Scheduled Deliverables

as of 2022-08-03

There are currently 92 scheduled deliverables being worked on by 41 teams

15 deliverables are scheduled to begin work by 14 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 436 devs (out of ~512, or 85%) with 926 assignments scheduled to work on 92 observable deliverables. Of those deliverables, 22% are for SQ42 exclusively, with ~218 devs (43%) scheduled for approximately 4383 man-days. 29% of deliverables are shared between both projects.

9 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:

AI - Commuter

  • AI Content Team
    1x Design dev working on 5 tasks (214% load) thru 2022-08-18

........................................................======|=====....................................
........................................................====..|.............====........................

AI - Medical

  • AI Content Team
    1x Animation dev working on 3 tasks (200% load) thru 2022-08-18
    2x Design devs working on 4 tasks (85% load) thru 2022-08-18

............................................................==|=====....................................
........................................................======|=====....................................

  • Facial Animation
    2x Animation devs working on 4 tasks (81% load) thru 2022-08-25

........................................................======|=======..................................

AI - Off Duty Activities - Sleeping

(Scheduled work ending soon!)

  • AI Content Team
    2x Animation devs working on 4 tasks (133% load) thru 2022-08-04

........................................................======|=........................................

AR and Map Marker System Rework

  • Graphics Team
    1x Engineering dev working on 4 tasks (163% load) thru 2022-08-10

....................................................==========|===......................................

  • UI Tech Team
    2x Engineering devs working on 5 tasks (107% load) thru 2022-09-01

..................................==================........==|=========................................

Argo SRV

  • Vehicle Content - EU
    4x Art devs working on 31 tasks (69% load) thru 2022-10-20
    1x Design dev working on 15 tasks (338% load) thru 2022-09-15

................................==============================|=======================..................
................................~~~~~~~~~~~~~~~~~~....========|=============....~~~~~~~~~~~~~~~~~~~~~~..

Asteroid Facilities

  • EU Sandbox 1
    1x Art dev working on 7 tasks (167% load) thru 2022-09-06

....................................................==========|==========...........=========...=======.

Atlas

  • Network Team
    5x Engineering devs working on 6 tasks (36% load) thru 2022-08-31

......=============.......============................========|=========................................

Banu Merchantman

  • Vehicle Content - EU
    12x Art devs working on 25 tasks (47% load) thru 2022-09-15
    3x Design devs working on 15 tasks (56% load) thru 2022-09-15

..================================================....========|=============....======================..
..============~~~~~~~~==~~................======~~....~~~~~~~~|~~~~~~~~~~~~~....======================..

  • VFX Team
    2x Art devs working on 4 tasks (123% load) thru 2022-08-07

........................................~~~~~...........======|==.......................................

  • Vehicle Content - US
    3x Tech Content devs will work on 16 tasks (165% load) starting 2022-08-18 thru 2022-09-14

..............................................................|...~~~~~~~~~~............................

Bounty Hunter V2

  • Mission Feature Team
    2x Design devs working on 6 tasks (40% load) thru 2022-09-22

....................................................~~~~~~~~~~|~~~~~~~~~~~~~~~..........................

  • US PU Gameplay Feature Team
    1x Design dev working on 7 tasks (220% load) thru 2022-08-25

......................................................========|=======........~~~~~~~~~~~~~~~~..........
......=========...=====...~~~~................................|...............================..........

Bug Fixing & Tech Debt

  • AI Content Team
    4x Animation devs working on 2 tasks (76% load) thru 2022-08-04

......======..======............====....====..................|.........................................
..............======....................====................==|=....====................................

  • Live Tools Team
    4x Engineering devs working on 15 tasks (38% load) thru 2022-12-19

..........................====================================|========================================.

  • Mission Feature Team
    3x Engineering devs working on 4 tasks (40% load) thru 2022-09-22

............................................................==|===============..........................
..............................................................|.............============================

  • SC Character Art
    7x Art devs working on 5 tasks (48% load) thru 2022-08-25

..............................................................|=======....====..........................

  • UI Tech Team
    4x Engineering devs working on 5 tasks (39% load) thru 2022-08-04

..====........................====..............==============|=............====........................

  • Vehicle Content - US
    3x Art devs working on 6 tasks (49% load) thru 2022-09-28

....................====......................................|...........======....................====
..........................................................====|=================........................

  • Vehicle Feature Team
    12x Engineering devs working on 12 tasks (41% load) thru 2022-08-17

..=================.......==========================..========|=====..........======....................
..........................======......................======..|...............======....................

  • Character Tech Art
    7x Tech Content devs will work on 2 tasks (43% load) starting 2022-08-14 thru 2022-08-25

..============........................============........====|...====....====..........................

  • Editor Team
    5x Engineering devs will work on 8 tasks (205% load) starting 2022-08-03 thru 2022-08-16

..........=====.......=================.......................|====.......=====.........................

Building Interiors

  • Location Concept Art
    7x Art devs working on 31 tasks (42% load) thru 2022-12-30

......................................========================|=========================================

  • MTL Sandbox 1
    14x Art devs working on 28 tasks (48% load) thru 2022-09-14
    4x Design devs working on 12 tasks (72% load) thru 2022-09-14

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============........========|=============..======================....
..~~~~~~~~~~~~~~~~~~~~~...............................========|=============..======================....

