ShinyTracker

RSI "Progress Tracker" Delta Reports

by ShinyHobo RSS

Scheduled Deliverables

as of 2022-06-22

There are currently 72 scheduled deliverables being worked on by 36 teams

25 deliverables are scheduled to begin work by 14 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 327 devs (out of ~512, or 64%) with 711 assignments scheduled to work on 72 observable deliverables. Of those deliverables, 29% are for SQ42 exclusively, with ~140 devs (27%) scheduled for approximately 1958 man-days. 28% of deliverables are shared between both projects.

47 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:

AR and Map Marker System Rework

(Scheduled work ending soon!)

  • UI Tech Team
    2x Engineering devs working on 7 tasks (96% load) thru 2022-06-24

..................................================|=....................................................

Archon

(Scheduled work ending soon!)

  • SQ42 Art
    14x Art devs working on 27 tasks (61% load) thru 2022-06-30

.==========================...........============|===..................................................

Argo SRV

  • Vehicle Content - EU
    4x Art devs working on 28 tasks (63% load) thru 2022-10-20
    1x Design dev will work on 12 tasks (270% load) starting 2022-07-03 thru 2022-09-15

................................==================|===================================..................
................................~~~~~~~~~~~~~~~~~~|...======================....~~~~~~~~~~~~~~~~~~~~~~..

Banu Merchantman

  • Weapon Content Team
    3x Art devs working on 5 tasks (111% load) thru 2022-06-23

..................========....========......======|=....................................................

  • Vehicle Content - EU
    12x Art devs will work on 16 tasks (30% load) starting 2022-07-03 thru 2022-09-15
    3x Design devs will work on 12 tasks (45% load) starting 2022-07-03 thru 2022-09-15

..================================================|...======================....======================..
..============~~~~~~~~==~~................======~~|...~~~~~~~~~~~~~~~~~~~~~~....======================..

Bug Fixing & Tech Debt

  • Actor Feature Team
    1x Engineering dev working on 3 tasks (107% load) thru 2022-07-07

............................................====~~|~~~~~..........==============........................

  • Actor Tech Team
    2x Engineering devs working on 13 tasks (59% load) thru 2022-07-07

..================================================|=====................................................

  • Arena Commander Feature Team
    2x Design devs working on 8 tasks (70% load) thru 2022-07-07
    4x Engineering devs working on 8 tasks (18% load) thru 2022-07-07

..======================....======================|=====................................................
..~~~~~~~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~~~~~~~|~~~~~................................................

  • Audio
    26x Audio devs working on 6 tasks (12% load) thru 2022-06-30

..==......==................============....======|===..................................................

  • Engine Team
    4x Engineering devs working on 7 tasks (29% load) thru 2022-07-07

.~================~~~~~~~~~.================~~~~~~|~~~~~................................................

  • Graphics Team
    10x Engineering devs working on 20 tasks (167% load) thru 2022-06-29
    2x Tech Content devs working on 4 tasks (167% load) thru 2022-06-29

....................=======...................====|===..................................................
....................~~~~~~~...................====|===..................................................

  • Live Tools Team
    4x Engineering devs working on 7 tasks (31% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 4x devs

..........................========================|====================================================.

  • Network Team
    2x Engineering devs working on 7 tasks (61% load) thru 2022-06-30

..=========.......=====...========================|===..................................................

  • Physics Team
    4x Engineering devs working on 9 tasks (21% load) thru 2022-06-29

..================================================|===..................................................

  • SQ42 UI Feature Team
    1x Engineering dev working on 3 tasks (200% load) thru 2022-07-07

..............................====..............==|=====................................................

  • Tools Team
    5x Engineering devs working on 13 tasks (24% load) thru 2022-07-05

..================================================|====.................................................

  • UI Tech Team
    4x Engineering devs working on 3 tasks (50% load) thru 2022-07-07

..====........................====..............==|=====................................................

  • Vehicle Content - US
    3x Tech Content devs working on 3 tasks (67% load) thru 2022-06-23

....====........========....................======|=......................~~~~~~....................====
..................................................|.......======================........................

  • Vehicle Feature Team
    12x Engineering devs working on 13 tasks (21% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 12x devs
    3x Design devs will work on 4 tasks (171% load) starting 2022-07-07 thru 2022-07-20

..=================.......========================|=..==============..........======....................
..........................======..................|...======..................======....................

