Scheduled Deliverables
as of 2023-09-20
There are currently 66 scheduled deliverables being worked on by 54 teams
10 deliverables are scheduled to begin work by 5 team(s) within two weeks
This report lists the actively assigned deliverables and the associated teams, along with the number of developers assigned to each time period. Deliverable time allocations are often staggered over their total lifespan and have multiple devs in the same department working in parallel, but their allocations are obviously not going to be equal. For a better look at this, clicking the team name (or one of the completion dates listed below it) will display a rendering of the current waterfall chart iteration. This chart provides an overview of the schedule breakdown of each team in week long segments.
The timeslots you see on the RSI website are actually fragmented into many smaller sections, usually two week sprints. I do my best to combine relevant timespans by looking for overlaps (4 days currently). If a team says they end earlier than you expect, it means that there is some sizeable period of time between then and the next time they start working on the deliverable again.
The load calculation is an approximation based on the sum of the part-time and full-time tasks (averaged at 80 hours to complete a piece) divided by the team capacity (with a focus factor of 60%) over the given time period. Without exact hourly estimates for each task, a more accurate assessment doesn’t seem likely, so interpret the load as a given dev group’s general utilization on a deliverable.
extra analysis (click me)
There are approximately 327 devs (out of ~512, or 64%) with 676 assignments scheduled to work on 66 observable deliverables. Of those deliverables, 36% are for SQ42 exclusively, with ~262 devs (51%) scheduled for approximately 5539 man-days. 24% of deliverables are shared between both projects.
12 deliverable(s) are not currently scheduled to continue work after this sprint:
- Arena Commander: Experimental Game Modes
- Arena Commander: Frontend Update
- Arena Commander: New Racetracks
- Entity Properties Plugin
- HEX
- Jump Points
- Persistent Hangars
- Persistent Streaming and Server Meshing
- Pyro System, Planet, and Mission Setup
- Quantum Simulation
- TestRunner Improvements
- Vehicle Tractor Beams
- Actor Feature Team
full-time with 88 task(s) scheduled, 50% of which are for SQ42 - Actor Tech Team
full-time with 25 task(s) scheduled, 50% of which are for SQ42 - AI Content Team
38% part-time with 107 task(s) scheduled, 71% of which are for SQ42 - AI Tech and Feature Team
27% part-time with 121 task(s) scheduled, 75% of which are for SQ42 - Arena Commander Feature Team
full-time with 48 task(s) scheduled, all of which are for SC - Audio
100% part-time with 77 task(s) scheduled, all of which are for SQ42 - Character Tech Art
full-time with 44 task(s) scheduled, all of which are for SQ42 - Editor Team
full-time with 47 task(s) scheduled, 50% of which are for SQ42 - Engine Team
full-time with 26 task(s) scheduled, 50% of which are for SQ42 - EU Landing Zone 1
full-time with 66 task(s) scheduled, all of which are for SC - EU Landing Zone 2
full-time with 62 task(s) scheduled, all of which are for SC - EU PU Gameplay Feature Team
9% part-time with 46 task(s) scheduled, 20% of which are for SQ42 - EU Sandbox 1
full-time with 66 task(s) scheduled, all of which are for SC - EU Sandbox 2
full-time with 42 task(s) scheduled, all of which are for SC - Facial Animation
full-time with 33 task(s) scheduled, all of which are for SQ42 - Game Services Team
16% part-time with 75 task(s) scheduled, all of which are for SC - Graphics Team
full-time with 60 task(s) scheduled, 50% of which are for SQ42 - Live Tools Team
full-time with 49 task(s) scheduled, 33% of which are for SQ42 - Location Concept Art
full-time with 30 task(s) scheduled, all of which are for SC - Mission Feature Team
full-time with 52 task(s) scheduled, 50% of which are for SQ42 - Motion Capture Team
7% part-time with 54 task(s) scheduled, all of which are for SQ42 - MTL Sandbox 1
7% part-time with 228 task(s) scheduled, all of which are for SC - NA PU Gameplay Feature Team
44% part-time with 34 task(s) scheduled, all of which are for SC - Narrative
full-time with 22 task(s) scheduled, all of which are for SC - Network Team
full-time with 25 task(s) scheduled, all of which are for SC - Persistent Tech Team
full-time with 20 task(s) scheduled, all of which are for SC - Physics Team
full-time with 15 task(s) scheduled, 50% of which are for SQ42 - SC Character Art
full-time with 38 task(s) scheduled, 50% of which are for SQ42 - SQ42 Art
15% part-time with 118 task(s) scheduled, all of which are for SQ42 - SQ42 Character Art
9% part-time with 47 task(s) scheduled, all of which are for SQ42 - SQ42 Feature Team
full-time with 25 task(s) scheduled, 60% of which are for SQ42 - SQ42 Level Design 1 - FPS
full-time with 77 task(s) scheduled, all of which are for SQ42 - SQ42 Level Design 2 - Flight
38% part-time with 55 task(s) scheduled, all of which are for SQ42 - SQ42 Level Design 3 - Social
full-time with 35 task(s) scheduled, all of which are for SQ42 - SQ42 UI Feature Team
23% part-time with 62 task(s) scheduled, 60% of which are for SQ42 - Systemic Services and Tools Team
6% part-time with 31 task(s) scheduled, 33% of which are for SQ42 - Tech Animation Team
20% part-time with 45 task(s) scheduled, all of which are for SQ42 - Tools Team
full-time with 27 task(s) scheduled, 50% of which are for SQ42 - UI Tech Team
full-time with 16 task(s) scheduled, 50% of which are for SQ42 - US PU Gameplay Feature Team
22% part-time with 27 task(s) scheduled, 50% of which are for SQ42 - Vehicle Content - MTL
22% part-time with 50 task(s) scheduled, all of which are for SC - Vehicle Content - US
13% part-time with 23 task(s) scheduled, all of which are for SC - Vehicle Feature Team
full-time with 22 task(s) scheduled, 50% of which are for SQ42 - Vehicle Gameplay Feature Team
full-time with 15 task(s) scheduled, 50% of which are for SQ42 - Weapon Content Team
full-time with 25 task(s) scheduled, 67% of which are for SQ42 - Weapon Feature Team
31% part-time with 125 task(s) scheduled, 42% of which are for SQ42
Actor Status T2
- Actor Feature Team
2x Engineering devs working on 13 tasks (102% load) thru 2023-10-14
2x Engineering devs working on 13 tasks (102% load) thru 2023-10-14
........................~~~~====================..======.=================|=========....................
