ShinyTracker

RSI "Progress Tracker" Delta Reports

by ShinyHobo RSS

Scheduled Deliverables

as of 2022-04-13

There are currently 91 scheduled deliverables being worked on by 38 teams

9 deliverables are scheduled to begin work by 6 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 405 devs (out of ~512, or 79%) with 888 assignments scheduled to work on 91 observable deliverables. Of those deliverables, 20% are for SQ42 exclusively, with ~121 devs (24%) scheduled for approximately 1075 man-days. 25% of deliverables are shared between both projects.

3 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:

Animatable Gunner Helmet

  • SQ42 Character Art
    1x Art dev working on 5 tasks (124% load) thru 2022-04-21

..............================|===......................................................................

Atlas

  • Network Team
    5x Engineering devs working on 3 tasks (26% load) thru 2022-05-05

......=============.......====|=======..................................................................

Banu Merchantman

  • Vehicle Content - EU
    8x Art devs working on 26 tasks (31% load) thru 2022-06-23
    3x Design devs working on 5 tasks (43% load) thru 2022-05-05

..============================|=====================..======================....======================..
..============~~~~~~~~==~~..~~|~~~~~~~..~~~~~~~~~~......................................................

  • Weapon Content Team
    3x Art devs working on 4 tasks (89% load) thru 2022-05-05

..................========....|=======......========....................................................

  • Narrative
    2x Design devs will work on 1 task (76% load) starting 2022-04-17 thru 2022-04-28

..............................|.====....====............................................................

Bug Fixing & Tech Debt

  • Actor Tech Team
    2x Engineering devs working on 12 tasks (54% load) thru 2022-07-07

..============================|=========================................................................

  • Audio
    26x Audio devs working on 6 tasks (10% load) thru 2022-05-12

..==......==................==|=========....==========..................................................

  • Engine Team
    4x Engineering devs working on 6 tasks (26% load) thru 2022-07-07

.=================~~~~~~~~~.==|=============~~~~~~~~~~~~................................................

  • Live Tools Team
    2x Engineering devs working on 6 tasks (53% load) thru 2022-06-30

..........................====|=================================================........................

  • Network Team
    2x Engineering devs working on 6 tasks (53% load) thru 2022-06-30

..=========.......=====...====|=======================..................................................

  • Physics Team
    4x Engineering devs working on 8 tasks (19% load) thru 2022-06-29

..============================|=======================..................................................

  • Vehicle Content - EU
    17x Art devs working on 1 task (25% load) thru 2022-04-14

..................==========..|.........==============......................====........................
..........................==..|=..........============......................====..............========..

  • Vehicle Experience Team
    4x Design devs working on 4 tasks (56% load) thru 2022-04-14
    3x Engineering devs working on 4 tasks (74% load) thru 2022-04-14

..=============.......========|=..==================..~~~~~~..................==========================
..=====...............========|=......................======..................==========................

  • Vehicle Feature Team
    9x Engineering devs working on 2 tasks (26% load) thru 2022-04-14

..=================.......====|=......................======..................======....................

  • Props Team
    12x Art devs will work on 9 tasks (313% load) starting 2022-04-24 thru 2022-04-28
    2x Tech Content devs will work on 2 tasks (417% load) starting 2022-04-24 thru 2022-04-28

......====........====..======|...==........==......==..................................................
......====........====....====|...==........==......==..................................................

Building Interiors

  • Location Concept Art
    7x Art devs working on 8 tasks (20% load) thru 2022-06-30

..........................====|=========================================================================

  • MTL Sandbox 1
    10x Art devs working on 25 tasks (5% load) thru 2022-06-02

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~|~~~============........======================..======================....
..~~~~~~~~~~~~~~~~~~~~~.......|.......................======================..======================....

Cargo System Refactor

  • Actor Feature Team
    1x Engineering dev working on 1 task (152% load) thru 2022-04-14

..==========................==|=........................................................................

  • Props Team
    2x Art devs working on 2 tasks (152% load) thru 2022-04-21

..............====....======..|===......................................................................

  • US PU Gameplay Feature Team
    3x Engineering devs working on 12 tasks (30% load) thru 2022-06-02
    2x Design devs working on 3 tasks (32% load) thru 2022-05-05
    2x Art devs working on 3 tasks (53% load) thru 2022-05-05

..~~~~~~~~========~~~~~~~~~~~~|=======~~~~~~~~..........................................................
..........................~~~~|~~~~~~~..................................................................
..........................====|=======..................................................................