Cargo System Refactor

  • US PU Gameplay Feature Team
    3x Engineering devs working on 5 tasks (31% load) thru 2022-08-25

..~~~~~~~~========~~~~~~~~~~~~================........~~~~~~~~|~~~~~~~..................................
..........................~~~~~~~~~~~~~~~~~~~~................|.........................................

Cave Archetypes

  • Audio
    1x Audio dev working on 5 tasks (463% load) thru 2022-08-04

..........................................................====|=........................................

  • VFX Team
    1x Art dev working on 3 tasks (385% load) thru 2022-08-07

............................................................==|==.......................................

Chapter 01

  • Cinematics Team
    2x Design devs working on 21 tasks (21% load) thru 2022-09-29
    3x Animation devs working on 29 tasks (19% load) thru 2022-09-29

.~~~~~~~~~~~~~~~~~~~~~~~~~======~~~~~~~~~~~~~~~~~~~~======~~~~|~~~~~~~~~~~~~~~~~........................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 9 tasks (36% load) thru 2022-09-28

.~====================~~~~~~~~======================..========|=================........................

  • SQ42 Art
    9x Art devs will work on 4 tasks (18% load) starting 2022-08-18 thru 2022-09-28

..............................................................|...==============........................

  • SQ42 Level Design 3 - Social
    3x Design devs will work on 2 tasks (85% load) starting 2022-08-04 thru 2022-08-17

..~~~~~~~~~~~~~~~~======..====....====....==================..|=====..==========........................

Chapter 02

  • Cinematics Team
    2x Animation devs working on 4 tasks (24% load) thru 2022-09-08
    1x Design dev will work on 3 tasks (56% load) starting 2022-08-15 thru 2022-09-29

........................................~~~~~~~~~~~~~~........|...~~~~~~~~~~~~~~........................
..........................~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~|~~~~~~~~~~~..............................

  • SQ42 Art
    2x Art devs working on 7 tasks (70% load) thru 2022-09-28

......................................................========|=================........................

Chapter 04

  • AI Content Team
    1x Design dev working on 4 tasks (85% load) thru 2022-08-18

........................................................~~~~~~|~~~~~....................................

  • Cinematics Team
    3x Animation devs working on 3 tasks (19% load) thru 2022-08-14

.~~~~~~~~~~~~~~~~~~~~~~~~~~...................................|.........................................
..........................~~~~~~~~~~~~~~~~..........~~~~~~~~~~|~~~~.....................................

  • Gameplay Story
    5x Animation devs working on 11 tasks (22% load) thru 2022-09-28

.......~~~~...........................~~~~....~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................
......................................~~~~....................|.........................................

  • SQ42 Art
    1x Art dev will work on 4 tasks (163% load) starting 2022-08-18 thru 2022-09-28

..............................................................|...==============........................

Chapter 06

  • Gameplay Story
    5x Animation devs working on 14 tasks (28% load) thru 2022-09-28

.~~~~~.~~~~~~~~.......~~~~~~..~~~~~~~~~~~~............~~~~~~~~|~~~~~~~~~~~~~~~~~........................
..................................~~~~~~~~....................|.........................................

  • SQ42 Level Design 3 - Social
    2x Design devs working on 7 tasks (70% load) thru 2022-09-28

..====~~~~~~~~~~~~======..====================================|=================........................

Chapter 09

(Scheduled work ending soon!)

  • Cinematics Team
    2x Design devs working on 2 tasks (35% load) thru 2022-08-14

.~~~~~~~~~~~~~~~~~~~~~~~~~~.....~~~~~~~~~~................~~~~|~~~~.....................................

Chapter 10

  • Gameplay Story
    5x Animation devs working on 8 tasks (16% load) thru 2022-09-28

.......~~~~~~~~.......~~~~~~~~~~~~~~~~~~~~............~~~~~~~~|~~~~~~~~~~~~~~~~~........................
..........................~~~~....~~~~~~~~....................|.........................................

  • SQ42 Level Design 3 - Social
    1x Design dev working on 7 tasks (131% load) thru 2022-09-28

..~~~~~~..................========~~~~========================|~~~==============........................

Chapter 11

  • Cinematics Team
    3x Design devs working on 4 tasks (16% load) thru 2022-09-29
    2x Animation devs working on 4 tasks (25% load) thru 2022-08-14

.~~~~~~~~~~~~~~~~~~~~~~~~~~.....~~~~~~~~~~~~~~~~~~~~~~....~~~~|~~~~~~~~~~~~~~~~~........................
..........................~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~|~~~~.....~~~~~~~~........................

  • SQ42 Level Design 1 - FPS
    5x Design devs will work on 4 tasks (33% load) starting 2022-08-04 thru 2022-09-14

.=====================~~~~~~~~....============........======..|=============............................

Chapter 12

  • AI Content Team
    2x Design devs working on 6 tasks (50% load) thru 2022-09-15

........................................................~~~~~~|~~~~~========............................
..............................................................|.........====............................