  • Mission Feature Team
    3x Design devs will work on 13 tasks (42% load) starting 2022-07-01 thru 2022-12-22

..................................................|.====================================================

  • Props Team
    12x Art devs will work on 18 tasks (625% load) starting 2022-06-26 thru 2022-06-30
    2x Tech Content devs will work on 4 tasks (833% load) starting 2022-06-26 thru 2022-06-30

......====........====..======....==........==....|.==..................................................
......====........====....====....==........==....|.==..................................................

Building Interiors

  • Location Concept Art
    7x Art devs working on 3 tasks (13% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 7x devs

......................................============|=====================================================

  • MTL Sandbox 1
    14x Art devs will work on 10 tasks (17% load) starting 2022-07-07 thru 2022-09-14
    4x Design devs will work on 6 tasks (36% load) starting 2022-07-07 thru 2022-09-14

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============....|...======================..======================....
..~~~~~~~~~~~~~~~~~~~~~...........................|...======================..======================....

Cargo System Refactor

  • EU Landing Zone Team
    3x Art devs working on 2 tasks (28% load) thru 2022-06-30

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~........========|===..................................................

  • US PU Gameplay Feature Team
    3x Engineering devs will work on 5 tasks (37% load) starting 2022-07-03 thru 2022-08-25

..~~~~~~~~========~~~~~~~~~~~~================....|...~~~~~~~~~~~~~~~~..................................

Chapter 01

(Scheduled work ending soon!)

  • Cinematics Team
    3x Animation devs working on 26 tasks (21% load) thru 2022-06-29
    2x Design devs working on 18 tasks (21% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~======~~~~~~~~~~~~~~~~~~|~~~..................................................

  • Gameplay Story
    5x Animation devs working on 14 tasks (25% load) thru 2022-06-30

..........................~~~~....~~~~............|.....................................................
..~~~~....................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 26 tasks (19% load) thru 2022-06-22

.~====================~~~~~~~~====================|=....................................................

  • SQ42 Level Design 3 - Social
    3x Design devs working on 4 tasks (57% load) thru 2022-06-30

..~~~~~~~~~~~~~~~~======..====....====....========|===..................................................

Chapter 02

(Scheduled work ending soon!)

  • Cinematics Team
    1x Design dev working on 6 tasks (111% load) thru 2022-06-29

..........................~~~~~~~~~~~~~~~~~~~~~~..|.....................................................
........................................~~~~~~~~~~|~~~..................................................

Chapter 04

(Scheduled work ending soon!)

  • Gameplay Story
    5x Animation devs working on 10 tasks (67% load) thru 2022-06-30

.......~~~~...........................~~~~....~~~~|~~~..................................................
......................................~~~~........|.....................................................

Chapter 06

(Scheduled work ending soon!)

  • SQ42 Level Design 3 - Social
    2x Design devs working on 8 tasks (72% load) thru 2022-06-30

..====~~~~~~~~~~~~======..========================|===..................................................

Chapter 10

(Scheduled work ending soon!)

  • SQ42 Level Design 3 - Social
    1x Design dev working on 8 tasks (134% load) thru 2022-06-30

..~~~~~~..................========~~~~============|===..................................................

Chapter 11

(Scheduled work ending soon!)

  • Cinematics Team
    3x Design devs working on 7 tasks (28% load) thru 2022-06-29
    2x Animation devs working on 4 tasks (83% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~.....~~~~~~~~~~~~~~~~~~|~~~..................................................
..........................~~~~~~~~~~~~~~~~....~~~~|~~~..................................................

  • Gameplay Story
    4x Animation devs working on 10 tasks (22% load) thru 2022-06-30

..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

Chapter 12

(Scheduled work ending soon!)

  • Cinematics Team
    3x Design devs working on 28 tasks (14% load) thru 2022-06-29
    3x Animation devs working on 21 tasks (22% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

  • Gameplay Story
    5x Animation devs working on 20 tasks (36% load) thru 2022-06-30

..............~~~~~.......~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................
..........................~~~~....~~~~~~~~........|.....................................................

  • SQ42 Level Design 1 - FPS
    4x Design devs working on 20 tasks (24% load) thru 2022-06-30

.~====~~~~~~~~~~~~~~~~~~~~~~~~====================|===..................................................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 11 tasks (31% load) thru 2022-06-22

..........................~~~~====================|=....................................................