Chapter 01

  • Cinematics Team
    3x Animation devs working on 24 tasks (17% load) thru 2022-06-29
    2x Design devs working on 16 tasks (19% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~====|=~~~~~~~~~~~~~~~~~~~~~~..................................................

  • Gameplay Story
    5x Animation devs working on 8 tasks (14% load) thru 2022-06-30
    1x Tech Content dev will work on 1 task (76% load) starting 2022-04-24 thru 2022-05-05

..~~~~....................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................
..........................~~~~|...~~~~..................................................................

Chapter 02

  • Cinematics Team
    2x Animation devs working on 3 tasks (24% load) thru 2022-06-08

..........................~~~~|~~~~~~~~~~~~~~~~~........................................................
..............................|.........~~~~~~~~~~~~~~..................................................

Chapter 06

  • Cinematics Team
    2x Design devs working on 22 tasks (20% load) thru 2022-04-20

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~......................................................................

  • Gameplay Story
    5x Animation devs working on 4 tasks (17% load) thru 2022-05-19
    1x Tech Content dev will work on 2 tasks (67% load) starting 2022-04-24 thru 2022-05-19

.~~~~~.~~~~~~~~.......~~~~~~..|~~~~~~~~~~~..............................................................
..............................|...~~~~~~~~..............................................................

Chapter 08

  • Gameplay Story
    5x Animation devs working on 5 tasks (23% load) thru 2022-04-21

..~~~~....~~~~~.......~~~~~~~~|~~~........~~~~..........................................................
..........................~~~~|.........................................................................

Chapter 10

  • Cinematics Team
    2x Design devs working on 22 tasks (20% load) thru 2022-04-20

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~......................................................................

  • Gameplay Story
    5x Animation devs working on 7 tasks (18% load) thru 2022-05-19
    1x Tech Content dev will work on 2 tasks (67% load) starting 2022-04-24 thru 2022-05-19

.......~~~~~~~~.......~~~~~~~~|~~~~~~~~~~~..............................................................
..........................~~~~|...~~~~~~~~..............................................................

Chapter 11

  • Gameplay Story
    4x Animation devs working on 6 tasks (13% load) thru 2022-06-30

..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

  • Cinematics Team
    3x Design devs will work on 3 tasks (12% load) starting 2022-04-21 thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~...|.~~~~~~~~~~~~~~~~~~~~~~..................................................

Chapter 12

  • Cinematics Team
    3x Design devs working on 24 tasks (12% load) thru 2022-06-29
    3x Animation devs working on 13 tasks (15% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

  • Gameplay Story
    5x Animation devs working on 8 tasks (14% load) thru 2022-06-30
    1x Tech Content dev will work on 2 tasks (67% load) starting 2022-04-24 thru 2022-05-19

..............~~~~~.......~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................
..........................~~~~|...~~~~~~~~..............................................................

  • Narrative
    1x Design dev working on 1 task (76% load) thru 2022-04-14

............................~~|~........................................................................

  • SQ42 Art
    5x Art devs working on 7 tasks (63% load) thru 2022-05-05

..........................====|=======..................................................................

Chapter 14

  • Cinematics Team
    3x Design devs working on 5 tasks (15% load) thru 2022-06-29
    1x Animation dev working on 4 tasks (37% load) thru 2022-06-29

..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................
..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

  • Gameplay Story
    3x Animation devs working on 6 tasks (18% load) thru 2022-06-30

..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

  • SQ42 Art
    1x Cinematics dev working on 2 tasks (145% load) thru 2022-04-21

..........................====|===......................................................................

  • Narrative
    1x Design dev will work on 1 task (152% load) starting 2022-04-17 thru 2022-04-28

..............................|.====....................................................................

Chapter 19

  • Cinematics Team
    2x Animation devs working on 4 tasks (19% load) thru 2022-06-29

..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

  • Gameplay Story
    5x Animation devs working on 3 tasks (20% load) thru 2022-05-05
    1x Tech Content dev will work on 1 task (76% load) starting 2022-04-24 thru 2022-05-05

..................~~~~~.......|~~~~~~~........~~~~~~~~..................................................
..............................|...~~~~..................................................................

