ShinyTracker

RSI "Progress Tracker" Delta Reports

by ShinyHobo RSS

Scheduled Deliverables

as of 2022-03-02

There are currently 102 scheduled deliverables being worked on by 46 teams

7 deliverables are scheduled to begin work by 5 team(s) within two weeks


This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.

The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.

The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.


extra analysis (click me)


There are approximately 395 devs (out of ~512, or 77%) with 865 assignments scheduled to work on 102 observable deliverables. Of those deliverables, 26% are for SQ42 exclusively, with ~168 devs (33%) scheduled for approximately 1943 man-days. 30% of deliverables are shared between both projects.

23 deliverable(s) are not currently scheduled to continue work after this sprint: Below are the time breakdowns for each team:

AI - Arcade Machine

  • AI Content Team
    1x Animation dev working on 4 tasks (247% load) thru 2022-03-16

..........~~~~~~..|.....................................................................................
..............====|=====................................................................................

AI - Untrained Combat

  • AI Tech and Feature Team
    2x Animation devs working on 5 tasks (102% load) thru 2022-03-16

..........========|=====................................................................................

AI - Usable System V2

(Scheduled work ending soon!)

  • AI Tech and Feature Team
    1x Engineering dev working on 6 tasks (91% load) thru 2022-03-02

..~~~~~~~~~~~~~~~~|~....................................................................................

Animatable Gunner Helmet

  • SQ42 Character Art
    1x Art dev working on 4 tasks (267% load) thru 2022-03-24

..................|=======..............................................................................

Archon

  • SQ42 Art
    14x Art devs working on 59 tasks (15% load) thru 2022-03-28

.=================|========.............................................................................

Asset Reference Database

(Scheduled work ending soon!)

  • Tools Team
    1x Engineering dev working on 4 tasks (247% load) thru 2022-03-14

..=========...====|====.................................................................................

ATC System Rewrite

  • Mission Feature Team
    1x Engineering dev working on 6 tasks (123% load) thru 2022-03-24

..================|=======..............................................................................

  • Systemic Services and Tools Team
    1x Engineering dev working on 2 tasks (123% load) thru 2022-03-28

..................|========.............................................................................

Banu Merchantman

  • Vehicle Content - EU
    8x Art devs working on 26 tasks (31% load) thru 2022-06-23
    3x Design devs working on 12 tasks (69% load) thru 2022-03-24

..================|=================================..======================....======================..
..============~~~~|~~~==~~..~~~~~~~~~~..~~~~~~~~~~......................................................

  • Weapon Content Team
    3x Art devs working on 9 tasks (200% load) thru 2022-03-24

..................|=======..............................................................................

Bombs

(Scheduled work ending soon!)

  • Narrative
    2x Design devs working on 3 tasks (227% load) thru 2022-03-03

................==|=....................................................................................

Bounty Hunter V2

  • US PU Gameplay Feature Team
    1x Art dev working on 2 tasks (256% load) thru 2022-03-14

......=========...|====...====================........================........========..................

Breakers Yard

  • SQ42 Art
    1x Cinematics dev working on 12 tasks (135% load) thru 2022-03-28

.=================|========.............................................................................

  • Narrative
    1x Design dev will work on 3 tasks (455% load) starting 2022-03-06 thru 2022-03-17

..................|.====................................................................................

Bug Fixing & Tech Debt

  • Actor Tech Team
    2x Engineering devs working on 13 tasks (59% load) thru 2022-07-07

..================|=====================================................................................

  • AI Content Team
    5x Design devs working on 3 tasks (77% load) thru 2022-03-02
    4x Animation devs working on 6 tasks (192% load) thru 2022-03-02

......======..====|=....................................................................................
..............====|=....................................................................................

  • AI Tech and Feature Team
    10x Engineering devs working on 16 tasks (96% load) thru 2022-03-16

..............====|~~~~~................................................................................

  • Engine Team
    4x Engineering devs working on 34 tasks (50% load) thru 2022-03-28

.~================|~~~~~~~~.............................................................................

  • EU Landing Zone Team
    15x Art devs working on 25 tasks (51% load) thru 2022-03-14
    5x Design devs working on 7 tasks (43% load) thru 2022-03-14

..............~~~~|~~~~...................====........................======......................=========.
..............~~~~|~~~~...................====........................======......................=========.

  • EU Sandbox 1
    6x Design devs working on 9 tasks (57% load) thru 2022-03-14
    11x Art devs working on 15 tasks (48% load) thru 2022-03-14

..............~~~~|~~~~...................====..........................=====...............=====.......
..............~~~~|~~~~...................====..........................=====...............=====.......

  • Network Team
    2x Engineering devs working on 2 tasks (128% load) thru 2022-03-14

..=========.......|====.................................................................................

  • Persistent Tech Team
    1x Engineering dev working on 2 tasks (256% load) thru 2022-03-14

..................|====.................................................................................

  • Physics Team
    4x Engineering devs working on 4 tasks (20% load) thru 2022-03-28

..================|========.............................................................................