Additional Derelict Settlements
- EU Sandbox 1
3x Art devs working on 22 tasks (177% load) thru 2023-11-05
3x Art devs working on 22 tasks (177% load) thru 2023-11-05
................................................~~~~=============...======|==============...========....
- MTL Sandbox 1
2x Design devs working on 35 tasks (82% load) thru 2023-12-14
3x Art devs working on 41 tasks (62% load) thru 2023-12-14
2x Design devs working on 35 tasks (82% load) thru 2023-12-14
3x Art devs working on 41 tasks (62% load) thru 2023-12-14
==============================.===============~~~~~~======================|=========================....
==============================.===============~~~~~~======================|=========================....
Arena Commander: Experimental Game Modes
(Scheduled work ending soon!)
- Arena Commander Feature Team
1x Engineering dev working on 12 tasks (114% load) thru 2023-09-20
1x Engineering dev working on 12 tasks (114% load) thru 2023-09-20
======================..==================================================|=............................
Arena Commander: Frontend Update
(Scheduled work ending soon!)
- Arena Commander Feature Team
1x Design dev working on 12 tasks (114% load) thru 2023-09-20
1x Engineering dev working on 12 tasks (114% load) thru 2023-09-20
1x Design dev working on 12 tasks (114% load) thru 2023-09-20
1x Engineering dev working on 12 tasks (114% load) thru 2023-09-20
........................==================================================|=............................
........................==================================================|=............................
Arena Commander: New Racetracks
(Scheduled work ending soon!)
- Arena Commander Feature Team
1x Design dev working on 12 tasks (114% load) thru 2023-09-20
1x Design dev working on 12 tasks (114% load) thru 2023-09-20
........................==================================================|=............................
Bounty Hunter V2
- EU Landing Zone 2
3x Art devs working on 37 tasks (60% load) thru 2023-12-14
3x Art devs working on 37 tasks (60% load) thru 2023-12-14
==========================================================================|=========================....
- Mission Feature Team
7x Design devs will work on 18 tasks (95% load) starting 2023-09-21 thru 2023-11-05
2x Engineering devs will work on 11 tasks (204% load) starting 2023-09-21 thru 2023-11-05
7x Design devs will work on 18 tasks (95% load) starting 2023-09-21 thru 2023-11-05
2x Engineering devs will work on 11 tasks (204% load) starting 2023-09-21 thru 2023-11-05
....=================...................============================......|==============...............
....=================...============================......................|==============...............
Bug Fixing & Tech Debt
- Actor Feature Team
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
1x Animation dev working on 3 tasks (83% load) thru 2023-10-14
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
1x Animation dev working on 3 tasks (83% load) thru 2023-10-14
........................~~~~====================..======.=================|=========....................
....................................============................==========|=========....................
- AI Tech and Feature Team
11x Engineering devs working on 4 tasks (21% load) thru 2023-10-14
11x Engineering devs working on 4 tasks (21% load) thru 2023-10-14
............=========================.......~~~~~~~~~~~~.========.......==|=========....................
- Engine Team
5x Engineering devs working on 26 tasks (255% load) thru 2023-09-28
5x Engineering devs working on 26 tasks (255% load) thru 2023-09-28
................====~~~~~...............========..................========|===..........................
- EU PU Gameplay Feature Team
3x Design devs working on 8 tasks (116% load) thru 2023-09-20
3x Design devs working on 8 tasks (116% load) thru 2023-09-20
=========================.......=============...................====~~~~~.|.........====~~~~~...........
....=====================.......=============...................====~~~~==|=........~~~~~~~~========....
- Graphics Team
3x Tech Content devs working on 5 tasks (62% load) thru 2023-09-29
13x Engineering devs working on 55 tasks (157% load) thru 2023-09-29
3x Tech Content devs working on 5 tasks (62% load) thru 2023-09-29
13x Engineering devs working on 55 tasks (157% load) thru 2023-09-29
..................=======...................=======.............==========|===..........................
..................=======...................=======.............==========|===..........................
- Live Tools Team
7x Engineering devs working on 22 tasks (19% load) thru 2023-09-28
7x Engineering devs working on 22 tasks (19% load) thru 2023-09-28
==========================================================================|===..........................
- Mission Feature Team
9x Design devs working on 32 tasks (456% load) thru 2023-09-20
5x Engineering devs working on 20 tasks (513% load) thru 2023-09-20
9x Design devs working on 32 tasks (456% load) thru 2023-09-20
5x Engineering devs working on 20 tasks (513% load) thru 2023-09-20
....................=====.............................................====|=................========....
....=====================.............................................====|=................========....
- Physics Team
4x Engineering devs working on 15 tasks (139% load) thru 2023-09-29
4x Engineering devs working on 15 tasks (139% load) thru 2023-09-29
..................=======...................=======.............==========|===..........................
- Systemic Services and Tools Team
6x Engineering devs working on 6 tasks (34% load) thru 2023-09-20
6x Engineering devs working on 6 tasks (34% load) thru 2023-09-20
....................=====...................=====.............============|=............................