Chapter 13

(Scheduled work ending soon!)

  • SQ42 Level Design 3 - Social
    1x Design dev working on 5 tasks (157% load) thru 2022-06-30

..~~~~~~~~~~~~~~~~~~..................============|===..................................................

Chapter 14

(Scheduled work ending soon!)

  • Cinematics Team
    3x Design devs working on 9 tasks (28% load) thru 2022-06-29
    3x Animation devs working on 9 tasks (28% load) thru 2022-06-29

..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................
..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

  • Gameplay Story
    3x Animation devs working on 8 tasks (24% load) thru 2022-06-30

..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

  • SQ42 Level Design 1 - FPS
    6x Design devs working on 41 tasks (20% load) thru 2022-06-30

.=====================~~~~~~~~====================|===..................................................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 22 tasks (46% load) thru 2022-06-22

......================~~~~~~~~====================|=....................................................

Chapter 15

(Scheduled work ending soon!)

  • Cinematics Team
    3x Animation devs working on 28 tasks (17% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~.......................|.....................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

  • Gameplay Story
    5x Animation devs working on 11 tasks (47% load) thru 2022-06-30

..............~~~~~...~~~~~~..............~~~~~~~~|~~~..................................................

Chapter 18

(Scheduled work ending soon!)

  • Gameplay Story
    4x Animation devs working on 10 tasks (83% load) thru 2022-06-30

..............~~~~~...........................~~~~|~~~..................................................

Chapter 19

(Scheduled work ending soon!)

  • Cinematics Team
    2x Animation devs working on 8 tasks (37% load) thru 2022-06-29

..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

  • Gameplay Story
    5x Animation devs working on 10 tasks (67% load) thru 2022-06-30

..................~~~~~.......~~~~~~~~........~~~~|~~~..................................................
..................................~~~~............|.....................................................

  • SQ42 Level Design 1 - FPS
    3x Design devs working on 7 tasks (100% load) thru 2022-06-30

......~~~~~~~~~~~~~~~~~~~~~~..............========|===..................................................

Chapter 20

(Scheduled work ending soon!)

  • Gameplay Story
    4x Animation devs working on 10 tasks (83% load) thru 2022-06-30

..............................................~~~~|~~~..................................................

Chapter 22

(Scheduled work ending soon!)

  • Gameplay Story
    4x Animation devs working on 10 tasks (83% load) thru 2022-06-30

..............................................~~~~|~~~..................................................

  • SQ42 Level Design 1 - FPS
    6x Design devs working on 4 tasks (28% load) thru 2022-06-30

......~~~~============~~~~~~..............========|===..................................................

Chapter 23

(Scheduled work ending soon!)

  • Cinematics Team
    3x Animation devs working on 17 tasks (52% load) thru 2022-06-29

..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~.......................|.....................................................

  • Gameplay Story
    5x Animation devs working on 10 tasks (67% load) thru 2022-06-30

..................~~~~~.......~~~~~~~~........~~~~|~~~..................................................
..................................~~~~............|.....................................................

Chapter 25

(Scheduled work ending soon!)

  • Cinematics Team
    1x Design dev working on 5 tasks (208% load) thru 2022-06-29

..........................~~~~~~~~............~~~~|~~~..................................................

Chapter 26

(Scheduled work ending soon!)

  • SQ42 Art
    9x Art devs working on 42 tasks (28% load) thru 2022-06-30

.=================================================|===..................................................

  • SQ42 Level Design 1 - FPS
    7x Design devs working on 7 tasks (43% load) thru 2022-06-30

.===========================..............========|===..................................................

Character Work

(Scheduled work ending soon!)

  • Audio
    5x Audio devs working on 11 tasks (61% load) thru 2022-06-30

....================................==============|===..................................................

  • Facial Animation
    6x Animation devs working on 20 tasks (33% load) thru 2022-06-30

....==============================================|===..................................................

Charge/Drain T0

  • Weapon Feature Team
    1x Engineering dev working on 4 tasks (126% load) thru 2022-07-07

........................................==========|=====..........==============........................

Chemline

(Scheduled work ending soon!)

  • SQ42 Art
    6x Art devs working on 39 tasks (18% load) thru 2022-06-30

.=================================================|===..................................................

DGS Crash Recovery

(Scheduled work ending soon!)