  • Props Team
    11x Art devs working on 24 tasks (606% load) thru 2022-03-05
    2x Tech Content devs working on 6 tasks (833% load) thru 2022-03-05

......====........|===..======..........................................................................
......====........|===....====..........................................................................

  • Systemic Services and Tools Team
    5x Engineering devs working on 4 tasks (49% load) thru 2022-03-28

..................|========...................====....................==========..................====..

  • Tools Team
    5x Engineering devs working on 8 tasks (32% load) thru 2022-03-28

..================|========.............................................................................

  • US PU Gameplay Feature Team
    4x Design devs working on 4 tasks (41% load) thru 2022-03-28
    4x Engineering devs working on 5 tasks (39% load) thru 2022-03-28
    3x Art devs working on 3 tasks (51% load) thru 2022-03-28

..............====|===~~~~~...................====....................========................==========
..................|~~~~~~~~...................====....................========................==========
..................|===~~~~~...................====....................========................==========

  • Vehicle Content - EU
    5x Design devs working on 6 tasks (63% load) thru 2022-03-31

..................|.......==..==..........============......................====..............========..
..................|=========............==============..................................................

  • Vehicle Content - US
    3x Tech Content devs working on 5 tasks (111% load) thru 2022-03-17
    2x Design devs will work on 2 tasks (152% load) starting 2022-03-06 thru 2022-03-17

....====........==|=====..................................................======....................======
..................|.====..................................................======....................======
..................|.....................========........................................................

  • Vehicle Tech Team
    3x Engineering devs working on 14 tasks (64% load) thru 2022-03-17
    2x Design devs working on 11 tasks (124% load) thru 2022-03-17

..~~~~~~~~~~~~~~~~|~~~~~................................................................................
..================|=====................................................................................

  • Weapon Content Team
    1x Animation dev working on 3 tasks (1250% load) thru 2022-03-03

..==......====....|.....................................................................................
............==....|=....................................................................................

  • Editor Team
    4x Engineering devs will work on 12 tasks (385% load) starting 2022-03-15 thru 2022-03-28

..........=====...|...=====.............................................................................

  • Graphics Team
    10x Engineering devs will work on 30 tasks (238% load) starting 2022-03-08 thru 2022-03-28
    2x Tech Content devs will work on 6 tasks (188% load) starting 2022-03-08 thru 2022-03-28

..................|.=======.............................................................................
..................|.~~~~~~~.............................................................................

  • Vehicle Experience Team
    3x Engineering devs will work on 4 tasks (74% load) starting 2022-03-15 thru 2022-04-14
    4x Design devs will work on 4 tasks (56% load) starting 2022-03-15 thru 2022-04-14

..=====...........|...==========......................======..................==========................
..=============...|...==========..==================..~~~~~~..................==========================

  • Weapon Feature Team
    2x Engineering devs will work on 3 tasks (93% load) starting 2022-03-04 thru 2022-03-31

..................|=========............................................................................

Building Interiors

  • MTL Sandbox 1
    10x Art devs working on 18 tasks (4% load) thru 2022-06-02
    4x Design devs working on 9 tasks (6% load) thru 2022-06-02

.~~~~~~~~~~~~~~~~~|~~~~.~~~~~~~~~~============........======================..======================....
.~~~~~~~~~~~~~~~~~|~~~~.~~~~~~~~~~============........======================..======================....

Cargo System Refactor

  • US PU Gameplay Feature Team
    3x Engineering devs working on 14 tasks (30% load) thru 2022-06-02

..................|.......~~~~========..................................................................
..~~~~~~~~========|~~~~~~~~~~~~~~~~~~~~~~~~~~~..........................................................

  • Props Team
    2x Art devs will work on 5 tasks (321% load) starting 2022-03-13 thru 2022-03-26

..........========|...======............................................................................

Cave Archetypes

  • Planet Content Team
    4x Art devs working on 10 tasks (6% load) thru 2022-05-05

.~~~~~~~~~~~~~~.~~|~~~~~~~~~~~~~~~====........=====================.......=================.......=====.

Chapter 01

  • Cinematics Team
    3x Animation devs working on 21 tasks (21% load) thru 2022-03-28
    1x Design dev working on 13 tasks (39% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................
.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 1 - FPS
    1x Design dev working on 19 tasks (94% load) thru 2022-03-31

.=================|=========............................................................................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 19 tasks (18% load) thru 2022-03-31

.~================|=========............................................................................

  • SQ42 Level Design 3 - Social
    3x Design devs working on 10 tasks (49% load) thru 2022-03-17

..~~~~~~~~~~~~~~~~|=====................................................................................

Chapter 04

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

Chapter 05

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

Chapter 06

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 3 - Social
    2x Design devs working on 6 tasks (68% load) thru 2022-03-17

..====~~~~~~~~~~~~|=====................................................................................

  • Gameplay Story
    5x Animation devs will work on 9 tasks (100% load) starting 2022-03-15 thru 2022-03-30

.~~~~~.~~~~~~~~...|...~~~~~~............................................................................

Chapter 07

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 2 - Flight
    2x Design devs working on 5 tasks (76% load) thru 2022-03-31

.~~~~~~~..========|=========............................................................................

