering dev working on 6 tasks (189% load) thru 2022-12-15
    1x Art dev working on 3 tasks (455% load) thru 2022-12-01
    1x Design dev will work on 3 tasks (455% load) starting 2022-12-04 thru 2022-12-15

......................................................................................========|=======..
..............................................................................................|===......
......................................................................................====....|...====..

Player/Machine Physical Interaction

  • Actor Feature Team
    1x Engineering dev working on 6 tasks (109% load) thru 2022-12-30
    1x Animation dev working on 8 tasks (145% load) thru 2022-12-30

..............................................................................================|=========
..............................................................................================|=========

Prone T1

  • Actor Feature Team
    1x Engineering dev working on 8 tasks (145% load) thru 2022-12-30
    1x Animation dev working on 10 tasks (181% load) thru 2022-12-30

..............................................................................================|=========
..............................................................................================|=========

Pyro System, Planet, and Mission Setup

  • Audio
    4x Audio devs working on 8 tasks (72% load) thru 2022-12-01

....................................................................======..........==========|===......

Quantum Simulation

  • Systemic Services and Tools Team
    5x Engineering devs working on 31 tasks (64% load) thru 2022-12-15

.=================================================....========================================|=======..

Quantum Travel Experience

  • Physics Team
    1x Engineering dev working on 5 tasks (132% load) thru 2022-12-04

................................................................................==============|====.....

  • SQ42 UI Feature Team
    1x Design dev working on 3 tasks (455% load) thru 2022-12-01

..............................................................................................|===......

  • Vehicle Feature Team
    3x Engineering devs working on 7 tasks (56% load) thru 2022-12-08

......................................==============..======================..================|=====....

RaStar

(Scheduled work ending soon!)

  • VFX Team
    1x Art dev working on 3 tasks (385% load) thru 2022-11-24

..........................................................................................====|=........

Resource Management

  • Narrative
    1x Design dev working on 3 tasks (192% load) thru 2022-11-23

..........................................................................................~~~~|~........

  • Vehicle Content - EU
    5x Art devs working on 13 tasks (59% load) thru 2022-12-15

......................................................==============............==============|=======..

  • Vehicle Content - US
    1x Design dev working on 8 tasks (150% load) thru 2022-12-30
    1x Art dev working on 10 tasks (152% load) thru 2023-01-20

................................................................................==============|=========
........................................................................................~~~~~~|.........
................................................................................==============|=========

  • EU PU Gameplay Feature Team
    2x Design devs will work on 3 tasks (96% load) starting 2022-12-07 thru 2022-12-20
    2x Engineering devs will work on 3 tasks (192% load) starting 2022-12-07 thru 2022-12-20

..........................~~~~~~~~~~~~~~~~~...~~~~~...~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~|...~~~~~.
..........~~~~~~~~~.......=========================...========================================|...=====.

RSI Lynx

  • Vehicle Content - EU
    3x Art devs working on 12 tasks (126% load) thru 2022-12-15
    1x Design dev working on 11 tasks (399% load) thru 2022-12-15

......................................................................................========|=======..
........................................................................................======|=======..

Satellites - Points of Interest

  • Location Concept Art
    2x Art devs working on 29 tasks (263% load) thru 2022-12-30

......................................================........................================|=========

Ship CPU

(Scheduled work ending soon!)

  • Vehicle Feature Team
    1x Engineering dev working on 7 tasks (285% load) thru 2022-12-08

......................................................................................========|=====....

SQ42 - Vehicle Support

  • Audio
    3x Audio devs working on 11 tasks (102% load) thru 2022-12-01

................................................................................==============|===..====

  • SQ42 Art
    1x Cinematics dev working on 5 tasks (167% load) thru 2022-12-30
    1x Art dev working on 8 tasks (145% load) thru 2022-12-30

..........................................................................................====|=========
..............................................................................================|=========

  • Vehicle Content - EU
    3x Design devs working on 18 tasks (149% load) thru 2022-12-08

......................................................====================......==============|=====....
..............................................................................................|.........

  • Vehicle Content - US
    3x Tech Content devs working on 12 tasks (71% load) thru 2022-12-10
    1x Design dev working on 14 tasks (141% load) thru 2023-03-17
    2x Art devs working on 17 tasks (85% load) thru 2023-03-17

................................====................................................~~~~~~~~==|=======..
................................................................................==============|=========
................................................................................==============|=========

  • Vehicle Feature Team
    9x Engineering devs working on 13 tasks (34% load) thru 2022-12-08

..............................................................................................|.........
..........................======......======..................................================|=====....