  • Network Team
    1x Engineering dev working on 12 tasks (165% load) thru 2022-06-30

..................================================|===..................................................

DGS Mesh Node

(Scheduled work ending soon!)

  • Network Team
    3x Engineering devs working on 12 tasks (55% load) thru 2022-06-30

..................================================|===..................................................

Drake Corsair

  • Vehicle Content - US
    5x Art devs working on 15 tasks (62% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 5x devs
    2x Design devs working on 7 tasks (72% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 2x devs
    3x Tech Content devs will work on 8 tasks (54% load) starting 2022-07-07 thru 2022-08-17

..======================....======================|=..======............................................
..======================....======================|=..==========........................................
........................................~~~~......|...~~~~~~~~~~~~~~....................................

Drake Vulture

(Scheduled work ending soon!)

  • Narrative
    1x Design dev working on 1 task (72% load) thru 2022-07-05

................................................==|====.................................................

Entity Properties Plugin

(Scheduled work ending soon!)

  • Editor Team
    1x Engineering dev working on 7 tasks (212% load) thru 2022-07-05

..=========...=========...............============|====.................................................

EVA T2

(Scheduled work ending soon!)

  • Actor Feature Team
    2x Animation devs working on 15 tasks (34% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~................................................

  • Actor Tech Team
    2x Engineering devs working on 10 tasks (88% load) thru 2022-07-07

............................======================|=====................................................

FPS Devices T1

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 4 tasks (63% load) thru 2022-07-07

..............==============............~~~~~~~~~~|~~~~~................................................

FPS Radar / Scanning

(Scheduled work ending soon!)

  • Actor Feature Team
    2x Engineering devs working on 11 tasks (57% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~~~~~~~......................|.....................................................
..........======================================~~|~~~~~................................................

  • Vehicle Feature Team
    1x Design dev working on 4 tasks (163% load) thru 2022-06-23

......................................============|=....................................................

Gainey

(Scheduled work ending soon!)

  • SQ42 Art
    4x Art devs working on 10 tasks (22% load) thru 2022-06-30

..........................~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................

Hacking T0

  • Props Team
    2x Art devs working on 7 tasks (324% load) thru 2022-06-23

..............................................====|=....................................................

HEX

  • Live Tools Team
    5x Engineering devs working on 7 tasks (21% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 5x devs

..=====================...========================|===~~~~~~~~~~~~~~~~~~~~~~~~~~~~=====================.

Jump Points

  • EU Sandbox 1
    1x Art dev working on 2 tasks (152% load) thru 2022-06-27

..............~~~~~...................====....====|==.......................=========...................

Ladders T1

(Scheduled work ending soon!)

  • Actor Feature Team
    2x Animation devs working on 9 tasks (75% load) thru 2022-07-07

............................====================~~|~~~~~................................................

Lean Over Cover

(Scheduled work ending soon!)

  • Actor Tech Team
    1x Engineering dev working on 14 tasks (246% load) thru 2022-07-07

............................======================|=====................................................

Login Flow

(Scheduled work ending soon!)

  • Game Services Team
    7x Engineering devs working on 23 tasks (30% load) thru 2022-06-30

..====================~~~~~~~~====================|===..................................................

  • Live Tools Team
    2x Engineering devs working on 12 tasks (57% load) thru 2022-06-30

......================~~~~~~~~====================|===..................................................

Long Term Persistence Enhancements

(Scheduled work ending soon!)

  • Persistent Tech Team
    1x Engineering dev working on 5 tasks (157% load) thru 2022-06-30

......................................============|===..................................................

Mantle T2

(Scheduled work ending soon!)

  • Actor Feature Team
    1x Engineering dev working on 4 tasks (110% load) thru 2022-07-07

........................................========~~|~~~~~................................................

Map and Radar System Rework

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    2x Engineering devs working on 12 tasks (114% load) thru 2022-07-07
    2x Art devs working on 6 tasks (109% load) thru 2022-07-07

..............................====================|=====................................................
..........................................========|=====................................................

Miscellaneous Support

  • Actor Feature Team
    3x Animation devs working on 27 tasks (40% load) thru 2022-12-30
    1x Engineering dev working on 25 tasks (111% load) thru 2022-12-30
    3x Design devs working on 27 tasks (40% load) thru 2022-12-30

..==============================================~~|~~~~~~~==============================================
..==============================================~~|~~~~~~~==============================================
..==============================================~~|~~~~~~~==============================================
..==========================......................|.....................................................