Chapter 08

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • Gameplay Story
    5x Animation devs will work on 9 tasks (100% load) starting 2022-03-15 thru 2022-03-30

..~~~~....~~~~~...|...~~~~~~............................................................................

Chapter 09

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

Chapter 10

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • Gameplay Story
    5x Animation devs will work on 9 tasks (100% load) starting 2022-03-15 thru 2022-03-30

.......~~~~~~~~...|...~~~~~~............................................................................

Chapter 11

  • Cinematics Team
    2x Design devs working on 23 tasks (21% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 1 - FPS
    5x Design devs working on 17 tasks (29% load) thru 2022-03-31

.=================|=========............................................................................

Chapter 12

  • Cinematics Team
    2x Design devs working on 21 tasks (20% load) thru 2022-03-28
    2x Animation devs working on 11 tasks (26% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................
.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 1 - FPS
    3x Design devs working on 13 tasks (34% load) thru 2022-03-31

.=====~~~~~~~~~~~~|~~~~~~~~~............................................................................

Chapter 13

(Scheduled work ending soon!)

  • SQ42 Level Design 3 - Social
    1x Design dev working on 5 tasks (71% load) thru 2022-03-03

..~~~~~~~~~~~~~~~~|~....................................................................................

Chapter 14

  • SQ42 Level Design 1 - FPS
    2x Design devs working on 33 tasks (60% load) thru 2022-03-31

.=================|=========............................................................................

  • SQ42 Level Design 2 - Flight
    5x Design devs working on 12 tasks (58% load) thru 2022-03-31

......============|=========............................................................................

Chapter 15

  • Cinematics Team
    1x Design dev working on 21 tasks (39% load) thru 2022-03-28
    3x Animation devs working on 21 tasks (15% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................
.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 3 - Social
    3x Design devs working on 5 tasks (35% load) thru 2022-03-17

......~~~~~~~~====|=====................................................................................

  • Gameplay Story
    5x Animation devs will work on 9 tasks (100% load) starting 2022-03-15 thru 2022-03-30

..............~~~~|...~~~~~~............................................................................

Chapter 18

  • SQ42 Level Design 1 - FPS
    4x Design devs working on 19 tasks (21% load) thru 2022-03-31

.~====~~~~~~~~~~~~|~~~~~~~~~............................................................................

Chapter 19

  • Gameplay Story
    5x Animation devs working on 9 tasks (107% load) thru 2022-03-14

..................|~~~~.................................................................................

  • SQ42 Level Design 1 - FPS
    3x Design devs working on 6 tasks (28% load) thru 2022-03-31

......~~~~~~~~~~~~|~~~~~~~~~............................................................................

Chapter 20

  • Cinematics Team
    2x Animation devs working on 13 tasks (19% load) thru 2022-03-28
    2x Design devs working on 11 tasks (26% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................
.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • SQ42 Level Design 1 - FPS
    2x Design devs working on 6 tasks (36% load) thru 2022-03-31

......~~~~~~~~~~~~|~~~~~~~~~............................................................................

Chapter 21

  • Cinematics Team
    1x Animation dev working on 13 tasks (39% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • Gameplay Story
    4x Animation devs working on 9 tasks (134% load) thru 2022-03-14

..................|~~~~.................................................................................

  • SQ42 Level Design 3 - Social
    2x Design devs working on 2 tasks (64% load) thru 2022-03-03

..............~~~~|~....................................................................................

Chapter 22

  • SQ42 Level Design 1 - FPS
    6x Design devs working on 8 tasks (28% load) thru 2022-03-31

......============|=========............................................................................

Chapter 23

  • Cinematics Team
    1x Design dev working on 9 tasks (43% load) thru 2022-03-28

.~~~~~~~~~~~~~~~~~|~~~~~~~~.............................................................................

  • Gameplay Story
    5x Animation devs working on 9 tasks (107% load) thru 2022-03-14

..................|~~~~.................................................................................

Chapter 26

  • SQ42 Art
    8x Art devs working on 26 tasks (30% load) thru 2022-03-28

.=================|========.............................................................................

  • SQ42 Level Design 1 - FPS
    5x Design devs working on 31 tasks (23% load) thru 2022-03-31

.=================|=========............................................................................

Character Work

  • AI Content Team
    4x Animation devs working on 7 tasks (42% load) thru 2022-03-16
    3x Design devs will work on 6 tasks (256% load) starting 2022-03-03 thru 2022-03-16

..................|=====................................................................................
..================|=====................................................................................

  • AI Tech and Feature Team
    4x Engineering devs working on 12 tasks (72% load) thru 2022-03-02

..~~~~========~~~~|~....................................................................................
..==========......|.....................................................................................

  • Audio
    5x Audio devs working on 19 tasks (116% load) thru 2022-03-03

....==============|=....................................................................................

  • Character Tech Art
    2x Tech Content devs working on 7 tasks (87% load) thru 2022-03-24

......============|=======..............................................................................

  • Facial Animation
    6x Animation devs working on 8 tasks (32% load) thru 2022-03-24

....==============|=======..............................................................................

  • SQ42 Character Art
    9x Art devs working on 35 tasks (38% load) thru 2022-03-24

.=================|=======..............................................................................