Chapter 20

  • Cinematics Team
    2x Design devs working on 12 tasks (20% load) thru 2022-06-08

.~~~~~~~~~~~~~~~~~~~~~~~~~~...|.........................................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~........................................................

Chapter 21

(Scheduled work ending soon!)

  • Cinematics Team
    1x Design dev working on 1 task (42% load) thru 2022-04-20

.~~~~~~~~~~~~~~~~~~~~~~~~~~...|.........................................................................
..........................~~~~|~~~......................................................................

Chapter 23

  • Cinematics Team
    3x Animation devs working on 5 tasks (15% load) thru 2022-06-29

.~~~~~~~~~~~~~~~~~~~~~~~~~~...|.........................................................................
..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

  • Gameplay Story
    5x Animation devs working on 3 tasks (20% load) thru 2022-05-05
    1x Tech Content dev will work on 1 task (76% load) starting 2022-04-24 thru 2022-05-05

..................~~~~~.......|~~~~~~~........~~~~~~~~..................................................
..............................|...~~~~..................................................................

Chapter 25

  • Cinematics Team
    1x Design dev working on 1 task (42% load) thru 2022-04-20

..........................~~~~|~~~............~~~~~~~~..................................................

Chapter 26

  • SQ42 Art
    9x Art devs working on 22 tasks (15% load) thru 2022-06-30

.=============================|=======================..................................................

Character Work

  • Character Tech Art
    7x Tech Content devs working on 11 tasks (17% load) thru 2022-06-16

......========================|===================......................................................

  • Facial Animation
    6x Animation devs working on 12 tasks (20% load) thru 2022-06-30

....==========================|=======================..................................................

  • Motion Capture Team
    5x Animation devs working on 7 tasks (26% load) thru 2022-05-19

......=========.......~~~~~~~~|~~~~~~~~~~~..............................................................

  • SQ42 Character Art
    9x Art devs working on 25 tasks (18% load) thru 2022-06-16

.=============================|===================......................................................

  • Tech Animation Team
    8x Tech Content devs working on 5 tasks (39% load) thru 2022-05-09

..........~~~~~~~~~~~~~~~~~...|========...=========.....................................................

  • Weapon Content Team
    2x Art devs will work on 4 tasks (185% load) starting 2022-04-17 thru 2022-05-05

..............................|.======......====........................................................

Chemline

  • SQ42 Art
    6x Art devs working on 36 tasks (17% load) thru 2022-06-30

.=============================|=======================..................................................

Commodity Kiosk

  • US PU Gameplay Feature Team
    3x Art devs working on 7 tasks (46% load) thru 2022-06-02

..~~~~~~~~~~~~~~~~~...........|.........................................................................
..=================.......~~~~|===============..........................................................

Datacore Deserializer

(Recently started!)

  • Systemic Services and Tools Team
    1x Engineering dev working on 7 tasks (179% load) thru 2022-06-02

..........................====|===============........................======............................

Derelict Spaceships - Points of Interest

  • MTL Sandbox 1
    8x Art devs working on 12 tasks (4% load) thru 2022-06-02
    4x Design devs working on 8 tasks (5% load) thru 2022-06-02

.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~|~~~============........======================..======================....
.~~~~~~~~~~~~~~~~~~~~~~.~~~~~~|~~~============........======================..======================....

  • Narrative
    2x Design devs working on 1 task (76% load) thru 2022-04-14

............................==|=........................................................................

DGS Crash Recovery

  • Network Team
    1x Engineering dev working on 8 tasks (110% load) thru 2022-06-30

..................============|=======================..................................................

DGS Mesh Node

  • Network Team
    3x Engineering devs working on 8 tasks (37% load) thru 2022-06-30

..................============|=======================..................................................

Drake Corsair

  • Vehicle Content - US
    5x Art devs working on 17 tasks (70% load) thru 2022-06-23

..======================....==|=====================....................................................
..======================......|.........................................................................

Drake Vulture

  • VFX Team
    1x Art dev working on 3 tasks (79% load) thru 2022-05-15

............................~~|~====~~~~~...............................................................

  • Audio
    3x Audio devs will work on 7 tasks (85% load) starting 2022-04-17 thru 2022-06-02

....................========..|.==============..........................................................