- US PU Gameplay Feature Team
7x Design devs working on 9 tasks (27% load) thru 2023-09-20
5x Engineering devs working on 12 tasks (375% load) thru 2023-09-20
4x Art devs working on 6 tasks (69% load) thru 2023-09-20
7x Design devs working on 9 tasks (27% load) thru 2023-09-20
5x Engineering devs working on 12 tasks (375% load) thru 2023-09-20
4x Art devs working on 6 tasks (69% load) thru 2023-09-20
========================....========~~~~=========...======================|=............................
....................====....................=====.......................~~|~............................
....................====............~~~~~~~~~~~~~...............==========|=............................
Building Interiors
- MTL Sandbox 1
13x Art devs working on 47 tasks (23% load) thru 2023-12-14
5x Design devs working on 29 tasks (27% load) thru 2023-12-14
13x Art devs working on 47 tasks (23% load) thru 2023-12-14
5x Design devs working on 29 tasks (27% load) thru 2023-12-14
........................======.===============~~~~~~======================|=========================....
==============================.===============~~~~~~======================|=========================....
Chapter 02
- SQ42 Character Art
3x Art devs working on 11 tasks (67% load) thru 2023-10-14
3x Art devs working on 11 tasks (67% load) thru 2023-10-14
................~~~~====........~~~~........====..======....==============|=========....................
Chapter 04
- AI Content Team
7x Design devs working on 29 tasks (22% load) thru 2023-10-14
7x Design devs working on 29 tasks (22% load) thru 2023-10-14
========================================~~~~~~~~~~======.===========~~~~==|=========....................
- SQ42 Art
6x Art devs working on 13 tasks (34% load) thru 2023-10-14
6x Art devs working on 13 tasks (34% load) thru 2023-10-14
............=============.........................======.=================|=========....................
- SQ42 Character Art
4x Art devs working on 9 tasks (35% load) thru 2023-10-14
4x Art devs working on 9 tasks (35% load) thru 2023-10-14
============~~~~================================..======.=================|=========....................
- SQ42 Level Design 1 - FPS
1x Design dev working on 4 tasks (230% load) thru 2023-10-14
1x Design dev working on 4 tasks (230% load) thru 2023-10-14
....................=====...................=====.......................==|=========....................
- SQ42 Level Design 3 - Social
2x Design devs working on 6 tasks (83% load) thru 2023-10-14
2x Design devs working on 6 tasks (83% load) thru 2023-10-14
....................................=============...............==========|=========....................
Chapter 05
- Character Tech Art
5x Tech Content devs working on 10 tasks (56% load) thru 2023-10-14
5x Tech Content devs working on 10 tasks (56% load) thru 2023-10-14
........============................============................==========|=========....................
Chapter 07
- SQ42 Level Design 2 - Flight
4x Design devs working on 13 tasks (43% load) thru 2023-10-14
4x Design devs working on 13 tasks (43% load) thru 2023-10-14
========================~~~~=====================.======.=================|=========....................
Chapter 10
- SQ42 Level Design 3 - Social
1x Design dev working on 5 tasks (189% load) thru 2023-10-14
1x Design dev working on 5 tasks (189% load) thru 2023-10-14
........................................=========...................======|=========....................
Chapter 11
- SQ42 Level Design 2 - Flight
3x Design devs working on 8 tasks (46% load) thru 2023-10-14
3x Design devs working on 8 tasks (46% load) thru 2023-10-14
....====~~~~=============...====~~~~=============........===~~~~==========|=========....................
Chapter 12
- AI Content Team
6x Design devs working on 9 tasks (57% load) thru 2023-10-14
6x Design devs working on 9 tasks (57% load) thru 2023-10-14
====~~~~=====...~~~~~...~~~~~...........====~~~~~~~~~~~~............======|=========....................
- SQ42 Character Art
5x Art devs working on 13 tasks (41% load) thru 2023-10-14
5x Art devs working on 13 tasks (41% load) thru 2023-10-14
................~~~~====........====~~~~========..======.=================|=========....................
- SQ42 Level Design 1 - FPS
5x Design devs working on 11 tasks (49% load) thru 2023-10-14
5x Design devs working on 11 tasks (49% load) thru 2023-10-14
........=================.......=================...........==============|=========....................
Chapter 13
- SQ42 Level Design 3 - Social
2x Design devs working on 6 tasks (83% load) thru 2023-10-14
2x Design devs working on 6 tasks (83% load) thru 2023-10-14
....................................=============...............==========|=========....................
Chapter 14
- SQ42 Level Design 1 - FPS
10x Design devs working on 9 tasks (14% load) thru 2023-10-14
10x Design devs working on 9 tasks (14% load) thru 2023-10-14
=================================================.======.=================|=========....................
Chapter 16
- SQ42 Level Design 2 - Flight
3x Design devs working on 7 tasks (37% load) thru 2023-10-14
3x Design devs working on 7 tasks (37% load) thru 2023-10-14
........~~~~=============.......~~~~=============...........~~~~==========|=========....................
Chapter 17
- SQ42 Art
10x Art devs working on 9 tasks (14% load) thru 2023-10-14
10x Art devs working on 9 tasks (14% load) thru 2023-10-14
=========================.........................======.=================|=========....................
- SQ42 Level Design 1 - FPS
2x Design devs working on 9 tasks (71% load) thru 2023-10-14
2x Design devs working on 9 tasks (71% load) thru 2023-10-14
=================================================.======.=================|=========....................
- SQ42 Level Design 2 - Flight
4x Design devs working on 9 tasks (33% load) thru 2023-10-14
4x Design devs working on 9 tasks (33% load) thru 2023-10-14
====================~~~~====================~~~~~.======.===============~~|~~~~~~~~~....................