  • Tech Animation Team
    6x Tech Content devs working on 6 tasks (15% load) thru 2022-03-28

..........~~~~~~~~|~~~~~~~~.............................................................................

  • Motion Capture Team
    5x Animation devs will work on 9 tasks (231% load) starting 2022-03-15 thru 2022-03-28

......=========...|...=====.............................................................................

Chemline

  • Narrative
    1x Design dev working on 3 tasks (227% load) thru 2022-03-03

................~~|~....................................................................................

  • SQ42 Art
    5x Art devs working on 32 tasks (22% load) thru 2022-03-28

.=================|========.............................................................................

  • VFX Team
    1x Art dev working on 4 tasks (106% load) thru 2022-03-13

....==============|====.................................................................................

Civilian NPC Movement Improvements

(Scheduled work ending soon!)

  • AI Tech and Feature Team
    1x Engineering dev working on 6 tasks (91% load) thru 2022-03-02

..~~~~~~~~~~~~~~~~|~....................................................................................

Derelict Spaceships - Points of Interest

  • MTL Sandbox 1
    8x Art devs working on 20 tasks (6% load) thru 2022-06-02
    3x Design devs working on 8 tasks (7% load) thru 2022-06-02

.~~~~~~~~~~~~~~~~~|~~~~.~~~~~~~~~~============........======================..======================....
.~~~~~~~~~~~~~~~~~|~~~~.~~~~~~~~~~============........======================..======================....

DGS Crash Recovery

(Recently started!)

  • Network Team
    1x Engineering dev working on 3 tasks (217% load) thru 2022-03-24

..................|=======..............................................................................

DGS Mesh Node

  • Network Team
    3x Engineering devs working on 3 tasks (72% load) thru 2022-03-24

..................|=======..............................................................................

Drake Corsair

  • Vehicle Content - US
    5x Art devs working on 9 tasks (41% load) thru 2022-03-17
    2x Design devs working on 7 tasks (79% load) thru 2022-03-17

..================|=====....============................................................................
..================|=====................................................................................

Drake Vulture

  • Vehicle Content - US
    1x Design dev working on 3 tasks (200% load) thru 2022-03-03

..==========......|.....................................................................................
............======|=....................................................................................
........========..|.....................................................................................

  • Vehicle Experience Team
    1x Design dev working on 2 tasks (123% load) thru 2022-03-14

..............====|====.................................................................................

  • Audio
    1x Audio dev will work on 6 tasks (400% load) starting 2022-03-06 thru 2022-03-31

..................|.========............................................................................

Dynamic Events

  • Mission Feature Team
    7x Design devs working on 16 tasks (23% load) thru 2022-06-16
    3x Engineering devs working on 6 tasks (41% load) thru 2022-03-24

..================|===============================..====~~~~~~~~~~~~~~~~~~~~============================
..================|=======..................................................============================

Enemy Characters

  • AI Tech and Feature Team
    1x Engineering dev working on 5 tasks (203% load) thru 2022-03-02
    1x Animation dev working on 6 tasks (182% load) thru 2022-03-02

......============|=....................................................................................
..================|=....................................................................................

  • SQ42 Character Art
    4x Art devs working on 8 tasks (41% load) thru 2022-03-24

..================|=======..............................................................................

Entity Properties Plugin

(Scheduled work ending soon!)

  • Editor Team
    1x Engineering dev working on 3 tasks (185% load) thru 2022-03-14

..=========...====|====.................................................................................

EVA T2

  • Actor Feature Team
    2x Animation devs working on 15 tasks (34% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~................................................

Fire Hazard

(Scheduled work ending soon!)

  • Graphics Team
    1x Tech Content dev working on 5 tasks (66% load) thru 2022-03-07

..~~~~~~~~~~~~~~~~|~~...................................................................................

  • VFX Team
    1x Tech Content dev working on 4 tasks (53% load) thru 2022-03-13

....~~~~~~~~~~~~~~|~~~~.................................................................................

FPS Devices T1

(Recently started!)

  • Weapon Feature Team
    1x Engineering dev working on 10 tasks (84% load) thru 2022-07-07

..............~~~~|=========~~~~~~~~~~~~~~~~~~~~~~~~~~~~................................................

FPS Radar / Scanning

  • Actor Feature Team
    2x Engineering devs working on 5 tasks (76% load) thru 2022-03-31
    1x Design dev working on 7 tasks (67% load) thru 2022-03-31

..........========|=========............................................................................
..~~~~~~~~~~~~~~~~|~~~~~~~~~............................................................................

  • Narrative
    2x Design devs will work on 3 tasks (227% load) starting 2022-03-06 thru 2022-03-17

..................|.====................................................................................

Frontier Clothing

  • SC Character Art
    9x Art devs working on 20 tasks (22% load) thru 2022-03-24

.=================|=======..............................................................................

Gen12 - Renderer T1

(Scheduled work ending soon!)

  • Graphics Team
    7x Engineering devs working on 14 tasks (53% load) thru 2022-03-07

..================|==...................................................................................