Dynamic Events

  • Mission Feature Team
    7x Design devs working on 31 tasks (45% load) thru 2022-06-16

..============================|===================..====~~~~~~~~~~~~~~~~~~~~============================
..========================....|.............................................============================

  • US PU Gameplay Feature Team
    2x Design devs working on 14 tasks (87% load) thru 2022-06-02

..~~~~~~~~~~~~~~~~~.......~~~~|~~~~~~~~~~~~~~~........================..................................

Dynamic Mission System

  • Mission Feature Team
    1x Engineering dev working on 9 tasks (93% load) thru 2022-06-16

..........................~~~~|~~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~~~~~~..........................

Dynamic Population

  • Systemic Services and Tools Team
    2x Engineering devs working on 8 tasks (84% load) thru 2022-06-16

..........................====|===================......................................................

ECUS Improvements

  • Engine Team
    2x Engineering devs working on 4 tasks (31% load) thru 2022-05-26

..~~~~~~~~~~~~~~~~~.........~~|~~~~~~~~~~~~~............................................................

Enemy Characters

  • SQ42 Character Art
    4x Art devs working on 12 tasks (30% load) thru 2022-06-16

..============================|===================......................................................

EVA T2

  • Actor Feature Team
    2x Animation devs working on 13 tasks (29% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~................................................

  • Actor Tech Team
    2x Engineering devs working on 6 tasks (53% load) thru 2022-07-07

............................==|=========================................................................

  • VFX Team
    1x Art dev will work on 1 task (128% load) starting 2022-04-18 thru 2022-05-01

..............................|.=====...................................................................

FPS Devices T1

  • Weapon Feature Team
    1x Engineering dev working on 9 tasks (72% load) thru 2022-07-07

..............~~~~==========~~|~~~~~~~~~~~~~~~~~~~~~~~~~................................................

FPS Radar / Scanning

  • Actor Feature Team
    2x Engineering devs working on 7 tasks (60% load) thru 2022-05-12

..~~~~~~~~~~~~~~~~~~~~~~~~~~..|.........................................................................
..........====================|=========................................................................

  • Graphics Team
    1x Engineering dev working on 1 task (83% load) thru 2022-04-20

..........................====|===......................................................................

Frontier Clothing

  • SC Character Art
    12x Art devs working on 20 tasks (11% load) thru 2022-06-16

.=============================|===================......................................................

FS-Tech-Anim - Asset Integration

  • Tech Animation Team
    7x Tech Content devs working on 1 task (18% load) thru 2022-04-25

..=========...................|====...=====.............................................................

Gainey

  • SQ42 Art
    4x Art devs working on 6 tasks (13% load) thru 2022-06-30

..........................~~~~|~~~~~~~~~~~~~~~~~~~~~~~..................................................

Gen12 - Renderer T1

  • Engine Team
    2x Engineering devs working on 5 tasks (79% load) thru 2022-05-26

..=================.........==|=============............................................................

  • Graphics Team
    7x Engineering devs working on 6 tasks (21% load) thru 2022-06-08

..===================.....====|=================........................................................

Greycat Industrial Salvage Backpack

  • Character Tech Art
    2x Tech Content devs working on 1 task (76% load) thru 2022-04-21

..............====............|===......................................................................

  • SC Character Art
    2x Art devs will work on 1 task (76% load) starting 2022-04-24 thru 2022-05-05

.=========................====|...====..................................................................

Greycat Industrial Salvage Tool

(Scheduled work ending soon!)

  • Weapon Content Team
    1x Art dev working on 1 task (417% load) thru 2022-04-14

............==....==..........|=........................................................................

Greycat Industrial Tractor Tool

(Scheduled work ending soon!)

  • Narrative
    2x Design devs working on 1 task (76% load) thru 2022-04-14

................~~~~........==|=........................................................................

Hacking T0

  • Weapon Content Team
    1x Art dev working on 1 task (417% load) thru 2022-04-14

....======....................|=........................................................................
......==................==....|.........................................................................

  • Weapon Feature Team
    1x Engineering dev working on 10 tasks (117% load) thru 2022-05-26

..============================|=============............................................................

  • Narrative
    2x Design devs will work on 2 tasks (33% load) starting 2022-04-17 thru 2022-05-12

....................~~~~......|.~~~~~~~~................................................................