  • Cinematics Team
    3x Design devs working on 29 tasks (13% load) thru 2022-09-29
    4x Animation devs working on 19 tasks (11% load) thru 2022-09-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • SQ42 Art
    12x Art devs working on 20 tasks (68% load) thru 2022-08-17

..........................============................========|=====....................................

  • SQ42 Level Design 1 - FPS
    4x Design devs working on 9 tasks (45% load) thru 2022-09-28

.=====~~~~~~~~~~~~~~~~~~~~~~~~================================|=================........................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 9 tasks (36% load) thru 2022-09-28

..........................~~~~======================..========|=================........................

  • SQ42 Level Design 3 - Social
    3x Design devs working on 5 tasks (51% load) thru 2022-08-31

..........................================............========|=========................................

Chapter 14

  • Cinematics Team
    3x Design devs working on 11 tasks (17% load) thru 2022-09-29
    3x Animation devs working on 11 tasks (17% load) thru 2022-09-29

..........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................
..........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • SQ42 Art
    11x Art devs working on 25 tasks (46% load) thru 2022-09-28
    1x Cinematics dev working on 7 tasks (141% load) thru 2022-09-28

......................................................========|=================........................
..........................========....................========|=================........................

  • SQ42 Level Design 1 - FPS
    7x Design devs working on 17 tasks (49% load) thru 2022-09-28

.=====================~~~~~~~~================================|=================........................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 9 tasks (36% load) thru 2022-09-28

......================~~~~~~~~======================..========|=================........................

  • VFX Team
    1x Art dev working on 5 tasks (152% load) thru 2022-08-21

....................................................==========|======...................................

  • SQ42 Level Design 3 - Social
    1x Design dev will work on 2 tasks (128% load) starting 2022-08-04 thru 2022-08-17

..................................~~~~........................|~~~~~....................................

Chapter 15

  • Cinematics Team
    3x Animation devs working on 29 tasks (14% load) thru 2022-09-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~...................................|.........................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

Chapter 17

  • Gameplay Story
    4x Animation devs working on 7 tasks (18% load) thru 2022-09-28

......................................................~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • SQ42 Art
    1x Art dev working on 7 tasks (141% load) thru 2022-09-28

......................................................========|=================........................

Chapter 18

  • Gameplay Story
    4x Animation devs working on 8 tasks (20% load) thru 2022-09-28

..............~~~~~...........................~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

Chapter 19

  • Cinematics Team
    2x Animation devs working on 9 tasks (21% load) thru 2022-09-29

..........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • Gameplay Story
    5x Animation devs working on 7 tasks (14% load) thru 2022-09-28

..................~~~~~.......~~~~~~~~........~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................
..................................~~~~........................|.........................................

  • SQ42 Art
    3x Art devs will work on 8 tasks (102% load) starting 2022-08-18 thru 2022-09-28

..............................................................|...==============........................

Chapter 20

  • Cinematics Team
    2x Design devs working on 4 tasks (24% load) thru 2022-09-08

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~|~~~~~~~~~~~..............................
.~~~~~~~~~~~~~~~~~~~~~~~~~~...................................|.........................................

  • Gameplay Story
    4x Animation devs working on 8 tasks (20% load) thru 2022-09-28

..............................................~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • SQ42 Art
    2x Art devs working on 7 tasks (70% load) thru 2022-09-28

......................................................========|=================........................

Chapter 23

  • Cinematics Team
    3x Animation devs working on 13 tasks (20% load) thru 2022-09-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~...................................|.........................................
..........................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

Character Work

  • AI Content Team
    5x Animation devs working on 5 tasks (31% load) thru 2022-09-01

..................======....................====..............|.........................................
..======================....====================........======|=========................................

  • Audio
    5x Audio devs working on 7 tasks (15% load) thru 2022-08-18

....================..........================================|=====....========........................

  • Character Tech Art
    7x Tech Content devs working on 11 tasks (32% load) thru 2022-09-22

......============================================....========|===============..........................

  • Facial Animation
    7x Animation devs working on 20 tasks (18% load) thru 2022-09-22

....==========================================~~~~~~~~~~======|===============..........................

  • SQ42 Character Art
    12x Art devs working on 19 tasks (33% load) thru 2022-09-22

.=================================================....========|===============..........................

  • Tech Animation Team
    11x Tech Content devs working on 13 tasks (12% load) thru 2022-09-12

..........~~~~~~~~~~~~~~~~~...~~~~=====...~~~~========~~~~~~~~|============.............................

  • Actor Feature Team
    1x Engineering dev will work on 7 tasks (141% load) starting 2022-08-18 thru 2022-11-09
    2x Animation devs will work on 9 tasks (90% load) starting 2022-08-18 thru 2022-11-09

..............................................................|...==========================............
..............................................................|...==========================............

  • Motion Capture Team
    9x Animation devs will work on 16 tasks (64% load) starting 2022-08-14 thru 2022-09-29

......=========.......====~~~~~~~~~~~~~~~~....................|...==============........................