Greycat Industrial Cydnus Mining Droid

  • SQ42 Art
    1x Art dev working on 8 tasks (159% load) thru 2022-03-28

..================|========.............................................................................

Greycat Industrial Salvage Tool

(Scheduled work ending soon!)

  • Narrative
    1x Design dev working on 3 tasks (227% load) thru 2022-03-03

................~~|~....................................................................................

  • Weapon Content Team
    1x Art dev working on 3 tasks (1250% load) thru 2022-03-03

............==....|=....................................................................................

Greycat Industrial Tractor Tool

(Scheduled work ending soon!)

  • Narrative
    1x Design dev working on 3 tasks (227% load) thru 2022-03-03

................~~|~....................................................................................

Hacking T0

  • UI Tech Team
    1x Engineering dev working on 6 tasks (313% load) thru 2022-03-17

..............====|=====................................................................................

  • Weapon Feature Team
    1x Engineering dev working on 7 tasks (134% load) thru 2022-03-31

..================|=========............................................................................

  • Narrative
    2x Design devs will work on 3 tasks (114% load) starting 2022-03-06 thru 2022-03-17

..................|.~~~~................................................................................

Healing T0 / Actor Status T1

(Scheduled work ending soon!)

  • Motion Capture Team
    5x Animation devs working on 4 tasks (49% load) thru 2022-03-14

.======.......====|====.................................................................................

Improved OC Workflow

(Scheduled work ending soon!)

  • Editor Team
    2x Engineering devs working on 4 tasks (123% load) thru 2022-03-14

..............====|====.................................................................................

Infiltrate/Defend Mission

  • Mission Feature Team
    3x Design devs working on 4 tasks (21% load) thru 2022-03-24

..........~~~~~~~~|~~~~~~~..........................======..............................................

Jump Points

  • Graphics Team
    1x Engineering dev working on 4 tasks (163% load) thru 2022-03-07

........==========|==...................................................................................

  • VFX Team
    2x Art devs working on 3 tasks (61% load) thru 2022-04-03

................==|==========...........................................................................

Lava Tech

(Scheduled work ending soon!)

  • Planet Tech Team
    1x Engineering dev working on 3 tasks (185% load) thru 2022-03-14

..............====|====.................................................................................

Levski - Hospital Interior Location

(Scheduled work ending soon!)

  • VFX Team
    1x Art dev working on 2 tasks (167% load) thru 2022-03-13

................==|====.................................................................................

Long Term Persistence Enhancements

(Recently started!)

  • Persistent Tech Team
    1x Engineering dev working on 3 tasks (154% load) thru 2022-03-28

..................|===~~~~~.............................................................................

Look IK Architecture Refactor

  • Tech Animation Team
    2x Tech Content devs working on 6 tasks (83% load) thru 2022-03-28

..........========|~~~~~~~~.............................................................................

Lorville - Hospital Interior Location

(Scheduled work ending soon!)

  • Audio
    3x Audio devs working on 16 tasks (157% load) thru 2022-03-10

......==========~~|===..................................................................................

Lorville Cityscape

  • Location Concept Art
    2x Art devs working on 4 tasks (81% load) thru 2022-03-14

..=====...========|====...============================..................................................

MISC Hull A

  • Audio
    3x Audio devs working on 13 tasks (136% load) thru 2022-03-03

....==============|=....................................................................................

  • Narrative
    1x Design dev working on 3 tasks (227% load) thru 2022-03-03

................~~|~....................................................................................

  • Vehicle Content - US
    3x Tech Content devs working on 5 tasks (52% load) thru 2022-03-17

........==========|=====................................................................................

  • VFX Team
    1x Art dev working on 3 tasks (81% load) thru 2022-03-13

..........~~~~~~==|====.................................................................................

MISC Hull C

  • Narrative
    2x Design devs working on 3 tasks (114% load) thru 2022-03-03

........====....~~|~....................................................................................

Miscellaneous Support

  • Actor Feature Team
    2x Design devs working on 27 tasks (60% load) thru 2022-12-30
    3x Animation devs working on 27 tasks (40% load) thru 2022-12-30
    1x Engineering dev working on 25 tasks (111% load) thru 2022-12-30
    1x Art dev working on 7 tasks (134% load) thru 2022-03-31

..================|=============================~~~~~~~~~~================================================
..================|=============================~~~~~~~~~~================================================
..================|=============================~~~~~~~~~~================================================
..================|=========............................................................................

  • Actor Tech Team
    5x Engineering devs working on 15 tasks (15% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~|~~~======~~~~~~~~~~~~~~~~~~~~~~~~~~~~................................................

  • AI Content Team
    2x Tech Content devs working on 10 tasks (72% load) thru 2022-03-16
    2x Animation devs will work on 6 tasks (385% load) starting 2022-03-03 thru 2022-03-16
    1x Design dev will work on 3 tasks (385% load) starting 2022-03-03 thru 2022-03-16

..~~~~~~~~~~~~~~~~|~~~~~................................................................................
..................|=====................................................................................
..................|=====................................................................................

  • AI Tech and Feature Team
    1x Tech Content dev working on 7 tasks (97% load) thru 2022-03-16

..~~~~~~~~====~~~~|~~~~~................................................................................