HEX

  • Live Tools Team
    5x Engineering devs working on 11 tasks (28% load) thru 2022-06-30

..=====================...~~~~|=================================================........................

Hospital Surgeon

  • Character Tech Art
    2x Tech Content devs working on 1 task (76% load) thru 2022-04-21

..............====............|===........====..........................................................

  • SC Character Art
    1x Art dev working on 3 tasks (128% load) thru 2022-05-05

..============............====|=======..................................................................

Jump Points

  • Graphics Team
    1x Engineering dev working on 3 tasks (72% load) thru 2022-06-08

........=============.....====|=================........................................................

  • Vehicle Feature Team
    7x Engineering devs will work on 8 tasks (28% load) starting 2022-04-15 thru 2022-06-23

......=====...................|=====================......======================..................======

Ladders T1

(Recently started!)

  • Actor Feature Team
    2x Animation devs working on 7 tasks (57% load) thru 2022-07-07

............................==|=================~~~~~~~~................................................

Lean Over Cover

(Recently started!)

  • Actor Tech Team
    1x Engineering dev working on 10 tasks (175% load) thru 2022-07-07

............................==|=========================................................................

Life Support T0

  • Narrative
    1x Design dev working on 1 task (76% load) thru 2022-04-14

............................~~|~........................................................................

Login Flow

  • Game Services Team
    7x Engineering devs working on 47 tasks (63% load) thru 2022-06-30

..====================~~~~~~~~|=======================..................................................

  • Live Tools Team
    2x Engineering devs working on 16 tasks (77% load) thru 2022-06-30

......================~~~~~~~~|=======================..................................................

Lorville Cityscape

  • Location Concept Art
    2x Art devs working on 7 tasks (61% load) thru 2022-06-30

..=====...=============...====|=======================..................................................

microTech Lagrange Points

(Recently started!)

  • EU Sandbox 1
    1x Art dev working on 1 task (49% load) thru 2022-05-05

..........................====|=======..................................................................

  • Lighting Team
    1x Art dev will work on 2 tasks (133% load) starting 2022-04-24 thru 2022-05-19

..............................|...========..............................................................

MISC Hull C

  • US PU Gameplay Feature Team
    1x Engineering dev working on 9 tasks (162% load) thru 2022-06-02

..........................~~~~|===============..........................................................

  • Vehicle Content - EU
    1x Design dev working on 5 tasks (758% load) thru 2022-04-14

............................==|=........................................................................

MISC Hull E

(Recently started!)

  • Vehicle Concept Art
    1x Art dev working on 9 tasks (326% load) thru 2022-05-19

............................==|===========..............................................................

MISC Odyssey

  • Vehicle Concept Art
    2x Art devs working on 7 tasks (182% load) thru 2022-05-05

............................==|=======..................................................................

Miscellaneous Support

  • Actor Feature Team
    2x Design devs working on 25 tasks (55% load) thru 2022-12-30
    3x Animation devs working on 25 tasks (37% load) thru 2022-12-30
    1x Engineering dev working on 24 tasks (106% load) thru 2022-12-30

..============================|=================~~~~~~~~~~==============================================
..============================|=================~~~~~~~~~~==============================================
..============================|=================~~~~~~~~~~==============================================
..==========================..|.........................................................................

  • Actor Tech Team
    5x Engineering devs working on 13 tasks (14% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~======~~|~~~~~~~~~~~~~~~~~~~~~~~~~................................................

  • Gameplay Story
    1x Tech Content dev working on 1 task (152% load) thru 2022-04-21

.=====.===============~~~~~~..|===........============..................................................

  • Graphics Team
    3x Engineering devs working on 3 tasks (24% load) thru 2022-06-08

..............=======.....====|=================........................................................
..===================.........|.........................................................................

  • Lighting Team
    9x Art devs working on 12 tasks (14% load) thru 2022-06-30

......========================|=======================..................................................

  • Motion Capture Team
    5x Animation devs working on 13 tasks (22% load) thru 2022-06-30

..============================|===========~~~~~~~~~~~~..................................................

  • VFX Team
    8x Art devs working on 4 tasks (13% load) thru 2022-05-01
    2x Tech Content devs working on 5 tasks (49% load) thru 2022-05-29

..............................|.........=====...........................................................
......................~~~~~~~~|~=====...=====...........................................................
......................========|==============...........................................................