  • Actor Tech Team
    5x Engineering devs working on 15 tasks (14% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~======~~~~~~~~~~~~~~~~~~~~~~|~~~~~................................................

  • Arena Commander Feature Team
    2x Design devs working on 11 tasks (84% load) thru 2022-07-07
    3x Engineering devs working on 14 tasks (42% load) thru 2022-07-07

........................==========================|=====................................................
....====================~~~~======================|=====................................................

  • Editor Team
    1x Design dev working on 13 tasks (118% load) thru 2022-07-05

..================================================|====.................................................

  • Gameplay Story
    1x Tech Content dev working on 3 tasks (128% load) thru 2022-06-30

.=====.===============~~~~~~..====........========|===..................................................

  • Lighting Team
    9x Art devs working on 14 tasks (16% load) thru 2022-06-30

......============================================|===..................................................

  • Motion Capture Team
    5x Animation devs working on 15 tasks (26% load) thru 2022-06-30

..========================================~~~~~~~~|~~~..................................................

  • SQ42 Feature Team
    2x Engineering devs working on 15 tasks (47% load) thru 2022-06-30

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~====================|===..................................................

  • Tools Team
    2x Engineering devs working on 15 tasks (68% load) thru 2022-07-05

..================================================|====.................................................

  • UI Tech Team
    3x Engineering devs working on 10 tasks (63% load) thru 2022-07-07

..............................====================|=====................................................

  • Vehicle Feature Team
    12x Engineering devs working on 10 tasks (11% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 12x devs
    3x Design devs working on 8 tasks (64% load) thru 2022-06-23

..............====================================|=..==========================..======================
..............................====================|=..........==================..======..........======

  • Weapon Feature Team
    5x Design devs working on 33 tasks (30% load) thru 2022-12-30

..==============================================~~|~~~~~~~==============================================

mobiGlas Rework

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    1x Design dev working on 6 tasks (217% load) thru 2022-07-07

..........................................========|=====................................................
......................................======......|.....................................................

Name Resolving API

(Scheduled work ending soon!)

  • Persistent Tech Team
    1x Engineering dev working on 5 tasks (333% load) thru 2022-06-30

..........=========...........................====|===..................................................

Outpost Homestead - Independent & Outlaw

  • EU Sandbox 1
    10x Art devs working on 15 tasks (27% load) thru 2022-09-06
    4x Design devs working on 7 tasks (31% load) thru 2022-09-06

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....====|======================...=================...=======.
.~~~~~~~~~~.~~~~~~~~~~~~~~~.~~~~~~....====....====|======================...............................

  • Lighting Team
    6x Art devs working on 6 tasks (31% load) thru 2022-06-30

..............=========...............============|===..................................................

Outpost Theme Variants

  • EU Sandbox 1
    4x Design devs working on 4 tasks (76% load) thru 2022-06-27
    2x Art devs working on 4 tasks (152% load) thru 2022-06-27

.~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~~========....====|==...................=====================...=======.
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~========....====|==...................................................

Persistent Streaming and Server Meshing

  • Game Services Team
    10x Engineering devs working on 13 tasks (11% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 10x devs

..====================~~~~~~~~====================|====================================================.

  • Network Team
    9x Engineering devs working on 2 tasks (15% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 9x devs

..=====.......============....................====|=====================================================

  • Persistent Tech Team
    4x Engineering devs working on 19 tasks (42% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 4x devs

..====================~~~~~~~~====================|=====================================================

  • Vehicle Feature Team
    3x Engineering devs working on 4 tasks (54% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 3x devs

......................................============|=..==========================........................

  • Actor Feature Team
    2x Animation devs will work on 4 tasks (61% load) starting 2022-07-07 thru 2022-08-17

....................................============..|...~~~~==========....................................

  • Mission Feature Team
    3x Engineering devs will work on 13 tasks (30% load) starting 2022-07-01 thru 2022-12-22

.~========================~~~~~~~~~~~~~~~~~~~~~~~~|.~~~~~~~~~~~~~~~~~~~~~~~~============================

  • US PU Gameplay Feature Team
    4x Engineering devs will work on 4 tasks (16% load) starting 2022-07-03 thru 2022-08-25

..................................============....|...~~~~~~~~~~~~~~~~..................................