  • Editor Team
    1x Design dev working on 8 tasks (159% load) thru 2022-03-28

..================|========.............................................................................

  • Gameplay Story
    1x Tech Content dev working on 14 tasks (129% load) thru 2022-03-30

.=====.===========|=========............................................................................

  • Graphics Team
    1x Engineering dev working on 3 tasks (250% load) thru 2022-03-07
    1x Tech Content dev working on 5 tasks (132% load) thru 2022-03-07

..............====|==...................................................................................
..================|==...................................................................................

  • Lighting Team
    7x Art devs working on 8 tasks (28% load) thru 2022-03-28

......============|========.............................................................................

  • SQ42 Art
    3x Art devs working on 14 tasks (93% load) thru 2022-03-28

..================|========.............................................................................

  • Tech Animation Team
    3x Tech Content devs working on 8 tasks (53% load) thru 2022-03-28

..================|========.............................................................................

  • Tools Team
    2x Engineering devs working on 11 tasks (109% load) thru 2022-03-28

..================|========.............................................................................

  • Vehicle Experience Team
    1x Engineering dev working on 4 tasks (121% load) thru 2022-03-14

..................|...........======================......======================......==================
......============|====...............==============....................................................

  • Vehicle Feature Team
    7x Engineering devs working on 3 tasks (17% load) thru 2022-03-28

..............====|========...======================......======================..======================

  • Vehicle Tech Team
    3x Engineering devs working on 8 tasks (55% load) thru 2022-03-31

....==============|=====~~~~............................................................................
..................|.....====............................................................................

  • Weapon Feature Team
    5x Design devs working on 33 tasks (30% load) thru 2022-12-30

..================|=============================~~~~~~~~~~================================================
..................|...............................................==============........................

  • Planet Content Team
    9x Art devs will work on 8 tasks (57% load) starting 2022-03-15 thru 2022-03-28

..............~~~~|...~~~~~...........====........................=====...................=====.........

  • Props Team
    2x Tech Content devs will work on 7 tasks (449% load) starting 2022-03-13 thru 2022-03-26
    11x Art devs will work on 9 tasks (105% load) starting 2022-03-13 thru 2022-03-26

..================|=..======............................................................................
..================|=..======............................................................................

  • VFX Team
    2x Tech Content devs will work on 2 tasks (42% load) starting 2022-03-14 thru 2022-04-03
    8x Art devs will work on 4 tasks (42% load) starting 2022-03-14 thru 2022-04-03

..................|...~~~~~~~...........................................................................
..................|...=======...........................................................................

Modular Shaders

(Scheduled work ending soon!)

  • Graphics Team
    1x Engineering dev working on 5 tasks (132% load) thru 2022-03-07

..================|==...................................................................................

Move Planet to Compute

  • Planet Tech Team
    1x Engineering dev working on 3 tasks (185% load) thru 2022-03-14

..............====|====...=========.....................................................................

Origin X1

  • Vehicle Content - EU
    1x Design dev working on 6 tasks (128% load) thru 2022-03-24
    1x Art dev working on 8 tasks (252% load) thru 2022-03-24

..............~~~~|~~~~~~~..~~~~~~~~~~..~~~~~~~~~~......................................................
..........========|=======..========================..====..............................................

Outpost Homestead - Independent & Outlaw

  • EU Sandbox 1
    10x Art devs working on 16 tasks (4% load) thru 2022-05-19
    4x Design devs working on 6 tasks (4% load) thru 2022-05-19

.~~~~~~~~~~~~~~.~~|~~~~~~~~.~~~~~~========....===========================...............................
.~~~~~~~~~~.~~~~~~|~~~~~~~~.~~~~~~========....=======.......=====...=====...............................

  • Lighting Team
    5x Art devs working on 4 tasks (24% load) thru 2022-03-14

......============|====.................................................................................

  • Props Team
    11x Art devs will work on 4 tasks (47% load) starting 2022-03-13 thru 2022-03-26

..================|...======............................................................................

Outpost Theme Variants

  • EU Sandbox 1
    7x Art devs working on 7 tasks (3% load) thru 2022-05-19
    4x Design devs working on 7 tasks (5% load) thru 2022-05-19

.~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~========....===========================...=================...=======.
.~~~~~~~~~~~~~~.~~|~~~~~~~~~~~~~~~========....===============...=============================...=======.

Persistent Streaming and Server Meshing

  • Actor Feature Team
    1x Engineering dev working on 7 tasks (134% load) thru 2022-03-31

..================|=========............................................................................

  • Actor Tech Team
    1x Engineering dev working on 7 tasks (134% load) thru 2022-03-31

..================|=========............................................................................

  • Mission Feature Team
    3x Engineering devs working on 14 tasks (31% load) thru 2022-06-16

.~================|=======~~~~~~~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~~~~============================

  • Network Team
    9x Engineering devs working on 10 tasks (14% load) thru 2022-06-30

..=====.......====|=======================================================================================

  • Persistent Tech Team
    4x Engineering devs working on 19 tasks (42% load) thru 2022-06-30

..================|===~~~~~~~~============================================================================

  • Vehicle Tech Team
    1x Design dev working on 7 tasks (174% load) thru 2022-03-17
    1x Engineering dev working on 7 tasks (87% load) thru 2022-03-17

....==============|=====................................................................................
....~~~~~~~~~~~~~~|~~~~~................................................................................