  • Weapon Feature Team
    5x Design devs working on 28 tasks (25% load) thru 2022-12-30

..============================|=================~~~~~~~~~~==============================================
..............................|...................................==============........................

  • Vehicle Experience Team
    4x Design devs will work on 5 tasks (30% load) starting 2022-04-15 thru 2022-06-23

..............................|=====================......======================......==================

  • Vehicle Feature Team
    7x Engineering devs will work on 5 tasks (17% load) starting 2022-04-15 thru 2022-06-23

..............=============...|=====================......======================..======================

Origin X1

  • Vehicle Content - EU
    1x Art dev working on 14 tasks (288% load) thru 2022-06-23
    1x Design dev working on 7 tasks (182% load) thru 2022-05-05

..........================..==|=====================..======............................................
..............~~~~~~~~~~~~..~~|~~~~~~~..~~~~~~~~~~......................................................

Outpost Homestead - Independent & Outlaw

  • EU Sandbox 1
    10x Art devs working on 10 tasks (3% load) thru 2022-05-19
    4x Design devs working on 5 tasks (3% load) thru 2022-05-19

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~|~~~========....===========================...............................
.~~~~~~~~~~.~~~~~~~~~~~~~~~.~~|~~~========....=======.......=====...=====...............................

  • Props Team
    13x Art devs working on 5 tasks (58% load) thru 2022-04-21

..================....======..|===..======....==........................................................

Outpost Theme Variants

  • EU Sandbox 1
    7x Art devs working on 5 tasks (2% load) thru 2022-05-19
    4x Design devs working on 5 tasks (4% load) thru 2022-05-19

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~========....===========================...=================...=======.
.~~~~~~~~~~~~~~.~~~~~~~~~~~~~~|~~~========....===============...=============================...=======.

Persistent Hangars

  • US PU Gameplay Feature Team
    3x Engineering devs working on 6 tasks (25% load) thru 2022-06-02
    4x Design devs working on 9 tasks (28% load) thru 2022-06-02

..........................~~~~|~~~~~~~~~~~~~~~........================........================..........
..........................~~~~|~~~~~~~~~~~~~~~........================........================..........
..............................|...............................................================..........

Persistent Streaming and Server Meshing

  • Game Services Team
    10x Engineering devs working on 17 tasks (15% load) thru 2022-06-30

..====================~~~~~~~~|=================================================........................

  • Mission Feature Team
    3x Engineering devs working on 20 tasks (40% load) thru 2022-06-16

.~========================~~~~|~~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~~~~============================

  • Network Team
    9x Engineering devs working on 13 tasks (18% load) thru 2022-06-30

..=====.......================|=========================================================================

  • Persistent Tech Team
    4x Engineering devs working on 15 tasks (33% load) thru 2022-06-30

..====================~~~~~~~~|=========================================================================

Personal Inventory

  • Actor Feature Team
    1x Engineering dev working on 4 tasks (126% load) thru 2022-05-26

..~~~~~~~~~~~~~~~~~~~~~~~~~~..|.........................................................................
............................==|=============............................................................

Physical Damage & Breakability

  • Physics Team
    3x Engineering devs working on 4 tasks (32% load) thru 2022-06-08

..===================.....====|=================........................................................

Physics - Ropes Simulation

  • Physics Team
    1x Engineering dev working on 3 tasks (72% load) thru 2022-06-08

..===================.....====|=================........................................................

Player Interaction Experience T1 - Lockers & Inventory

  • Actor Feature Team
    1x Art dev working on 12 tasks (103% load) thru 2022-09-28
    1x Design dev working on 12 tasks (56% load) thru 2022-09-28

............................==|=================~~~~~~~~~~======================........................
............................~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~........................
..............................|.......................==========================........................

Player Interaction Experience T2 - Visor HUD & Helmet

  • Actor Feature Team
    1x Design dev working on 12 tasks (56% load) thru 2022-09-28

..............................|.......................==============....................................
............................~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~........................
..............==============..|.........................................................................

Player Reflection

(Recently started!)

  • Actor Tech Team
    1x Engineering dev working on 10 tasks (88% load) thru 2022-07-07

............................~~|~~~~~~~~~~~~~~~~~~~~~~~~~................................................

