Progress Tracker Delta
578 deliverables listed | 2025-09-23 => 2025-09-29
There were 8 modifications, 0 removals, and 0 additions in this update. Please note that not all removals are intentional; there is currently a bug with how time is entered on the Progress Tracker that can cause deliverables to disappear.
extra analysis (click me)
There are 6 assignments scheduled to work on 6 observable deliverables. Of those deliverables, 0% are for SQ42 exclusively. 0% of deliverables are shared between both projects.
On average, the schedule has expanded by 24 days.
The top currently scheduled tasks (in estimated man-days) are:
- 88 - Transport Refactor (full-time)

- 62 - Command Module (full-time)

- 39 - REDACTED Creature (full-time)

- 39 - FPS Radar / Scanning (100% part-time)


- 38 - Inventory Rework (full-time)

- 29 - Engineering (100% part-time)

The top currently scheduled tasks (in assigned devs) are:
- 1 - REDACTED Creature (full-time)

- 1 - Command Module (full-time)

- 1 - Inventory Rework (full-time)

- 1 - Transport Refactor (full-time)

- 1 - Engineering (100% part-time)

- 1 - FPS Radar / Scanning (100% part-time)


[8] deliverable(s) updated:
Command Module 
2025-08-10 => 2026-02-12
- End date has been extended from 2025-12-11 to 2026-02-12
- SC & SQ42 - Core Gameplay Pillar added 63 days of work
xDeveloper with 1 tasks (14% => 9% load)
Crafting 
2023-12-31 => 2025-12-11
- SC & SQ42 - Core Gameplay Pillar freed up 73 days of work
Engineering 
2023-12-31 => 2025-10-23
- End date has been extended from 2025-09-29 to 2025-10-23
FPS Radar / Scanning 

2021-01-03 => 2025-12-11
- End date has been extended from 2025-09-29 to 2025-12-11
Inventory Rework 
2025-06-30 => 2025-10-23
- End date has been extended from 2025-09-29 to 2025-10-23
Item Expiry 
2025-05-11 => 2025-08-14
- SC & SQ42 - Core Gameplay Pillar freed up 46 days of work
REDACTED Sandbox Activity 
2024-12-05 => 2025-03-26
- Start date has been corrected from 2025-01-31 to 2024-12-05
- End date has moved earlier (time allocation removal(s) or priority up likely)
from 2025-06-05 to 2025-03-26
Transport Refactor 
2025-02-02 => 2025-10-23
- End date has been extended from 2025-10-16 to 2025-10-23
- SC & SQ42 - Core Gameplay Pillar added 7 days of work
xDeveloper with 1 tasks (7% => 6% load)