  • Weapon Content Team
    5x Art devs working on 14 tasks (120% load) thru 2022-12-22

........................................................................====........======..==|=========

Stanton Fashion Clothing

(Scheduled work ending soon!)

  • Character Tech Art
    1x Tech Content dev working on 3 tasks (455% load) thru 2022-12-01

..........................................................................====....====........|===......

StarWords Improvements

  • Tools Team
    2x Engineering devs working on 11 tasks (113% load) thru 2022-12-29

..=========...=========...=========...========~~~~~~~~~~~~~...=========...=====...============|=========

Subsumption Editor Integration

(Scheduled work ending soon!)

  • AI Tech and Feature Team
    1x Engineering dev working on 6 tasks (189% load) thru 2022-12-01

..======================....====================........====================......============|===......

Time Trial Race Missions

  • Mission Feature Team
    1x Design dev working on 6 tasks (111% load) thru 2022-12-22

............................................................................==================|=========

Unannounced Vehicle

(Scheduled work ending soon!)

  • VFX Team
    2x Art devs working on 3 tasks (192% load) thru 2022-11-24

........................................................=====.............................====|=........

Unified Itemports - FPS

(Scheduled work ending soon!)

  • Character Tech Art
    5x Tech Content devs working on 7 tasks (93% load) thru 2022-12-01

......................................................====....========....................====|===......

Zero G Push & Pull

  • Actor Tech Team
    1x Engineering dev working on 8 tasks (165% load) thru 2022-12-29

......................................................========================....============|=========


The following deliverables are scheduled to begin (or continue) work within two weeks

Artificial Gravity

  • EU PU Gameplay Feature Team
    1x Engineering dev will work on 3 tasks (192% load) starting 2022-12-07 thru 2022-12-20
    1x Design dev will work on 3 tasks (385% load) starting 2022-12-07 thru 2022-12-20

..............................................................................~~~~~~~~~~~~~~~~|...~~~~~.
..............................................................................================|...=====.

  • Narrative
    1x Design dev will work on 4 tasks (93% load) starting 2022-11-24 thru 2022-12-30

..............................................................................................|~~~~~~~~~

Asteroid Facilities

  • EU Sandbox 1
    3x Art devs will work on 5 tasks (139% load) starting 2022-11-30 thru 2022-12-20

....................................................=====================...........=========.|.=======.

Chapter 24

  • SQ42 Level Design 2 - Flight
    2x Design devs will work on 2 tasks (46% load) starting 2022-11-24 thru 2022-12-30

..............................................................................................|=========

Chapter 28

(Starting soon!)

  • SQ42 Character Art
    1x Art dev will work on 3 tasks (455% load) starting 2022-12-04 thru 2022-12-15

..............................................................................................|...====..

FS-Tech-Anim - Asset Integration

  • Tech Animation Team
    7x Tech Content devs will work on 4 tasks (35% load) starting 2022-11-25 thru 2022-12-22

..=========...................=====...=====.......=====...........=========...................|=========

Life Support T0

  • EU PU Gameplay Feature Team
    1x Design dev will work on 5 tasks (321% load) starting 2022-12-07 thru 2022-12-20
    1x Engineering dev will work on 5 tasks (321% load) starting 2022-12-07 thru 2022-12-20

..~~~~~~~~~~~~~~~~~...~~~~~~~~~~~~~~~~~~~~~...~~~~~...~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~|...~~~~~.
..=================...=================...............==================..~~~~~~~~~~~~~~~~~~~~|...~~~~~.

New Player Experience

  • EU Landing Zone 2
    1x Art dev will work on 2 tasks (256% load) starting 2022-12-07 thru 2022-12-20

..............................................................................................|...=====.

  • Narrative
    1x Design dev will work on 3 tasks (69% load) starting 2022-11-24 thru 2022-12-30

........................................................====================......==========..|~~~~~~~~~

Outpost Theme Variants

  • EU Sandbox 1
    4x Design devs will work on 15 tasks (313% load) starting 2022-11-30 thru 2022-12-20

.~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~~========....=======.......................=================.|.=======.

Vehicle Tractor Beams

  • EU PU Gameplay Feature Team
    2x Engineering devs will work on 2 tasks (128% load) starting 2022-12-07 thru 2022-12-20

..............................................................................................|...=====.

VOLT Parallax

(Scheduled work ending soon!)

  • Narrative