Player Interaction Experience T0 - Hints & Interactions

  • Actor Feature Team
    2x Engineering devs working on 6 tasks (52% load) thru 2022-08-17

............................................====~~|~~~~~~~==========....................................

  • Narrative
    1x Design dev working on 3 tasks (217% load) thru 2022-07-05

................................................==|====.................................................

Player Interaction Experience T1 - Lockers & Inventory

  • Actor Feature Team
    1x Art dev working on 13 tasks (112% load) thru 2022-09-28
    1x Design dev working on 13 tasks (61% load) thru 2022-09-28
    1x Engineering dev will work on 13 tasks (114% load) starting 2022-07-07 thru 2022-12-30

............................====================~~|~~~~~~~======================........................
............................~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~~~........................
..................................................|...==================================================

Player Interaction Experience T2 - Visor HUD & Helmet

  • Actor Feature Team
    1x Design dev working on 13 tasks (61% load) thru 2022-09-28

............................~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~~~........................
..................................................|...............======================================
..............==============......................|.....................................................

Player Reflection

(Scheduled work ending soon!)

  • Actor Tech Team
    1x Engineering dev working on 14 tasks (123% load) thru 2022-07-07

............................~~~~~~~~~~~~~~~~~~~~~~|~~~~~................................................

Proximity Mine

(Scheduled work ending soon!)

  • Narrative
    2x Design devs working on 5 tasks (181% load) thru 2022-07-05

................................................==|====.................................................

Pyro Space Stations

  • EU Landing Zone Team
    15x Art devs working on 24 tasks (107% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 15x devs
    3x Design devs working on 6 tasks (133% load) thru 2022-06-30
    ↳ will continue 2022-07-07 with 3x devs

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....====|=====================..======..=================.....
.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~~~~~========....====|=====================..======..=================.....

Quantum Travel Experience

  • Vehicle Feature Team
    2x Engineering devs working on 4 tasks (81% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 2x devs

......................................============|=..======================......==================....

Rescue/Transport Mission

  • Narrative
    2x Design devs working on 2 tasks (72% load) thru 2022-07-05

....====........................................==|====.................................................

Resource Management

  • Vehicle Feature Team
    3x Engineering devs working on 4 tasks (54% load) thru 2022-06-23
    ↳ will continue 2022-07-07 with 3x devs
    2x Design devs working on 4 tasks (81% load) thru 2022-06-23

......................................============|=..======================............................
......................................============|=..............==============........................

  • EU PU Gameplay Feature Team
    2x Design devs will work on 5 tasks (38% load) starting 2022-07-07 thru 2022-08-31
    2x Engineering devs will work on 11 tasks (66% load) starting 2022-07-07 thru 2022-11-22

..........................~~~~~~~~~~~~~~~~~...~~~~|...~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~...~~~~~.
..........~~~~~~~~~.......=================...====|...=========================================...=====.

RSI Scorpius

(Scheduled work ending soon!)

  • Vehicle Content - US
    2x Tech Content devs working on 3 tasks (100% load) thru 2022-06-23

..==........................~~~~............======|=....................................................

Satellites - Points of Interest

  • Location Concept Art
    2x Art devs working on 5 tasks (79% load) thru 2022-06-30

......................................============|===........................==========================

Shops and Patrons

(Scheduled work ending soon!)

  • Facial Animation
    4x Animation devs working on 5 tasks (83% load) thru 2022-06-30

..====....................============........====|===..................................................

Space Mines

(Scheduled work ending soon!)

  • Weapon Feature Team
    1x Engineering dev working on 4 tasks (63% load) thru 2022-07-07

........................................~~~~~~~~~~|~~~~~................................................

StarWords Improvements

(Scheduled work ending soon!)

  • Tools Team
    2x Engineering devs working on 12 tasks (182% load) thru 2022-07-05

..=========...=========...=========...============|====.................................................

Theaters of War - Miscellaneous Support

(Scheduled work ending soon!)

  • Firesprite Team
    2x Engineering devs working on 8 tasks (7% load) thru 2022-06-30
    4x Design devs working on 15 tasks (10% load) thru 2022-06-30
    4x Art devs working on 15 tasks (7% load) thru 2022-06-30

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~================|===..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~================|===..................................................

Unannounced Vehicle

(Scheduled work ending soon!)