Probability Volume Encounter Density Refactor

  • Systemic Services and Tools Team
    1x Engineering dev working on 5 tasks (225% load) thru 2022-05-05

..=================.......====|=======..................................................................

Pyro Space Stations

  • EU Landing Zone Team
    12x Art devs working on 58 tasks (10% load) thru 2022-05-19
    3x Design devs working on 10 tasks (8% load) thru 2022-05-19

.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~|~~~========....==========================..======..=================.....
.~~~~~~~~~~~~~~.~~~~~~~~~~~.~~|~~~========....==========================..======..=================.....

Pyro System, Planet, and Mission Setup

  • Narrative
    4x Design devs working on 1 task (38% load) thru 2022-04-14

........========............==|=....~~~~~~~~............................................................

Quantum Simulation

  • Systemic Services and Tools Team
    5x Engineering devs working on 47 tasks (27% load) thru 2022-06-16

.=============================|===================....================================================..

Replication Layer Entity Authority

  • Network Team
    6x Engineering devs working on 5 tasks (21% load) thru 2022-06-02

..=========...=====.......====|===============..........................................................

Rescue/Transport Mission

  • Mission Feature Team
    1x Design dev working on 10 tasks (97% load) thru 2022-06-16
    2x Engineering devs working on 6 tasks (46% load) thru 2022-06-16

..........~~~~~~~~~~~~~~~~====|===================......................................................
..........................~~==|=====~~~~~~~~~~~~~~......................................................

Resource Management

  • Vehicle Feature Team
    2x Engineering devs working on 10 tasks (198% load) thru 2022-05-12

..........................====|=========................................................................

Reststop Hangar Replacements

  • EU Landing Zone Team
    1x Design dev working on 6 tasks (16% load) thru 2022-05-19

.~~~~~~~~~~~~~~~~~~.~~~~~~~.~~|~~~========..............................................................

RSI Scorpius

  • Audio
    2x Audio devs working on 10 tasks (124% load) thru 2022-04-28

................==============|=====....................................................................

  • Vehicle Content - EU
    1x Design dev working on 4 tasks (267% load) thru 2022-04-28

..================..........==|=====....................................................................
..==========================..|.........................................................................

  • Vehicle Experience Team
    1x Engineering dev working on 2 tasks (119% load) thru 2022-04-28

..............=========...====|=====....................................................................
..............=========.......|.........................................................................

  • VFX Team
    1x Art dev working on 2 tasks (49% load) thru 2022-04-17

......................~~~~~~~~|~~.......................................................................

Salvage T0

  • Vehicle Feature Team
    1x Engineering dev working on 4 tasks (115% load) thru 2022-04-14

..............================|=........................................................................

  • VFX Team
    2x Engineering devs working on 7 tasks (30% load) thru 2022-05-15
    4x Art devs working on 8 tasks (23% load) thru 2022-05-15
    1x Tech Content dev working on 1 task (60% load) thru 2022-04-17

....~~~~~~~~~~~~~~~~~~~~~~~~~~|~=========...............................................................
....==================~~~~~~~~|~=========...............................................................
............................~~|~~.......................................................................

  • Audio
    4x Audio devs will work on 6 tasks (78% load) starting 2022-04-17 thru 2022-05-19

..................==========..|.==========..............................................................

Shops and Patrons

  • Facial Animation
    4x Animation devs working on 6 tasks (64% load) thru 2022-05-05

..====....................====|=======........========..................................................

Space Mines

(Recently started!)

  • Weapon Feature Team
    1x Engineering dev working on 6 tasks (53% load) thru 2022-07-07

............................~~|~~~~~~~~~~~~~~~~~~~~~~~~~................................................

Stanton Fashion Clothing

(Recently started!)

  • SC Character Art
    2x Art devs working on 2 tasks (152% load) thru 2022-04-21

..............................|===........====..........................................................

Theaters of War - Miscellaneous Support

  • Firesprite Team
    4x Design devs working on 18 tasks (11% load) thru 2022-06-30
    4x Art devs working on 18 tasks (8% load) thru 2022-06-30
    2x Engineering devs working on 11 tasks (14% load) thru 2022-06-30

.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~====================..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~====================..................................................
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~====================..................................................

Unannounced Vehicle

  • Vehicle Content - EU
    1x Design dev working on 17 tasks (122% load) thru 2022-06-02

............~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~..........................................................
..==========================..|.........................................................................