Commodity Kiosk

  • US PU Gameplay Feature Team
    3x Art devs working on 7 tasks (73% load) thru 2022-08-25

..=================.......~~~~~~~~~~~~~~~~====........========|=======..................................
..~~~~~~~~~~~~~~~~~...........................................|.........................................

Cooperative Locomotion

(Scheduled work ending soon!)

  • Actor Feature Team
    2x Engineering devs working on 5 tasks (71% load) thru 2022-08-17

......................................................~~~~====|=====....................................

Derelict Spaceships - Points of Interest

  • MTL Sandbox 1
    4x Design devs working on 6 tasks (36% load) thru 2022-09-14
    8x Art devs working on 11 tasks (33% load) thru 2022-09-14

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============........========|=============..======================....
.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============........========|=============..======================....

  • VFX Team
    1x Art dev will work on 1 task (128% load) starting 2022-08-08 thru 2022-08-21

..............................................................|.=====...................................

DGS Crash Recovery

  • Network Team
    1x Engineering dev working on 8 tasks (161% load) thru 2022-09-28

..................============================================|=================........................

DGS Mesh Node

  • Network Team
    3x Engineering devs working on 8 tasks (54% load) thru 2022-09-28

..................============================================|=================........................

Doors/Airlocks/Light Panels UI

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    1x Art dev working on 3 tasks (455% load) thru 2022-08-04

......................................====..................==|=........................................
..................................====........................|.........................................

Drake Corsair

  • Vehicle Content - US
    3x Tech Content devs working on 11 tasks (75% load) thru 2022-08-17
    2x Design devs working on 7 tasks (216% load) thru 2022-08-03

........................................~~~~..........~~~~~~~~|~~~~~....................................
..======================....========================..======..|.........................................
..======================....========================..========|=........................................

  • VFX Team
    1x Art dev will work on 3 tasks (385% load) starting 2022-08-08 thru 2022-08-21

..............................................................|.=====...................................

Drake Vulture

  • Audio
    3x Audio devs working on 8 tasks (29% load) thru 2022-09-01

....................========..==~~~~~~================~~======|=========................................

Dynamic Events

  • Mission Feature Team
    7x Design devs working on 13 tasks (13% load) thru 2022-12-22

..================================================..~~~~~~~~~~|~~~~~~~~~~~~~============================
..========================....................................|.............============================

  • US PU Gameplay Feature Team
    2x Design devs working on 5 tasks (79% load) thru 2022-08-25

..~~~~~~~~~~~~~~~~~.......~~~~~~~~~~~~~~~~~~~~........========|=======........================..........

  • Narrative
    2x Design devs will work on 2 tasks (152% load) starting 2022-08-07 thru 2022-08-18

..............................................................|.====....................................

Dynamic Mission System

  • Mission Feature Team
    1x Engineering dev working on 6 tasks (60% load) thru 2022-09-22

..........................~~~~~~~~~~~~~~~~~~~~~~~~..~~~~~~~~~~|~~~~~~~~~~~~~~~..........................

Enemy Characters

  • Narrative
    2x Design devs working on 6 tasks (455% load) thru 2022-08-04

............................................................==|=........................................

  • SQ42 Character Art
    5x Art devs working on 9 tasks (57% load) thru 2022-09-22

..================================================....====....|===============..........................

  • Weapon Content Team
    5x Art devs working on 15 tasks (200% load) thru 2022-08-18
    1x Animation dev working on 4 tasks (606% load) thru 2022-08-04

............................................................==|=====....========........................
............................................................==|=........................................

Enemy Ships

  • SQ42 Art
    1x Art dev working on 7 tasks (141% load) thru 2022-09-28

......................................................========|=================........................

EVA T2

  • Actor Feature Team
    2x Animation devs working on 21 tasks (33% load) thru 2022-09-28

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • Actor Tech Team
    2x Engineering devs working on 13 tasks (58% load) thru 2022-09-22

............................====================~~~~~~~~~~====|===============..........................

Fire Hazard

  • Graphics Team
    2x Engineering devs working on 7 tasks (112% load) thru 2022-08-31
    1x Tech Content dev working on 5 tasks (108% load) thru 2022-08-31

..........................................................~~~~|~~~~~~~~~................................
..~~~~~~~~~~~~~~~~~~~...............................~~~~~~~~~~|~~~~~~~~~................................

  • VFX Team
    3x Engineering devs working on 7 tasks (103% load) thru 2022-08-21
    1x Tech Content dev working on 4 tasks (123% load) thru 2022-08-21

............................................................~~|~~~~~~...................................
....~~~~~~~~~~~~~~~~~~~.............=====...................~~|~~~~~~...................................

Fire Rats Armor

(Recently started!)

  • SC Character Art
    1x Art dev working on 5 tasks (214% load) thru 2022-09-08

..............................................................|===========..............................

Flak Ammunition

(Recently started!)

(Scheduled work ending soon!)

  • Narrative
    1x Design dev working on 3 tasks (227% load) thru 2022-08-04

............................................................~~|~........................................