  • Vehicle Content - EU
    2x Art devs working on 26 tasks (126% load) thru 2022-06-30

............~~~~~~~~~~~~~~~~======================|.....................................................
....==============================================|===..................................................

Unannounced Vehicle

  • Vehicle Content - EU
    4x Art devs working on 32 tasks (67% load) thru 2022-10-20
    2x Design devs will work on 12 tasks (135% load) starting 2022-07-03 thru 2022-09-15

............................======================|===================================..................
............................~~~~~~~~~~~~~~~~~~~~~~|...======================....~~~~~~~~~~~~~~..........

Underground Facilities

  • Location Concept Art
    4x Art devs working on 13 tasks (57% load) thru 2022-06-30

..=====================...========================|===..................................................

  • EU Sandbox 2
    1x Art dev will work on 2 tasks (238% load) starting 2022-06-28 thru 2022-07-12
    3x Design devs will work on 4 tasks (159% load) starting 2022-06-28 thru 2022-07-12

.=============================....................|.=====...................=====.......................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~....................|.=====...................=====.......................

Visor/Lens Rework

(Scheduled work ending soon!)

  • SQ42 UI Feature Team
    1x Engineering dev working on 4 tasks (256% load) thru 2022-06-24

..............................====..........======|=....................................................
..........................................======..|.....................................................

Weapon Misfire & Wear

  • Weapon Feature Team
    1x Engineering dev working on 9 tasks (109% load) thru 2022-09-28

............................................====~~|~~~~~~~======================........................

Zero G Push & Pull

(Scheduled work ending soon!)

  • Actor Feature Team
    2x Animation devs working on 13 tasks (29% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~................................................


The following deliverables are scheduled to begin (or continue) work within two weeks

Asteroid Facilities

(Starting soon!)

  • EU Sandbox 1
    1x Art dev will work on 5 tasks (119% load) starting 2022-06-28 thru 2022-09-06

..................................................|.=====================...........=========...=======.

Bounty Hunter V2

  • Mission Feature Team
    2x Design devs will work on 6 tasks (40% load) starting 2022-07-01 thru 2022-09-22

..................................................|.~~~~~~~~~~~~~~~~~~~~~~~~~~..........................

  • US PU Gameplay Feature Team
    1x Design dev will work on 4 tasks (126% load) starting 2022-07-03 thru 2022-08-25

..................................................|...================........~~~~~~~~~~~~~~~~..........

Cave Archetypes

  • EU Sandbox 2
    5x Art devs will work on 10 tasks (238% load) starting 2022-06-28 thru 2022-07-12
    1x Tech Content dev will work on 2 tasks (238% load) starting 2022-06-28 thru 2022-07-12

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~....................|.=====...................=====.......................
..................................................|.=====...................=====.......................

Commodity Kiosk

  • US PU Gameplay Feature Team
    3x Art devs will work on 4 tasks (42% load) starting 2022-07-03 thru 2022-08-25

..=================.......~~~~~~~~~~~~~~~~====....|...================..................................

Derelict Spaceships - Points of Interest

  • MTL Sandbox 1
    4x Design devs will work on 6 tasks (36% load) starting 2022-07-07 thru 2022-09-14
    8x Art devs will work on 11 tasks (33% load) starting 2022-07-07 thru 2022-09-14

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============....|...======================..======================....
.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~============....|...======================..======================....

Dynamic Events

  • Mission Feature Team
    7x Design devs will work on 15 tasks (18% load) starting 2022-07-01 thru 2022-12-22

..================================================|.====~~~~~~~~~~~~~~~~~~~~============================

  • US PU Gameplay Feature Team
    2x Design devs will work on 4 tasks (63% load) starting 2022-07-03 thru 2022-08-25

..~~~~~~~~~~~~~~~~~.......~~~~~~~~~~~~~~~~~~~~....|...================........================..........

Dynamic Mission System

  • Mission Feature Team
    1x Engineering dev will work on 7 tasks (70% load) starting 2022-07-01 thru 2022-09-22

..........................~~~~~~~~~~~~~~~~~~~~~~~~|.~~~~~~~~~~~~~~~~~~~~~~~~~~..........................

Dynamic Population

  • Mission Feature Team
    1x Engineering dev will work on 3 tasks (185% load) starting 2022-07-01 thru 2022-07-28

....................................~~~~~~~~~~~~~~|.==========..........................................