Chapter 18
- Character Tech Art
3x Tech Content devs working on 5 tasks (63% load) thru 2023-10-14
3x Tech Content devs working on 5 tasks (63% load) thru 2023-10-14
........................................========....................======|=========....................
Chapter 19
- SQ42 Art
8x Art devs working on 16 tasks (37% load) thru 2023-10-14
8x Art devs working on 16 tasks (37% load) thru 2023-10-14
.........................................................=================|=========....................
Chapter 20
- Character Tech Art
1x Tech Content dev working on 4 tasks (230% load) thru 2023-10-14
1x Tech Content dev working on 4 tasks (230% load) thru 2023-10-14
............................................====........................==|=========....................
- SQ42 Level Design 1 - FPS
6x Design devs working on 9 tasks (57% load) thru 2023-10-14
6x Design devs working on 9 tasks (57% load) thru 2023-10-14
................=========...............=========...................======|=========....................
Chapter 21
- AI Content Team
7x Design devs working on 5 tasks (16% load) thru 2023-10-14
7x Design devs working on 5 tasks (16% load) thru 2023-10-14
........~~~~============~~~~~~~~~~~~~...~~~~~~~~~~~~~~~~.~~~~~~~~...~~~~==|=========....................
- SQ42 Art
3x Art devs working on 9 tasks (24% load) thru 2023-10-14
3x Art devs working on 9 tasks (24% load) thru 2023-10-14
............~~~~~~~~~~~~~.........................~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
- SQ42 Character Art
1x Art dev working on 7 tasks (156% load) thru 2023-10-14
1x Art dev working on 7 tasks (156% load) thru 2023-10-14
................................================............==============|=========....................
- SQ42 Level Design 2 - Flight
1x Design dev working on 4 tasks (230% load) thru 2023-10-14
1x Design dev working on 4 tasks (230% load) thru 2023-10-14
....................=====...................=====.......................==|=========....................
- SQ42 Level Design 3 - Social
3x Design devs working on 6 tasks (56% load) thru 2023-10-14
3x Design devs working on 6 tasks (56% load) thru 2023-10-14
....................................=============...............==========|=========....................
Chapter 22
- SQ42 Character Art
2x Art devs working on 7 tasks (78% load) thru 2023-10-14
2x Art devs working on 7 tasks (78% load) thru 2023-10-14
====............~~~~........................====..======....==============|=========....................
- SQ42 Level Design 1 - FPS
10x Design devs working on 21 tasks (33% load) thru 2023-10-14
10x Design devs working on 21 tasks (33% load) thru 2023-10-14
=================================================.======.=================|=========....................
- SQ42 Level Design 2 - Flight
2x Design devs working on 7 tasks (50% load) thru 2023-10-14
2x Design devs working on 7 tasks (50% load) thru 2023-10-14
........~~~~========~~~~~.......~~~~========~~~~~...........~~~~========~~|~~~~~~~~~....................
Chapter 23
- SQ42 Art
3x Art devs working on 9 tasks (24% load) thru 2023-10-14
3x Art devs working on 9 tasks (24% load) thru 2023-10-14
............~~~~~~~~~~~~~.........................~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
- SQ42 Level Design 3 - Social
2x Design devs working on 7 tasks (78% load) thru 2023-10-14
2x Design devs working on 7 tasks (78% load) thru 2023-10-14
~~~~=====.......................=================...........==============|=========....................
Chapter 24
- SQ42 Level Design 1 - FPS
1x Design dev working on 5 tasks (189% load) thru 2023-10-14
1x Design dev working on 5 tasks (189% load) thru 2023-10-14
................=========...............=========...................======|=========....................
- SQ42 Level Design 2 - Flight
2x Design devs working on 7 tasks (44% load) thru 2023-10-14
2x Design devs working on 7 tasks (44% load) thru 2023-10-14
........~~~~~~~~~~~~=====.......~~~~~~~~~~~~=====...........~~~~~~~~~~~~==|=========....................
Chapter 25
- Character Tech Art
1x Tech Content dev working on 4 tasks (230% load) thru 2023-10-14
1x Tech Content dev working on 4 tasks (230% load) thru 2023-10-14
............................................====........................==|=========....................
- SQ42 Art
4x Art devs working on 17 tasks (67% load) thru 2023-10-14
4x Art devs working on 17 tasks (67% load) thru 2023-10-14
..................................................======.=================|=========....................
Chapter 26
- SQ42 Art
11x Art devs working on 21 tasks (30% load) thru 2023-10-14
11x Art devs working on 21 tasks (30% load) thru 2023-10-14
....................=====.........................======.=================|=========....................
- SQ42 Level Design 1 - FPS
9x Design devs working on 9 tasks (16% load) thru 2023-10-14
9x Design devs working on 9 tasks (16% load) thru 2023-10-14
=================================================.======.=================|=========....................
- SQ42 Level Design 3 - Social
1x Design dev working on 5 tasks (189% load) thru 2023-10-14
1x Design dev working on 5 tasks (189% load) thru 2023-10-14
....................=====...............=========...................======|=========....................
- SQ42 UI Feature Team
2x Art devs working on 4 tasks (115% load) thru 2023-10-14
2x Art devs working on 4 tasks (115% load) thru 2023-10-14
....................................========~~~~~~~~~...................==|=========....................
Chapter 27
- SQ42 Art
1x Art dev working on 7 tasks (156% load) thru 2023-10-14
1x Art dev working on 7 tasks (156% load) thru 2023-10-14
............................................................==============|=========....................
Character Creator
- SQ42 Feature Team
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
................=====...=============.............======.=================|=========....................