FPS Devices T1

  • Audio
    2x Audio devs working on 11 tasks (153% load) thru 2022-09-29

..............................................................|=================........................

  • Weapon Feature Team
    2x Engineering devs working on 11 tasks (49% load) thru 2022-09-28

..............==============............~~~~~~~~~~~~~~~~~~====|=================........................

FPS Radar / Scanning

  • Actor Feature Team
    2x Engineering devs working on 5 tasks (71% load) thru 2022-08-17

..........==================================..........~~~~====|=====....................................
..~~~~~~~~~~~~~~~~~~~~~~~~~~..................................|.........................................

Frontier Clothing

  • Character Tech Art
    3x Tech Content devs working on 4 tasks (89% load) thru 2022-08-11

......................................========............====|===....========..........................

  • SC Character Art
    14x Art devs working on 14 tasks (21% load) thru 2022-09-22

.=================================================....========|===============..........................

Gen12 - Renderer T1

  • Graphics Team
    7x Engineering devs working on 14 tasks (54% load) thru 2022-08-31

..===================.....======================....==========|=========................................

HEX

  • Live Tools Team
    5x Engineering devs working on 31 tasks (36% load) thru 2022-12-19

..=====================...~~~~========================~~~~~~~~|~~~~~~~~~~~~~~~~~~~=====================.

Jump Points

  • Graphics Team
    1x Engineering dev working on 4 tasks (163% load) thru 2022-08-10

........=============.....======================....==========|===......................................

  • Vehicle Feature Team
    5x Engineering devs will work on 6 tasks (74% load) starting 2022-08-18 thru 2022-09-14

......=====...................................................|...==========............................

Ladders T1

(Scheduled work ending soon!)

  • Actor Feature Team
    3x Animation devs working on 14 tasks (53% load) thru 2022-08-17
    1x Engineering dev will work on 3 tasks (385% load) starting 2022-08-04 thru 2022-08-17

............................====================~~~~~~~~~~====|=====....................................
..............................................................|=====....................................

  • UI Tech Team
    1x Engineering dev working on 3 tasks (455% load) thru 2022-08-04

............................................................==|=........................................

Life Support T0

  • EU PU Gameplay Feature Team
    1x Engineering dev working on 6 tasks (182% load) thru 2022-08-31
    1x Design dev working on 6 tasks (91% load) thru 2022-08-31

..=================...=================...............========|=========..~~~~~~~~~~~~~~~~~~~~~...~~~~~.
..~~~~~~~~~~~~~~~~~...~~~~~~~~~~~~~~~~~~~~~...~~~~~...~~~~~~~~|~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~...~~~~~.

Lorville Cityscape

  • MTL Sandbox 1
    4x Art devs working on 12 tasks (72% load) thru 2022-09-14

......................................................========|=============..======================....

Map and Radar System Rework

  • SQ42 UI Feature Team
    3x Engineering devs working on 17 tasks (60% load) thru 2022-09-15
    3x Art devs working on 4 tasks (89% load) thru 2022-08-18

..............................================================|=============............................
..........................................==============....==|=====....................................

  • Graphics Team
    1x Engineering dev will work on 3 tasks (250% load) starting 2022-08-11 thru 2022-08-31

..............................................................|.========................................

MFD Rework

  • Vehicle Feature Team
    8x Engineering devs working on 6 tasks (23% load) thru 2022-09-14

..........................................................====|=============......==================....

  • UI Tech Team
    1x Engineering dev will work on 5 tasks (214% load) starting 2022-08-07 thru 2022-09-15

..............................................................|.============............................

Miscellaneous Support

  • Actor Feature Team
    3x Engineering devs working on 26 tasks (38% load) thru 2022-12-30
    3x Design devs working on 29 tasks (43% load) thru 2022-12-30
    3x Animation devs working on 29 tasks (43% load) thru 2022-12-30

..==============================================~~~~~~~~~~====|=========================================
..==============================================~~~~~~~~~~====|=========================================
..==============================================~~~~~~~~~~====|=========================================
..==========================..................................|.........................................

  • Actor Tech Team
    5x Engineering devs working on 23 tasks (20% load) thru 2022-09-22

..~~~~~~~~~~~~~~~~~~~~======~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~====|===============..........................

  • AI Content Team
    2x Tech Content devs working on 11 tasks (62% load) thru 2022-09-29

..~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~~~~~........~~~~~~|~~~~~~~~~~~~~====........................
..................======....................====..............|.........................................

  • Gameplay Story
    1x Tech Content dev working on 8 tasks (90% load) thru 2022-09-28

.=====.===============~~~~~~..====........====~~~~~~~~~~~~~~~~|~~~~~~~~~~~======........................

  • Graphics Team
    1x Tech Content dev working on 5 tasks (134% load) thru 2022-08-31
    4x Engineering devs working on 8 tasks (54% load) thru 2022-08-31

..===================...............................==========|=========................................
..............=======.....======================....==========|=========................................

  • Motion Capture Team
    8x Animation devs working on 18 tasks (16% load) thru 2022-08-13

..========================================~~~~~~~~~~==========|=====....................................