Ecosystem Enhancements

  • Planet Tech Team
    1x Engineering dev will work on 8 tasks (476% load) starting 2022-07-05 thru 2022-08-02

......................============================|...=========...=========...=============.............

Flak Ammunition

(Starting soon!)

  • Weapon Feature Team
    1x Engineering dev will work on 7 tasks (120% load) starting 2022-07-07 thru 2022-09-28

..................................................|...==========================........................

Infiltrate/Defend Mission

  • Mission Feature Team
    3x Design devs will work on 2 tasks (85% load) starting 2022-07-01 thru 2022-07-14

..........~~~~~~~~~~~~~~~~........................|.======..............................................

Life Support T0

  • EU PU Gameplay Feature Team
    1x Design dev will work on 5 tasks (76% load) starting 2022-07-07 thru 2022-08-31
    1x Engineering dev will work on 5 tasks (152% load) starting 2022-07-07 thru 2022-08-31

..~~~~~~~~~~~~~~~~~...~~~~~~~~~~~~~~~~~~~~~...~~~~|...~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~...~~~~~.
..=================...=================...........|...==================..=====================...=====.

Lorville Cityscape

  • MTL Sandbox 1
    4x Art devs will work on 6 tasks (36% load) starting 2022-07-07 thru 2022-09-14

..................................................|...======================..======================....

New Player Experience

(Starting soon!)

  • EU Landing Zone Team
    2x Art devs will work on 3 tasks (93% load) starting 2022-07-07 thru 2022-08-03

..................................................|...==========......======......=========.............

Ocean Shader Improvements

  • Planet Tech Team
    1x Engineering dev will work on 5 tasks (119% load) starting 2022-07-05 thru 2022-09-13

..........................................========|...=====================...=============.............

Prone T1

(Starting soon!)

  • Actor Feature Team
    1x Engineering dev will work on 13 tasks (114% load) starting 2022-07-07 thru 2022-12-30
    2x Animation devs will work on 13 tasks (57% load) starting 2022-07-07 thru 2022-12-30

..................................................|...==================================================
..................................................|...==================================================

Pyro System, Planet, and Mission Setup

  • US PU Gameplay Feature Team
    1x Design dev will work on 4 tasks (126% load) starting 2022-07-03 thru 2022-08-25

......................................========....|...================........================..........

Quantum Simulation

  • Systemic Services and Tools Team
    5x Engineering devs will work on 15 tasks (31% load) starting 2022-07-07 thru 2022-12-15

.=================================================|...================================================..

RaStar

  • Planet Tech Team
    2x Engineering devs will work on 3 tasks (89% load) starting 2022-07-05 thru 2022-08-02

..=================================...=========...|...=========...=========...=====================.....

RSI Lynx

(Starting soon!)

  • Vehicle Concept Art
    1x Art dev will work on 3 tasks (278% load) starting 2022-07-03 thru 2022-07-21

..................................................|...======............................................

Salvage T0

  • EU PU Gameplay Feature Team
    1x Engineering dev will work on 3 tasks (122% load) starting 2022-07-07 thru 2022-08-17

..........................=================...====|...==============....................................

Unannounced Vehicle

  • Vehicle Concept Art
    4x Art devs will work on 7 tasks (75% load) starting 2022-07-03 thru 2022-08-11

............................==============........|...============......................................

Unannounced Vehicle

(Starting soon!)

  • Vehicle Concept Art
    2x Art devs will work on 7 tasks (127% load) starting 2022-07-03 thru 2022-08-18

..................................................|...==============....................................

Unannounced Vehicle

  • Vehicle Content - EU
    2x Design devs will work on 12 tasks (68% load) starting 2022-07-03 thru 2022-09-15
    2x Art devs will work on 4 tasks (185% load) starting 2022-07-03 thru 2022-07-21

..............========..........................~~|...~~~~~~~~~~~~~~~~~~~~~~............................
..............============........................|...======............................................

  • Vehicle Content - US
    3x Tech Content devs will work on 8 tasks (54% load) starting 2022-07-07 thru 2022-08-17

..................................................|...~~~~~~~~~~~~~~....................................

Virtual AI Service

  • Systemic Services and Tools Team
    1x Engineering dev will work on 4 tasks (121% load) starting 2022-07-07 thru 2022-08-31

..................=====...........................|...==================................................