Character Work
- AI Tech and Feature Team
8x Engineering devs working on 37 tasks (26% load) thru 2023-10-14
3x Animation devs working on 25 tasks (47% load) thru 2023-10-14
1x Design dev working on 27 tasks (61% load) thru 2023-10-14
8x Engineering devs working on 37 tasks (26% load) thru 2023-10-14
3x Animation devs working on 25 tasks (47% load) thru 2023-10-14
1x Design dev working on 27 tasks (61% load) thru 2023-10-14
============================================~~~~~~~~~~~~.=================|=========....................
============================================~~~~~~~~~~~~.=================|=========....................
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
- Audio
11x Audio devs working on 35 tasks (16% load) thru 2023-09-27
11x Audio devs working on 35 tasks (16% load) thru 2023-09-27
............................~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..........................
- Character Tech Art
8x Tech Content devs working on 21 tasks (41% load) thru 2023-10-14
8x Tech Content devs working on 21 tasks (41% load) thru 2023-10-14
........................========....============..======.=================|=========....................
- Facial Animation
9x Animation devs working on 33 tasks (70% load) thru 2023-09-28
9x Animation devs working on 33 tasks (70% load) thru 2023-09-28
====================~~~~~~~~====================....======================|===..........................
- Motion Capture Team
9x Animation devs working on 54 tasks (23% load) thru 2023-09-28
9x Animation devs working on 54 tasks (23% load) thru 2023-09-28
============================================~~~~~~~~~~====================|===..........................
- SC Character Art
3x Art devs working on 17 tasks (89% load) thru 2023-10-14
3x Art devs working on 17 tasks (89% load) thru 2023-10-14
........................========================..======.=================|=========....................
- Tech Animation Team
12x Tech Content devs working on 45 tasks (22% load) thru 2023-09-20
12x Tech Content devs working on 45 tasks (22% load) thru 2023-09-20
============================================~~~~~~~~~~====================|=............................
Cutting T2
- Weapon Feature Team
1x Engineering dev working on 21 tasks (124% load) thru 2023-10-14
1x Engineering dev working on 21 tasks (124% load) thru 2023-10-14
==============================.=========================.=================|=========....................
Disarray Ammunition
- Weapon Feature Team
1x Engineering dev working on 11 tasks (67% load) thru 2023-10-14
1x Engineering dev working on 11 tasks (67% load) thru 2023-10-14
..........................................~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
Distortion Propagation
- Weapon Feature Team
1x Engineering dev working on 13 tasks (130% load) thru 2023-10-14
1x Engineering dev working on 13 tasks (130% load) thru 2023-10-14
..................................======================.=================|=========....................
Entity Properties Plugin
(Scheduled work ending soon!)
- Editor Team
1x Engineering dev working on 7 tasks (243% load) thru 2023-09-28
1x Engineering dev working on 7 tasks (243% load) thru 2023-09-28
=========...=====================...========================..============|===..........................
Freight Elevators
- EU Landing Zone 2
2x Art devs working on 13 tasks (61% load) thru 2023-12-14
2x Art devs working on 13 tasks (61% load) thru 2023-12-14
............=============.......................==========================|=========================....
- NA PU Gameplay Feature Team
3x Engineering devs working on 11 tasks (43% load) thru 2023-09-20
1x Design dev working on 7 tasks (150% load) thru 2023-09-20
3x Engineering devs working on 11 tasks (43% load) thru 2023-09-20
1x Design dev working on 7 tasks (150% load) thru 2023-09-20
....................................................~~~~~~~~~~~~~~~~~~~~~~|~............................
....................................................======================|=............................
Headhunters Faction Outfits
- SC Character Art
5x Art devs working on 21 tasks (66% load) thru 2023-10-14
5x Art devs working on 21 tasks (66% load) thru 2023-10-14
........................========================..======.=================|=========....................
HEX
(Scheduled work ending soon!)
- Live Tools Team
5x Engineering devs working on 27 tasks (33% load) thru 2023-09-28
5x Engineering devs working on 27 tasks (33% load) thru 2023-09-28
==========================================================================|===..........................
Incendiary Ammunition
- Weapon Feature Team
1x Engineering dev working on 11 tasks (67% load) thru 2023-10-14
1x Engineering dev working on 11 tasks (67% load) thru 2023-10-14
..........................................~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
Jump Points
(Scheduled work ending soon!)
- Vehicle Gameplay Feature Team
2x Engineering devs working on 8 tasks (85% load) thru 2023-09-20
3x Design devs working on 7 tasks (50% load) thru 2023-09-20
2x Engineering devs working on 8 tasks (85% load) thru 2023-09-20
3x Design devs working on 7 tasks (50% load) thru 2023-09-20
....................................................======================|=............................
....................................................======================|=............................
Map and Radar System Rework
- SQ42 Feature Team
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
....=============================================.======.=================|=========....................
- SQ42 UI Feature Team
4x Art devs working on 17 tasks (51% load) thru 2023-10-14
4x Art devs working on 17 tasks (51% load) thru 2023-10-14
....=====...........=====...=====........................=================|.............................
=============================.....................~~~~~~.=================|=========....................
Miscellaneous Support
- Actor Feature Team
4x Animation devs working on 13 tasks (51% load) thru 2023-10-14
2x Engineering devs working on 9 tasks (71% load) thru 2023-10-14
3x Design devs working on 17 tasks (89% load) thru 2023-10-14
4x Animation devs working on 13 tasks (51% load) thru 2023-10-14
2x Engineering devs working on 9 tasks (71% load) thru 2023-10-14
3x Design devs working on 17 tasks (89% load) thru 2023-10-14
====================~~~~~~~~====================..======.=================|=========....................
====================~~~~~~~~====================..======.=================|=========....................
====================~~~~~~~~====================..======.=================|=========....................