Personal Inventory

  • Actor Feature Team
    1x Animation dev working on 7 tasks (134% load) thru 2022-03-31
    1x Design dev working on 7 tasks (67% load) thru 2022-03-31

..================|=========............................................................................
..~~~~~~~~~~~~~~~~|~~~~~~~~~............................................................................

Physical Damage & Breakability

(Scheduled work ending soon!)

  • Physics Team
    3x Engineering devs working on 3 tasks (26% load) thru 2022-03-07

..================|==...................................................................................

Physics - Ropes Simulation

(Scheduled work ending soon!)

  • Physics Team
    1x Engineering dev working on 3 tasks (79% load) thru 2022-03-07

..================|==...................................................................................

Player Interaction Experience T2 - Visor HUD & Helmet

(Recently started!)

  • Actor Feature Team
    1x Animation dev working on 4 tasks (163% load) thru 2022-03-31

..................|.........~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~........................
..................|.....................========~~~~~~~~~~==========....................................
..............====|=========............................................................................

Player Item Shard Transition

(Scheduled work ending soon!)

  • Persistent Tech Team
    2x Engineering devs working on 3 tasks (93% load) thru 2022-03-14

..............====|====.................................................................................

Pyro Space Stations

  • EU Landing Zone Team
    12x Art devs working on 25 tasks (5% load) thru 2022-05-19
    3x Design devs working on 7 tasks (6% load) thru 2022-05-19

.~~~~~~~~~~~~~~.~~|~~~~~~~~.~~~~~~========....==========================..======..=================.....
.~~~~~~~~~~~~~~.~~|~~~~~~~~.~~~~~~========....==========================..======..=================.....

  • Lighting Team
    3x Art devs working on 10 tasks (101% load) thru 2022-03-14

......============|====.................................................................................

  • Props Team
    10x Art devs will work on 10 tasks (128% load) starting 2022-03-13 thru 2022-03-26

.=================|...======............................................................................

Quantum Simulation

  • Systemic Services and Tools Team
    5x Engineering devs working on 39 tasks (23% load) thru 2022-06-16

.=================|===============================....================================================..

RaStar

  • Planet Tech Team
    2x Engineering devs working on 11 tasks (81% load) thru 2022-04-26

..================|================...=========.......=========...=========.............................

Rescue/Transport Mission

  • Mission Feature Team
    1x Design dev working on 10 tasks (97% load) thru 2022-06-16

..........~~~~~~~~|~~~~~~~========================......................................................
..................|.......~~========~~~~~~~~~~~~~~......................................................

Roads

  • Planet Tech Team
    1x Engineering dev working on 5 tasks (152% load) thru 2022-03-14

......============|====...=====.........................................................................

RSI Scorpius

  • Audio
    1x Audio dev working on 8 tasks (342% load) thru 2022-03-31

................==|=========............................................................................

  • Vehicle Content - EU
    4x Art devs working on 16 tasks (76% load) thru 2022-03-31

..================|=========............................................................................
..================|.........========....................................................................

  • Vehicle Experience Team
    1x Engineering dev working on 2 tasks (123% load) thru 2022-03-14
    2x Design devs working on 2 tasks (62% load) thru 2022-03-14

..............====|====...==========....................................................................
..............====|====.................................................................................

  • VFX Team
    1x Art dev will work on 2 tasks (167% load) starting 2022-03-14 thru 2022-04-03

..................|...=======...........................................................................

Salvage T0

  • Actor Feature Team
    1x Design dev working on 7 tasks (67% load) thru 2022-03-31

..~~~~~~~~~~~~~~~~|~~~~~~~~~............................................................................

  • Audio
    2x Audio devs working on 10 tasks (260% load) thru 2022-03-31

..................|=========............................................................................

  • Graphics Team
    2x Engineering devs working on 5 tasks (40% load) thru 2022-03-07

..~~~~~~~~~~~~~~~~|~~...................................................................................

  • Narrative
    2x Design devs working on 3 tasks (114% load) thru 2022-03-03

................~~|~....................................................................................

  • Vehicle Feature Team
    1x Engineering dev working on 4 tasks (115% load) thru 2022-04-14

..............====|=============........................................................................

  • VFX Team
    1x Engineering dev working on 5 tasks (50% load) thru 2022-04-03

....=============.|.....................................................................................
....~~~~~~~~~~~~~~|~~~~~~~~~~...........................................................................

  • Weapon Feature Team
    1x Engineering dev working on 5 tasks (141% load) thru 2022-03-03

..================|=....................................................................................

Server Streaming

(Scheduled work ending soon!)

  • Network Team
    2x Engineering devs working on 6 tasks (71% load) thru 2022-03-14

..================|====.................................................................................

Shield Emitters

(Scheduled work ending soon!)

  • Vehicle Feature Team
    1x Engineering dev working on 2 tasks (123% load) thru 2022-03-14

..............====|====.................................................................................