Unannounced Vehicle

  • Audio
    1x Audio dev working on 8 tasks (252% load) thru 2022-04-28

....................==========|=====....................................................................

  • Vehicle Content - EU
    1x Art dev working on 18 tasks (244% load) thru 2022-05-05
    3x Design devs working on 21 tasks (81% load) thru 2022-06-02

..============================|=======..................................................................
....==========================|===============..........................................................

  • VFX Team
    1x Art dev working on 1 task (60% load) thru 2022-04-17

............................~~|~~.......................................................................

  • Vehicle Content - US
    3x Tech Content devs will work on 3 tasks (152% load) starting 2022-04-17 thru 2022-04-28

..............................|.====....................................................................

  • Vehicle Experience Team
    2x Design devs will work on 3 tasks (93% load) starting 2022-04-15 thru 2022-05-12

..............................|=========................................................................

Unannounced Vehicle

  • Vehicle Content - EU
    1x Design dev working on 19 tasks (136% load) thru 2022-06-02
    2x Art devs working on 17 tasks (139% load) thru 2022-04-21

............~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~..........................................................
....==========================|===......................................................................

Unannounced Vehicle

  • Vehicle Content - EU
    2x Art devs working on 18 tasks (203% load) thru 2022-06-16

..............============..==|===================......................................................
..............========........|.........................................................................

Unannounced Vehicle

  • Vehicle Concept Art
    1x Art dev working on 8 tasks (342% load) thru 2022-05-12

............====............==|=========................................................................

Underground Facilities

  • Location Concept Art
    4x Art devs working on 16 tasks (70% load) thru 2022-06-30

..=====================...====|=======================..................................................

VisArea Improvements

  • Engine Team
    1x Engineering dev working on 4 tasks (63% load) thru 2022-05-26

..~~~~~~~~~~~~~~~~~.........~~|~~~~~~~~~~~~~............................................................

Zero G Push & Pull

  • Actor Feature Team
    2x Animation devs working on 12 tasks (27% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~................................................

  • Narrative
    3x Design devs will work on 1 task (51% load) starting 2022-04-17 thru 2022-04-28

..............................|.====....................................................................


The following deliverables are scheduled to begin (or continue) work within two weeks

Argo SRV

(Starting soon!)

  • Vehicle Content - EU
    3x Art devs will work on 16 tasks (148% load) starting 2022-04-17 thru 2022-06-16
    1x Design dev will work on 5 tasks (758% load) starting 2022-04-17 thru 2022-04-28

..............................|.==================....======================............................
..............................|.====..====..............................................................

Chapter 04

  • Cinematics Team
    3x Animation devs will work on 1 task (24% load) starting 2022-04-21 thru 2022-05-14

..............................|.==========..............................................................

Chapter 09

  • Cinematics Team
    2x Design devs will work on 1 task (18% load) starting 2022-04-21 thru 2022-05-14

.~~~~~~~~~~~~~~~~~~~~~~~~~~...|.~~~~~~~~~~..............................................................

Maya Loadouts from P4K

  • Tech Animation Team
    5x Tech Content devs will work on 2 tasks (25% load) starting 2022-04-26 thru 2022-05-23

..~~~~~~~~~...................|...=========.............................................................

Satellites - Points of Interest

(Starting soon!)

  • Location Concept Art
    2x Art devs will work on 5 tasks (62% load) starting 2022-04-24 thru 2022-06-30

..............................|...======================================================================

Turret Usability Improvements

(Starting soon!)

  • Vehicle Experience Team
    2x Engineering devs will work on 8 tasks (97% load) starting 2022-04-15 thru 2022-06-23

..............................|=====================......======================........................

Unannounced Vehicle

(Starting soon!)

(Scheduled work ending soon!)

  • Narrative
    1x Design dev will work on 1 task (152% load) starting 2022-04-17 thru 2022-04-28

..............................|.====....................................................................

Unannounced Vehicle

(Starting soon!)

  • Vehicle Content - EU
    5x Art devs will work on 16 tasks (89% load) starting 2022-04-24 thru 2022-06-23

..............................|...==================..========================..==============..........

Weapon Misfire & Wear

  • Narrative
    1x Design dev will work on 1 task (76% load) starting 2022-04-17 thru 2022-04-28

..............................|.~~~~....................................................................