- Actor Tech Team
6x Engineering devs working on 25 tasks (66% load) thru 2023-10-14
6x Engineering devs working on 25 tasks (66% load) thru 2023-10-14
====================~~~~~~~~====================..======.=================|=========....................
- AI Content Team
2x Tech Content devs working on 31 tasks (35% load) thru 2023-10-14
4x Animation devs working on 33 tasks (47% load) thru 2023-10-14
2x Tech Content devs working on 31 tasks (35% load) thru 2023-10-14
4x Animation devs working on 33 tasks (47% load) thru 2023-10-14
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
============================================~~~~~~~~~~~~.=================|=========....................
- Editor Team
4x Engineering devs working on 12 tasks (104% load) thru 2023-09-28
1x Design dev working on 28 tasks (132% load) thru 2023-09-28
4x Engineering devs working on 12 tasks (104% load) thru 2023-09-28
1x Design dev working on 28 tasks (132% load) thru 2023-09-28
=========...=====================...========================..============|===..........................
==========================================================================|===..........................
- UI Tech Team
4x Engineering devs working on 16 tasks (196% load) thru 2023-09-28
4x Engineering devs working on 16 tasks (196% load) thru 2023-09-28
................=========...............=============.............========|===..........................
- Weapon Feature Team
5x Design devs working on 37 tasks (40% load) thru 2023-10-14
5x Design devs working on 37 tasks (40% load) thru 2023-10-14
==============================.=========================.=================|=========....................
mobiGlas Rework
- SQ42 Feature Team
2x Engineering devs working on 7 tasks (78% load) thru 2023-10-14
2x Engineering devs working on 7 tasks (78% load) thru 2023-10-14
=====.......=========...=====.......=============.======....==============|=========....................
- SQ42 UI Feature Team
2x Design devs working on 10 tasks (51% load) thru 2023-10-14
1x Art dev working on 4 tasks (230% load) thru 2023-10-14
2x Design devs working on 10 tasks (51% load) thru 2023-10-14
1x Art dev working on 4 tasks (230% load) thru 2023-10-14
............................=====...........~~~~~~======.=================|=========....................
............................=====...........~~~~~~~~~....====...........==|=========....................
New Missions - Cargo Hauling
- Narrative
1x Design dev working on 7 tasks (243% load) thru 2023-09-28
1x Design dev working on 7 tasks (243% load) thru 2023-09-28
..............................................................============|===..........................
- Mission Feature Team
2x Design devs will work on 7 tasks (130% load) starting 2023-09-21 thru 2023-11-05
2x Design devs will work on 7 tasks (130% load) starting 2023-09-21 thru 2023-11-05
..................................................==================......|==============...............
New Player Experience
- EU Landing Zone 2
1x Art dev working on 12 tasks (112% load) thru 2023-12-14
1x Art dev working on 12 tasks (112% load) thru 2023-12-14
=====...........................................==========================|=========================....
- Mission Feature Team
2x Design devs will work on 5 tasks (93% load) starting 2023-09-21 thru 2023-11-05
2x Design devs will work on 5 tasks (93% load) starting 2023-09-21 thru 2023-11-05
..................................................==================......|==============...............
Origin X1
- Vehicle Content - US
4x Art devs working on 13 tasks (58% load) thru 2023-10-08
1x Design dev working on 10 tasks (303% load) thru 2023-09-25
4x Art devs working on 13 tasks (58% load) thru 2023-10-08
1x Design dev working on 10 tasks (303% load) thru 2023-09-25
........................................................============~~~~~~|~~~~~~.......................
............................................................==============|==...........................
..........................................................................|.....=========...............
Outpost Homestead - Independent & Outlaw
- EU Sandbox 1
12x Art devs working on 28 tasks (56% load) thru 2023-11-05
4x Design devs working on 16 tasks (97% load) thru 2023-11-05
12x Art devs working on 28 tasks (56% load) thru 2023-11-05
4x Design devs working on 16 tasks (97% load) thru 2023-11-05
==================..==========.============...~~~~~~=============...======|==============...========....
==================..==========.============...~~~~~~=============...======|==============...========....
Persistent Hangars
(Scheduled work ending soon!)
- NA PU Gameplay Feature Team
2x Engineering devs working on 9 tasks (69% load) thru 2023-09-20
1x Design dev working on 7 tasks (150% load) thru 2023-09-20
2x Engineering devs working on 9 tasks (69% load) thru 2023-09-20
1x Design dev working on 7 tasks (150% load) thru 2023-09-20
....................................................~~~~~~~~~~~~~~~~~~~~~~|~............................
....................................................======================|=............................
Persistent Streaming and Server Meshing
(Scheduled work ending soon!)
- Game Services Team
10x Engineering devs working on 75 tasks (26% load) thru 2023-09-28
10x Engineering devs working on 75 tasks (26% load) thru 2023-09-28
==========================================================================|===..........................
- Network Team
9x Engineering devs working on 25 tasks (53% load) thru 2023-09-28
9x Engineering devs working on 25 tasks (53% load) thru 2023-09-28
====================~~~~~~~~====================....======================|===..........................
- Persistent Tech Team
4x Engineering devs working on 20 tasks (96% load) thru 2023-09-28
4x Engineering devs working on 20 tasks (96% load) thru 2023-09-28
====================~~~~~~~~====================....======================|===..........................
Plasma Ammunition
- Weapon Feature Team
1x Engineering dev working on 11 tasks (67% load) thru 2023-10-14
1x Engineering dev working on 11 tasks (67% load) thru 2023-10-14
..........................................~~~~~~~~~~~~~~.~~~~~~~~~~~~~~~~~|~~~~~~~~~....................