  • SQ42 Feature Team
    2x Engineering devs working on 3 tasks (93% load) thru 2022-08-03

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~================================|=........................................

  • Vehicle Feature Team
    12x Engineering devs working on 8 tasks (13% load) thru 2022-09-28
    3x Design devs will work on 6 tasks (61% load) starting 2022-08-04 thru 2022-09-28

..............======================================..========|=================..======================
..............................======================..........|=================..======..........======

  • Weapon Feature Team
    5x Design devs working on 38 tasks (34% load) thru 2022-12-30

..==============================================~~~~~~~~~~====|=========================================
..............................................................|...........======..................======

  • Editor Team
    3x Engineering devs will work on 4 tasks (82% load) starting 2022-08-17 thru 2022-09-13

......................................................~~~~====|...=========.............................

  • UI Tech Team
    3x Engineering devs will work on 3 tasks (152% load) starting 2022-08-07 thru 2022-08-18

..............................==========================......|.====....====............................

mobiGlas Rework

  • SQ42 Feature Team
    1x Engineering dev working on 7 tasks (141% load) thru 2022-09-28

......................................................========|=================........................

New Interdiction Scenarios

  • EU Sandbox 1
    1x Design dev working on 4 tasks (119% load) thru 2022-08-23

....................................................==========|======.......=========...................

New Missions - Orison

  • Mission Feature Team
    2x Design devs working on 6 tasks (50% load) thru 2022-09-22

....................................................~~~~~~~~~~|.........======..........................
....................................................========~~|~~~~~~~~~~~~~~~..........................

New Player Experience

  • EU Landing Zone Team
    2x Art devs working on 4 tasks (123% load) thru 2022-08-03

......................................................========|=......======......=========.............

  • Narrative
    1x Design dev working on 7 tasks (174% load) thru 2022-09-15

........................................................======|=============............................

Outpost Homestead - Independent & Outlaw

  • EU Sandbox 1
    10x Art devs working on 20 tasks (36% load) thru 2022-09-06
    4x Design devs working on 10 tasks (60% load) thru 2022-09-06

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....================|==========...=================...=======.
.~~~~~~~~~~.~~~~~~~~~~~~~~~.~~~~~~..................==========|==========...............................

  • Audio
    3x Audio devs will work on 6 tasks (133% load) starting 2022-08-07 thru 2022-09-01

..............................................................|.========................................

Persistent Streaming and Server Meshing

  • Actor Feature Team
    2x Animation devs working on 5 tasks (71% load) thru 2022-08-17

..==========================..................................|.........................................
....................................============......~~~~====|=====....................................

  • Actor Tech Team
    2x Engineering devs working on 8 tasks (67% load) thru 2022-09-22

..==========================..........................========|===============..........................

  • Game Services Team
    10x Engineering devs working on 35 tasks (35% load) thru 2022-12-19

..====================~~~~~~~~================================|========================================.

  • Network Team
    9x Engineering devs working on 14 tasks (15% load) thru 2022-12-30

..=====.......============....................================|=========================================

  • Persistent Tech Team
    4x Engineering devs working on 20 tasks (47% load) thru 2022-12-30

..====================~~~~~~~~================================|=========================================

  • US PU Gameplay Feature Team
    4x Engineering devs working on 6 tasks (24% load) thru 2022-08-25

..................................============........~~~~~~~~|~~~~~~~..................................

  • Vehicle Feature Team
    3x Engineering devs working on 8 tasks (54% load) thru 2022-09-28

......................................==============..========|=================........................

  • Weapon Feature Team
    1x Engineering dev working on 5 tasks (142% load) thru 2022-08-17

......................................................~~~~====|=====....................................

Physical Damage & Breakability

  • Physics Team
    3x Engineering devs working on 6 tasks (48% load) thru 2022-09-08

..===================.....======================....==========|===========..............................

Physics - Ropes Simulation

  • Physics Team
    1x Engineering dev working on 4 tasks (95% load) thru 2022-09-08

..===================.....======================....==========|===========..............................

Player Interaction Experience T0 - Hints & Interactions

  • Actor Feature Team
    2x Engineering devs working on 10 tasks (61% load) thru 2022-09-28

............................................====~~~~~~~~~~====|=================........................

Player Interaction Experience T1 - Lockers & Inventory

  • Actor Feature Team
    1x Engineering dev working on 10 tasks (120% load) thru 2022-11-09
    1x Design dev working on 13 tasks (61% load) thru 2022-09-28
    1x Animation dev working on 4 tasks (122% load) thru 2022-08-17

......................................................========|=============================............
............................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................
............................============================......|.........................................
......................................................~~~~====|=====....................................

Player Interaction Experience T2 - Visor HUD & Helmet

  • Actor Feature Team
    1x Design dev working on 14 tasks (66% load) thru 2022-09-28

..............................................................|...............==========================
............................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................
..............==============..................................|.........................................

Pyro Space Stations

  • EU Landing Zone Team
    15x Art devs working on 27 tasks (55% load) thru 2022-08-31
    3x Design devs working on 9 tasks (91% load) thru 2022-08-31

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....================|=========..======..=================.....
.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....================|=========..======..=================.....