Spacescaping

  • SQ42 Art
    1x Art dev working on 20 tasks (123% load) thru 2022-03-28

.=================|========.............................................................................

StarWords Improvements

(Scheduled work ending soon!)

  • Tools Team
    1x Engineering dev working on 4 tasks (247% load) thru 2022-03-14

..=========...====|====.................................................................................

Subsumption Editor Integration

  • AI Tech and Feature Team
    1x Engineering dev working on 7 tasks (169% load) thru 2022-03-16

..================|=====................................................................................

Theaters of War - Miscellaneous Support

  • Firesprite Team
    4x Design devs working on 15 tasks (10% load) thru 2022-06-30
    4x Art devs working on 15 tasks (7% load) thru 2022-06-30
    2x Engineering devs working on 8 tasks (11% load) thru 2022-06-30

.~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~====================..................................................
.~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~====================..................................................
.~~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~====================..................................................

Unannounced Vehicle

  • Vehicle Content - EU
    1x Design dev working on 17 tasks (122% load) thru 2022-06-02
    2x Art devs working on 15 tasks (123% load) thru 2022-04-21

............~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~..........................................................
....==============|===============......................................................................

Unannounced Vehicle

  • Vehicle Content - EU
    1x Art dev working on 18 tasks (244% load) thru 2022-05-05
    3x Design devs working on 21 tasks (81% load) thru 2022-06-02

..================|===================..................................................................
....==============|===========================..........................................................

  • Audio
    1x Audio dev will work on 5 tasks (333% load) starting 2022-03-06 thru 2022-03-31

..................|.========............................................................................

Unannounced Vehicle

  • Vehicle Content - EU
    2x Art devs working on 6 tasks (128% load) thru 2022-03-24
    1x Design dev working on 4 tasks (267% load) thru 2022-03-10

..............====|=======..======================......................................................
..............====|===..................................................................................

Unannounced Vehicle

  • Vehicle Content - EU
    1x Art dev working on 13 tasks (246% load) thru 2022-03-31
    1x Design dev working on 17 tasks (122% load) thru 2022-06-02

..================|=========............................................................................
............~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~..........................................................

Underground Facilities

  • Location Concept Art
    4x Art devs working on 12 tasks (71% load) thru 2022-03-14

..================|====...============================..................................................

Virtual AI Service

  • Systemic Services and Tools Team
    1x Engineering dev working on 1 task (128% load) thru 2022-03-14

..................|====...............................==================................................

Wheeled Vehicle Physics Improvements

(Scheduled work ending soon!)

  • Physics Team
    1x Engineering dev working on 3 tasks (79% load) thru 2022-03-07

..================|==...................................................................................

XenoThreat Armor

  • SC Character Art
    3x Art devs working on 8 tasks (55% load) thru 2022-03-24

..================|=======..............................................................................

Zero G Push & Pull

  • Actor Feature Team
    2x Animation devs working on 13 tasks (29% load) thru 2022-07-07

..~~~~~~~~~~~~~~~~|~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~................................................


The following deliverables are scheduled to begin (or continue) work within two weeks

Destructible Environments

(Starting soon!)

  • Planet Tech Team
    1x Engineering dev will work on 8 tasks (136% load) starting 2022-03-15 thru 2022-06-21

..................|...=============================...=========.........................................

DNA Head Textures Update

  • SC Character Art
    3x Art devs will work on 3 tasks (152% load) starting 2022-03-13 thru 2022-03-24

..................|...====..............................................................................

Ecosystem Enhancements

(Starting soon!)

  • Planet Tech Team
    1x Engineering dev will work on 2 tasks (256% load) starting 2022-03-15 thru 2022-03-28

..................|...=====...........................=========...=========.............................

Fire Extinguisher

  • Narrative
    1x Design dev will work on 3 tasks (227% load) starting 2022-03-06 thru 2022-03-17

..................|.~~~~................................................................................

  • Weapon Content Team
    1x Animation dev will work on 4 tasks (606% load) starting 2022-03-06 thru 2022-03-17

..................|.====................................................................................

Life Support T0

  • EU PU Gameplay Feature Team
    1x Engineering dev will work on 5 tasks (149% load) starting 2022-03-15 thru 2022-05-10
    1x Design dev will work on 6 tasks (71% load) starting 2022-03-15 thru 2022-05-24

..================|...=================...............==================..=====================...=====.
..~~~~~~~~~~~~~~~~|...~~~~~~~~~~~~~~~~~~~~~...~~~~~...~~~~~~~~~~~~~~~~~~..~~~~~~~~~~~~~~~~~~~~~...~~~~~.

Ship to Ship Refueling

  • EU PU Gameplay Feature Team
    2x Design devs will work on 2 tasks (64% load) starting 2022-03-15 thru 2022-03-28

..~~~~~~~~~~~~~~~~|...~~~~~.............................................................................

Underwater Rendering/Caustics

(Starting soon!)

  • Planet Tech Team
    1x Engineering dev will work on 2 tasks (256% load) starting 2022-03-15 thru 2022-03-28

..................|...=====...........=========.........................................................