Player Interaction Experience T2 - Visor HUD & Helmet
- SQ42 UI Feature Team
3x Design devs working on 19 tasks (50% load) thru 2023-10-14
3x Design devs working on 19 tasks (50% load) thru 2023-10-14
........=====...........====================~~~~~~~~~~~~.=================|=========....................
Pyro Space Stations
- EU Landing Zone 1
14x Art devs working on 51 tasks (110% load) thru 2023-11-05
3x Design devs working on 15 tasks (152% load) thru 2023-11-05
14x Art devs working on 51 tasks (110% load) thru 2023-11-05
3x Design devs working on 15 tasks (152% load) thru 2023-11-05
=============...........=================.......=================.......==|==============...............
=============...........=================.......=================.......==|==============...............
Pyro System, Planet, and Mission Setup
(Scheduled work ending soon!)
- Narrative
5x Design devs working on 9 tasks (34% load) thru 2023-09-28
5x Design devs working on 9 tasks (34% load) thru 2023-09-28
....................................................======================|===..........................
Quantum Simulation
(Scheduled work ending soon!)
- Systemic Services and Tools Team
6x Engineering devs working on 25 tasks (85% load) thru 2023-09-20
6x Engineering devs working on 25 tasks (85% load) thru 2023-09-20
=================================================.========================|=............................
Resource Management
- EU PU Gameplay Feature Team
5x Engineering devs working on 13 tasks (35% load) thru 2023-11-05
3x Design devs working on 15 tasks (46% load) thru 2023-12-14
5x Engineering devs working on 13 tasks (35% load) thru 2023-11-05
3x Design devs working on 15 tasks (46% load) thru 2023-12-14
=====...........=====================...=========...======================|=========~~~~~...========....
=========...............~~~~~~~~~.......====~~~~~...====~~~~~~~~==========|~~~~~~~~~~~~~============....
- Vehicle Feature Team
5x Engineering devs working on 7 tasks (28% load) thru 2023-09-25
5x Engineering devs working on 7 tasks (28% load) thru 2023-09-25
............................=========...............======================|==...........................
Salvage - Vehicle Munching
- EU PU Gameplay Feature Team
1x Engineering dev working on 10 tasks (309% load) thru 2023-11-05
1x Design dev will work on 8 tasks (215% load) starting 2023-09-21 thru 2023-10-22
1x Engineering dev working on 10 tasks (309% load) thru 2023-11-05
1x Design dev will work on 8 tasks (215% load) starting 2023-09-21 thru 2023-10-22
........................=========...........=====...=================...==|==============...========....
........................~~~~~...............~~~~~...~~~~~~~~~~~~~.........|~~~~~~~~~~...................
Sliding
- Actor Feature Team
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
2x Animation devs working on 6 tasks (83% load) thru 2023-10-14
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
2x Animation devs working on 6 tasks (83% load) thru 2023-10-14
........................~~~~====================..======.=================|=========....................
........................~~~~........============..======........==========|=========....................
SQ42 - Vehicle Support
- AI Tech and Feature Team
3x Engineering devs working on 13 tasks (164% load) thru 2023-10-14
3x Engineering devs working on 13 tasks (164% load) thru 2023-10-14
........................................====~~~~~~~~~...............======|=========....................
- Audio
11x Audio devs working on 42 tasks (19% load) thru 2023-09-27
11x Audio devs working on 42 tasks (19% load) thru 2023-09-27
============================~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~|~~~..........................
- SQ42 Art
4x Art devs working on 17 tasks (67% load) thru 2023-10-14
4x Art devs working on 17 tasks (67% load) thru 2023-10-14
=========================.........................======.=================|=========....................
- SQ42 UI Feature Team
2x Art devs working on 8 tasks (73% load) thru 2023-10-14
2x Art devs working on 8 tasks (73% load) thru 2023-10-14
............................================~~~~~~~~~....=================|=========....................
- Vehicle Feature Team
7x Engineering devs working on 15 tasks (43% load) thru 2023-09-25
7x Engineering devs working on 15 tasks (43% load) thru 2023-09-25
======================..=========================...======================|==...........................
- Weapon Content Team
6x Art devs working on 19 tasks (211% load) thru 2023-09-28
6x Art devs working on 19 tasks (211% load) thru 2023-09-28
..==========================..============..========================..====|===..........................
- Vehicle Content - EU
5x Art devs will work on 11 tasks (50% load) starting 2023-10-01 thru 2023-12-14
4x Design devs will work on 13 tasks (73% load) starting 2023-10-01 thru 2023-12-14
5x Art devs will work on 11 tasks (50% load) starting 2023-10-01 thru 2023-12-14
4x Design devs will work on 13 tasks (73% load) starting 2023-10-01 thru 2023-12-14
..........................======================....======================|...======================....
======================....======================....======================|...======================....
Subsumption Editor Integration
- AI Tech and Feature Team
1x Engineering dev working on 15 tasks (116% load) thru 2023-10-14
1x Engineering dev working on 15 tasks (116% load) thru 2023-10-14
=====================...====================~~~~~~~~~~~~.=================|=========....................
Swimming T0
- Actor Feature Team
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
1x Engineering dev working on 9 tasks (142% load) thru 2023-10-14
........................========================..======.=================|=========....................
............................========.....................=================|.............................
TestRunner Improvements
(Scheduled work ending soon!)
- Tools Team
4x Engineering devs working on 27 tasks (42% load) thru 2023-09-28
4x Engineering devs working on 27 tasks (42% load) thru 2023-09-28
==========================================================================|===..........................
Unannounced Vehicle
- Vehicle Content - MTL
2x Art devs working on 23 tasks (154% load) thru 2023-10-05
2x Art devs working on 23 tasks (154% load) thru 2023-10-05
..........................======~~~~~~~~~~~~~~~~....~~~~~~~~~~~~~~~~~~~~~~|~~~~~........................