  • VFX Team
    1x Art dev working on 3 tasks (185% load) thru 2022-08-07

........................................................======|==.......................................

Pyro System, Planet, and Mission Setup

  • US PU Gameplay Feature Team
    1x Design dev working on 6 tasks (189% load) thru 2022-08-25

......................................========........========|=======........================..........

Quantum Simulation

  • Systemic Services and Tools Team
    5x Engineering devs working on 27 tasks (56% load) thru 2022-12-15

.=================================================....========|=======================================..

Quantum Travel Experience

  • Vehicle Feature Team
    2x Engineering devs working on 9 tasks (109% load) thru 2022-09-14

......................................==============..========|=============......==================....

Replication Layer Entity Authority

  • Network Team
    6x Engineering devs working on 7 tasks (28% load) thru 2022-09-14

..=========...=====.......====================........========|=============............................

Rescue/Transport Mission

  • EU Landing Zone Team
    1x Design dev working on 4 tasks (256% load) thru 2022-08-17

..........................................................====|=====....................................

  • Facial Animation
    3x Animation devs working on 7 tasks (56% load) thru 2022-09-22

........................................................======|===============..........................

  • Narrative
    2x Design devs working on 3 tasks (227% load) thru 2022-08-04

....====........................................====........==|=........................................

Resource Management

  • EU PU Gameplay Feature Team
    2x Engineering devs working on 12 tasks (72% load) thru 2022-11-22
    2x Design devs working on 6 tasks (45% load) thru 2022-08-31

..........~~~~~~~~~.......=========================...========|================================...=====.
..........................~~~~~~~~~~~~~~~~~...~~~~~...~~~~~~~~|~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~...~~~~~.

  • Vehicle Feature Team
    3x Engineering devs working on 9 tasks (72% load) thru 2022-09-14
    2x Design devs will work on 7 tasks (142% load) starting 2022-08-18 thru 2022-09-28

......................................==============..========|=============............................
......................................==============..........|...==============........................

RSI Apollo

(Recently started!)

  • Vehicle Content - US
    4x Art devs working on 20 tasks (35% load) thru 2023-03-17
    1x Design dev will work on 6 tasks (244% load) starting 2022-08-04 thru 2022-09-14

..............................................................|=============............................
..........................................................====|=========================================

Salvage T0

  • Audio
    5x Audio devs working on 11 tasks (21% load) thru 2022-08-18

..................==========..~~~~~~~~~~~~~~~~~~~~~~~~~~~~====|=====....................................

  • EU PU Gameplay Feature Team
    1x Engineering dev working on 6 tasks (182% load) thru 2022-08-31

..........................=================...=====...========|=========................................

  • VFX Team
    4x Art devs working on 6 tasks (45% load) thru 2022-08-21

....=====================================...........==========|======...................................
....~~~~~~~~~~~~~~~~~~~~~~~~=================.......~~~~~~~~~.|.........................................

Sandbox Prison Activities

  • Mission Feature Team
    2x Engineering devs working on 3 tasks (41% load) thru 2022-09-08
    2x Design devs working on 7 tasks (50% load) thru 2022-09-22

............................................................~~|~~~~~======..............................
....................................................~~~~~~~~~~|~~~~~~~~~~~~~~~..........................

Security Post Kareah Reactivation

  • Mission Feature Team
    2x Design devs working on 7 tasks (60% load) thru 2022-09-22

....................................................====~~~~==|===============..........................
..............................................................|.....~~~~~~~~~~..........................

Ship CPU

  • Audio
    2x Audio devs working on 8 tasks (42% load) thru 2022-08-18

..............................==========~~~~~~========~~======|=====....................................

Shopkeeper Outfits

(Scheduled work ending soon!)

  • Character Tech Art
    2x Tech Content devs working on 3 tasks (227% load) thru 2022-08-11

......................................................====....|===......................................

SQ42 - Vehicle Support

  • Vehicle Content - US
    2x Art devs working on 11 tasks (108% load) thru 2022-10-15
    1x Design dev will work on 5 tasks (203% load) starting 2022-08-04 thru 2022-09-14

................................====..........................|.........................................
..............................................................|=============............................
..........................................................====|=======================..................

Unannounced Vehicle

  • Vehicle Content - EU
    2x Design devs working on 13 tasks (146% load) thru 2022-09-15
    4x Art devs working on 34 tasks (71% load) thru 2022-10-20

............................~~~~~~~~~~~~~~~~~~~~~~....========|=============....~~~~~~~~~~~~~~..........
............................==================================|=======================..................

  • Vehicle Feature Team
    2x Design devs working on 7 tasks (224% load) thru 2022-08-17

..........................................................====|=====....................................

  • Vehicle Content - US
    3x Tech Content devs will work on 10 tasks (103% load) starting 2022-08-18 thru 2022-09-14

..............................................................|...~~~~~~~~~~....==========..............

Unannounced Vehicle

  • Audio
    1x Audio dev working on 10 tasks (98% load) thru 2022-09-01

..............................================================|=========................................

Unannounced Vehicle

  • Vehicle Content - EU
    2x Design devs working on 13 tasks (73% load) thru 2022-09-15

..............========..........................~~....~~~~~~~~|~~~~~~~~~~~~~............................
..............============............................======..|.........................................

  • Vehicle Content - US
    3x Tech Content devs working on 11 tasks (75% load) thru 2022-08-17

......................................................~~~~~~~~|~~~~~....................................

  • Audio
    2x Audio devs will work on 4 tasks (303% load) starting 2022-08-07 thru 2022-08-18

..............................................................|.====....====............................

Unannounced Vehicle

(Scheduled work ending soon!)

  • Vehicle Concept Art
    4x Art devs working on 13 tasks (139% load) thru 2022-08-11

............................==============............========|===......................................

Unannounced Vehicle

  • Vehicle Concept Art
    2x Art devs working on 10 tasks (181% load) thru 2022-08-18

......................................................========|=====....................................

Unified Itemports - FPS

  • Character Tech Art
    5x Tech Content devs working on 4 tasks (53% load) thru 2022-08-25

......................................................====....|=======..................................

Virtual AI Service

  • Systemic Services and Tools Team
    1x Engineering dev working on 7 tasks (212% load) thru 2022-08-31

..................=====...............................========|=========................................

Visor/Lens Rework

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    1x Engineering dev working on 3 tasks (455% load) thru 2022-08-04

..............................====..........========........==|=........................................
..........................................======..............|.........................................

XenoThreat Armor

  • SC Character Art
    4x Art devs working on 8 tasks (41% load) thru 2022-09-22

..============....========............................========|===============..........................

Zero G Push & Pull

  • Actor Feature Team
    2x Animation devs working on 20 tasks (31% load) thru 2022-09-28

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................

  • Actor Tech Team
    1x Engineering dev working on 8 tasks (134% load) thru 2022-09-22

......................................................========|===============..........................


The following deliverables are scheduled to begin (or continue) work within two weeks

AI - Utility

(Starting soon!)

  • AI Content Team
    2x Animation devs will work on 3 tasks (227% load) starting 2022-08-07 thru 2022-08-18

..............................................................|.====....========........................

Chapter 05

  • SQ42 Art
    6x Art devs will work on 8 tasks (54% load) starting 2022-08-18 thru 2022-09-28

..............................................................|...==============........................

Chapter 13

  • SQ42 Level Design 3 - Social
    1x Design dev will work on 4 tasks (163% load) starting 2022-08-18 thru 2022-09-28

..~~~~~~~~~~~~~~~~~~..................================........|...==============........................

Charge/Drain T0

  • Weapon Feature Team
    2x Engineering devs will work on 8 tasks (80% load) starting 2022-08-18 thru 2022-11-09

........................................========~~~~~~~~......|...==========================............

Chemline

(Scheduled work ending soon!)

  • Narrative
    1x Design dev will work on 3 tasks (455% load) starting 2022-08-07 thru 2022-08-18

................~~~~..........................................|.====....................................

Ecosystem Enhancements

  • Planet Tech Team
    1x Engineering dev will work on 4 tasks (247% load) starting 2022-08-17 thru 2022-09-13

......................=============================...========|...=========.............................

Entity Properties Plugin

  • Editor Team
    1x Engineering dev will work on 4 tasks (247% load) starting 2022-08-17 thru 2022-09-13

..=========...=========...............========~~~~~~~~~~~~====|...=========.............................

FS-Tech-Anim - Asset Integration

  • Tech Animation Team
    7x Tech Content devs will work on 4 tasks (35% load) starting 2022-08-16 thru 2022-09-12

..=========...................=====...=====.......=====.......|...=========.............................

NPC Scheduler Service

  • Systemic Services and Tools Team
    2x Engineering devs will work on 5 tasks (154% load) starting 2022-08-04 thru 2022-08-31

......................................========................|=========................................

Persistent Hangars

  • US PU Gameplay Feature Team
    3x Engineering devs will work on 4 tasks (202% load) starting 2022-08-14 thru 2022-08-25

..............................................................|...====........~~~~~~~~~~~~~~~~..........

RaStar

  • Planet Tech Team
    2x Engineering devs will work on 4 tasks (123% load) starting 2022-08-17 thru 2022-09-13

..=================================...=========.......========|...=========.............................

Save/Load

  • SQ42 Feature Team
    2x Engineering devs will work on 5 tasks (76% load) starting 2022-08-04 thru 2022-09-28

..............................................................|=================........................

StarWords Improvements

  • Tools Team
    2x Engineering devs will work on 7 tasks (216% load) starting 2022-08-03 thru 2022-08-30

..=========...=========...=========...========~~~~~~~~~~~~~...|========...=====.........................

Unannounced Vehicle

(Starting soon!)

  • Vehicle Concept Art
    1x Art dev will work on 4 tasks (1667% load) starting 2022-08-14 thru 2022-08-18

..............................................................|...==............==============..........

Underground Facilities

  • EU Sandbox 1
    1x Art dev will work on 4 tasks (247% load) starting 2022-08-10 thru 2022-09-06

..............................................................|.=========...............................