Unannounced Vehicle
- Vehicle Content - MTL
2x Art devs working on 27 tasks (237% load) thru 2023-10-05
2x Art devs working on 27 tasks (237% load) thru 2023-10-05
..................................==============....======================|=====........................
Underground Facilities
- EU Sandbox 2
4x Art devs working on 24 tasks (769% load) thru 2023-09-24
3x Design devs working on 18 tasks (769% load) thru 2023-09-24
4x Art devs working on 24 tasks (769% load) thru 2023-09-24
3x Design devs working on 18 tasks (769% load) thru 2023-09-24
=====...................======..................=====...................==|==...........................
=====...................======..................=====...................==|==...........................
- Location Concept Art
5x Art devs working on 30 tasks (115% load) thru 2023-09-28
5x Art devs working on 30 tasks (115% load) thru 2023-09-28
====================~~~~~~~~====================....======================|===..........................
- MTL Sandbox 1
7x Art devs working on 47 tasks (32% load) thru 2023-12-14
3x Design devs working on 29 tasks (45% load) thru 2023-12-14
7x Art devs working on 47 tasks (32% load) thru 2023-12-14
3x Design devs working on 29 tasks (45% load) thru 2023-12-14
==============================.===============~~~~~~======================|=========================....
==============================.===============~~~~~~======================|=========================....
Vehicle Tractor Beams
(Scheduled work ending soon!)
- Narrative
1x Design dev working on 6 tasks (115% load) thru 2023-09-28
1x Design dev working on 6 tasks (115% load) thru 2023-09-28
................=========...........................======================|===..........................
Weapon Misfire & Wear
- Weapon Content Team
1x Animation dev working on 6 tasks (556% load) thru 2023-09-28
1x Animation dev working on 6 tasks (556% load) thru 2023-09-28
......................==~~~~..............................................|.............................
..............................................============..............==|===..........................
- Weapon Feature Team
3x Engineering devs working on 21 tasks (41% load) thru 2023-10-14
3x Engineering devs working on 21 tasks (41% load) thru 2023-10-14
==============================.=========================.=================|=========....................
The following deliverables are scheduled to begin (or continue) work within two weeks
Artificial Gravity
- EU PU Gameplay Feature Team
1x Engineering dev will work on 8 tasks (215% load) starting 2023-09-21 thru 2023-10-22
1x Engineering dev will work on 8 tasks (215% load) starting 2023-09-21 thru 2023-10-22
....................................................~~~~~~~~~~~~~.........|~~~~~~~~~~...................
Life Support T0
- EU PU Gameplay Feature Team
1x Engineering dev will work on 8 tasks (215% load) starting 2023-09-21 thru 2023-10-22
1x Engineering dev will work on 8 tasks (215% load) starting 2023-09-21 thru 2023-10-22
....................................................~~~~~~~~~~~~~.........|~~~~~~~~~~...................
New Missions - Data Heist
- Mission Feature Team
2x Design devs will work on 7 tasks (130% load) starting 2023-09-21 thru 2023-11-05
2x Design devs will work on 7 tasks (130% load) starting 2023-09-21 thru 2023-11-05
........................=================...========================......|==============...............
New Missions - Restoration Contracts
- Mission Feature Team
2x Design devs will work on 7 tasks (130% load) starting 2023-09-21 thru 2023-11-05
2x Design devs will work on 7 tasks (130% load) starting 2023-09-21 thru 2023-11-05
..................................................==================......|==============...............
New Missions - Steal/Recover Cargo
- Mission Feature Team
1x Engineering dev will work on 7 tasks (259% load) starting 2023-09-21 thru 2023-11-05
1x Engineering dev will work on 7 tasks (259% load) starting 2023-09-21 thru 2023-11-05
..........................................................................|==============...............
Origin G12
(Starting soon!)
- Vehicle Content - EU
2x Art devs will work on 12 tasks (135% load) starting 2023-10-01 thru 2023-12-14
1x Design dev will work on 11 tasks (248% load) starting 2023-10-01 thru 2023-12-14
2x Art devs will work on 12 tasks (135% load) starting 2023-10-01 thru 2023-12-14
1x Design dev will work on 11 tasks (248% load) starting 2023-10-01 thru 2023-12-14
..........................................................................|...======================....
..........................................................................|...======================....
Reputation - Hostility
- Mission Feature Team
1x Engineering dev will work on 7 tasks (259% load) starting 2023-09-21 thru 2023-11-05
1x Engineering dev will work on 7 tasks (259% load) starting 2023-09-21 thru 2023-11-05
..................................................==================......|==============...............
RSI Polaris
- Vehicle Content - EU
8x Art devs will work on 13 tasks (37% load) starting 2023-10-01 thru 2023-12-14
1x Design dev will work on 11 tasks (248% load) starting 2023-10-01 thru 2023-12-14
8x Art devs will work on 13 tasks (37% load) starting 2023-10-01 thru 2023-12-14
1x Design dev will work on 11 tasks (248% load) starting 2023-10-01 thru 2023-12-14
..........................======================....======================|...======================....
..........................................................................|...======================....
Security Network V1
- Mission Feature Team
2x Engineering devs will work on 5 tasks (102% load) starting 2023-09-25 thru 2023-11-05
2x Engineering devs will work on 5 tasks (102% load) starting 2023-09-25 thru 2023-11-05
..........................................................................|.=============...............
Unannounced Vehicle
- Vehicle Content - EU
4x Art devs will work on 4 tasks (93% load) starting 2023-10-01 thru 2023-10-19
4x Art devs will work on 4 tasks (93% load) starting 2023-10-01 thru 2023-10-19
................======....======================....======================|...======....................